File #: 2019-0563   
Type: Contract Status: Agenda Ready
File created: 7/18/2019 In control: Construction Committee
On agenda: 9/19/2019 Final action:
Title: AUTHORIZE Contract Modifications No. 102 & No. 103 (CCO 102 & CCO 103) by the California Department of Transportation (Caltrans) for the construction contract for Segment 3 (Shoemaker, Bloomfield and Rosecrans) of the I-5 South Capacity Enhancements Project from Orange County Line to I-605 (Project) under FUNDING AGREEMENT NO. MOU.P0004292 A/A3, in the total amount of $5.03 million within the LOP budget.
Sponsors: Construction Committee
Indexes: "Hot Spots" Program, Budget, Budgeting, Construction, Contractors, Contracts, High occupancy vehicle lanes, I-5, I-5 S 605 To Oc - Florence Ave Interchange (Project), I-5 S 605 To Oc -Imperial Hwy/Orr & Day Rd (Project), I-5 S 605 To Oc- Shoemaker-Rosecrans-Bloomfield (Project), I-5 S 605 To Oc- Valley View Ave Interchange (Project), I-605, Interchanges, Labor, Measure R, Metro Orange Line, Metrolink Orange County Line, Norwalk, Payment, Pedestrians, Project, Proposition C, Southern California Highways, Subcontractors, Subsidies
Related files: 2019-0755
Meeting_Body
CONSTRUCTION COMMITTEE
SEPTEMBER 19, 2019

Subject
SUBJECT: I-5 SOUTH CAPACITY ENHANCEMENTS FROM ORANGE COUNTY LINE TO I-605

Action
ACTION: APPROVE RECOMMENDATION

Heading
RECOMMENDATION

Title
AUTHORIZE Contract Modifications No. 102 & No. 103 (CCO 102 & CCO 103) by the California Department of Transportation (Caltrans) for the construction contract for Segment 3 (Shoemaker, Bloomfield and Rosecrans) of the I-5 South Capacity Enhancements Project from Orange County Line to I-605 (Project) under FUNDING AGREEMENT NO. MOU.P0004292 A/A3, in the total amount of $5.03 million within the LOP budget.

Issue
ISSUE

The construction contract for Segment 3 of I-5 South Capacity Enhancements from 0.1 Mile North of Carmenita Road Overcrossing to 0.1 Mile North of Silverbow Avenue Pedestrian Overcrossing was awarded on August 14, 2012. Project completion and Caltrans' acceptance is expected in Fall 2019.

The Project encountered a number of problems including relocation of conflicting unidentified utilities, disposal of unidentified contaminated material, third party delays, community concerns resulting in additional out of scope work, and other issues resulting in claims totaling $7.42 million.

Caltrans and the contractor have agreed to the final amount of $5.03 million to settle all claims listed to-date.

Contract modifications exceeding $500,000 require Board authorization.

Background
BACKGROUND

The Project includes widening/upgrading of I-5 and inclusion of High Occupancy Vehicle (HOV) lanes between Orange County Line and I-605. Caltrans designed and managed construction of the Project comprising of five segments and Carmenita Interchange. Carmenita Interchange, Segment 1 and 3 are complete. Segments 2, 4, and 5 are currently under construction. Total life of project budget for the combined five segments and Carmenita Interchange is $1.888 billion, which includes $188.216 million for Segment 3. Additional items of work outside the original ...