File #: 2019-0829   
Type: Contract Status: Consent Calendar
File created: 12/10/2019 In control: Board of Directors - Regular Board Meeting
On agenda: 1/23/2020 Final action:
Title: AUTHORIZE Contract Modification No. 235 (CCO 235) by the California Department of Transportation (Caltrans) for the construction contract for Segment 3 (Empire) of I-5 North Capacity Enhancements Project between SR-134 and SR-118 (Project) in the amount not to exceed $1.5 M under Funding Agreement No. MOU. P0008355/8501A/A9 within the LOP budget.
Sponsors: Construction Committee
Indexes: Air Quality Management District, Arroyo Verdugo subregion, Budget, Budgeting, Burbank, Construction, Contractors, Contracts, High occupancy vehicle lanes, I-5, I-5 N Hov Lanes Sr-134 To Sr-118 - Segment 2 (Sr-170 To Buena Vista) (Project), I-5 N Hov Lanes Sr-134 To Sr-118 - Segment 3 (Buena Vista To Magnolia) (Project), I-5 N Hov Lanes Sr-134 To Sr-118 - Segment 4 (Magnolia To Sr-134) (Project), I-5 North Corridor, I-5 North County Capacity Enhancements, Measure R, Project, Proposition C, Regional Surface Transportation Program, San Fernando Valley Service Sector, San Fernando Valley subregion, Southern California Highways, SR-118, SR-134, Subsidies
Meeting_Body
CONSTRUCTION COMMITTEE
JANUARY 16, 2020

Subject
SUBJECT: I-5 NORTH CAPACITY ENHANCEMENTS FROM SR- 118
TO SR-134; SEGMENT 3

Action
ACTION: APPROVE RECOMMENDATION

Heading
RECOMMENDATION

Title
AUTHORIZE Contract Modification No. 235 (CCO 235) by the California Department of Transportation (Caltrans) for the construction contract for Segment 3 (Empire) of I-5 North Capacity Enhancements Project between SR-134 and SR-118 (Project) in the amount not to exceed $1.5 M under Funding Agreement No. MOU. P0008355/8501A/A9 within the LOP budget.

Issue
ISSUE

The construction contract for Segment 3 between West Magnolia Boulevard Overcrossing and 0.3 mile North of Buena Vista Street/Winona Avenue Undercrossing was awarded on November 29, 2012. Empire Avenue Interchange in Burbank was open to traffic on September 30, 2019, and the removal and reconstruction of Burbank Bridge is scheduled to start in February 2020.

Eight abandoned 5-inch conduits for a total length of 5600 feet, owned by the City of Burbank for power transmission across the existing Burbank Bridge tested positive for asbestos.
.
The conduits are in the way of new Burbank bridge reconstruction and need to be abated as part of the removal of the Burbank bridge per the requirements of Air Quality Management District (AQMD). Each conduit is about 50 feet embedded in solid concrete bridge deck, 150 feet inside the existing bridge box girder, and 500 feet buried underneath the existing roadway on both sides of the bridge.

CCO 235 authorizes up to $1.5 million for the abatement of the referenced conduits. Contract modifications exceeding $500,000 require Board authorization per the Staff Delegations.


Background
BACKGROUND

Segment 3 (Empire), part of the I-5 North widening project, is about 80% complete. The I-5 North construction project was initiated by Caltrans in four segments. Segments 1 and 2 between North of Buena Vista Street/Winona Avenue Undercrossing and SR-118 are com...