File #: 2015-1255   
Type: Informational Report Status: Filed
File created: 8/7/2015 In control: Planning and Programming Committee
On agenda: 2/17/2016 Final action: 2/17/2016
Title: RECEIVE AND FILE report in response to the Metro Board July 23, 2015 directive to provide bi-monthly updates on the Eastside Transit Corridor Phase 2 Technical Study and Community Outreach.
Sponsors: Planning and Development (Department)
Indexes: Alignment, Alternatives analysis, Board approved Contract, Environmental Impact Report, Environmental impact statements, Gold Line Eastside Transit Corridor Phase 2, Informational Report, Metro Gold Line, Metro Rail E Line, Metro Rail L Line, Outreach, Project, Schedules and scheduling, SR-60, Surveys, West Santa Ana Branch Transit Corridor, West Santa Ana Branch Transit Corridor (WSAB) Project
Attachments: 1. Attachment A - July Board Motion, 2. Attachment B - Map of North-South Alignment Concepts for Washington Blvd.pdf, 3. Attachment C - Project Schedule
Meeting_Body
PLANNING AND PROGRAMMING COMMITTEE
FEBRUARY 17, 2016


Subject/Action
SUBJECT: EASTSIDE PHASE 2 UPDATE (OPERATION SHOVEL READY)

ACTION: RECEIVE AND FILE

Heading
RECOMMENDATION

Title
RECEIVE AND FILE report in response to the Metro Board July 23, 2015 directive to provide bi-monthly updates on the Eastside Transit Corridor Phase 2 Technical Study and Community Outreach.

Issue
ISSUE

In November 2014, the Board received the Eastside Transit Corridor Phase 2 Draft Environmental Impact Statement/Report (EIS/EIR) and approved carrying forward two build alternatives, the SR 60 North Side Design Variation (NSDV) and the Washington Boulevard Alternatives into further study. Staff was directed to address comments received from Cooperating and Public Agencies, identify an alternative to the Washington Blvd. via Garfield Alternative and analyze the feasibility of operating both alternatives.

At the July 23, 2015 meeting, the Board approved Contract Modification No. 12 for the Metro Eastside Transit Corridor Phase 2 Project, Alternatives Analysis (AA), Environmental Clearance, and Conceptual Engineering Consultant Services to undertake this work effort and Contract Modification No. 11 for community outreach in support of the Technical Study. With the approval of the contract modifications, the Board directed staff to provide bi-monthly updates on: (1) the project's contractual scope of work and description of the task order for the technical study; (2) the project's schedule and milestones for both the technical analysis and environmental planning process for all alternatives under consideration and study; and (3) bi-monthly updates on the project's schedule, progress reports and community outreach schedule and meeting results, including concerns raised by stakeholders (Attachment A). This report provides the requested bi-monthly update in response to the Board's direction.

Discussion
DISCUSSION

Contractual Scope of ...

Click here for full text