<?xml version="1.0" encoding="utf-8"?><rss version="2.0" xmlns:atom="http://www.w3.org/2005/Atom"><channel><title>Metro - File #: 2016-0097</title><link>https://metro.legistar.com/Gateway.aspx?M=LD&amp;From=RSS&amp;ID=2575216&amp;GUID=6ADA850D-3CFF-4BB9-8130-E8E7BDFF6C3F&amp;G=A5FAA737-A54D-4A6C-B1E8-FF70F765FA94</link><description /><generator>Legistar</generator><ttl>15</ttl><atom:link href="https://metro.legistar.com/Feed.ashx?G=A5FAA737-A54D-4A6C-B1E8-FF70F765FA94&amp;GUID=6ADA850D-3CFF-4BB9-8130-E8E7BDFF6C3F&amp;ID=2575216&amp;M=LD" rel="self" type="application/atom+xml" /><item><title>Metro - File #: 2016-0097</title><link>https://metro.legistar.com/Gateway.aspx?M=LD&amp;From=RSS&amp;ID=2575216&amp;GUID=6ADA850D-3CFF-4BB9-8130-E8E7BDFF6C3F&amp;G=A5FAA737-A54D-4A6C-B1E8-FF70F765FA94</link><guid isPermaLink="false">6ADA850D-3CFF-4BB9-8130-E8E7BDFF6C3F-2025-06-09-05-08-24</guid><description>Title: CONSIDER:

A.	APPROVE the staff recommendation to increase Life of Project (LOP) Budget by $5,000,000 from $2,773,879,593 to $2,778,879,593 for the Westside Purple Line Extension Section 1 Project, No. 865518.

B.	AUTHORIZE the CEO to negotiate and execute Contract Modification No. 1 to Contract C1078, Clark Construction Group to incorporate design direction based on Alternative A1, to revise the Baseline design of the building floor plans and site plan, in an amount not-to-exceed $4,500,000 increasing the total contract price from $52,830,310 to $57,330,310.

C.	AUTHORIZE the CEO to negotiate with the City to allow as-needed access through the MOW site for maintenance vehicles to service the electric and sewer vaults in the 6th Street Viaduct right of way.</description><pubDate>Mon, 09 Jun 2025 05:08:24 GMT</pubDate></item></channel></rss>