File #: 2021-0101   
Type: Contract Status: Passed
File created: 3/2/2021 In control: Board of Directors - Regular Board Meeting
On agenda: 5/27/2021 Final action: 5/27/2021
Title: AUTHORIZE the Chief Executive Officer (CEO) to execute Modification No. 18 to Contract No. AE58083E0129 with Gannet Fleming, Inc. for the East San Fernando Valley Transit Corridor Project, for geotechnical exploration along Van Nuys Blvd. (Oxnard St. to San Fernando Rd.), in the amount of $987,531 increasing the total Contract value from $71,062,041 to $72,049,572.
Sponsors: Construction Committee
Indexes: Alternatives Analysis study approved by the Board, Board approved Locally Preferred Alternative, Budgeting, Construction, Contracts, Design build, East San Fernando Valley Light Rail Project, East San Fernando Valley Transit Corridor, Environmental Impact Report, Light rail transit, Metrolink, Plan, Procurement, Professional Services, Program Management, Project, Project management, Record Of Decision, San Fernando, San Fernando Valley Service Sector, San Fernando Valley subregion, Testing, Van Nuys
Attachments: 1. Attachment A: Procurement Summary, 2. Attachment B: Contract Modification / Change Order Log, 3. Attachment C - DEOD Summary
Related files: 2021-0440

Meeting_Body

CONSTRUCTION COMMITTEE

MAY 20, 2021

 

Subject

SUBJECT:                     EAST SAN FERNANDO VALLEY LIGHT RAIL TRANSIT - GEOTECHNICAL EXPLORATION

 

Action

ACTION:                     AUTHORIZE CONTRACT MODIFICATION FOR GEOTECHNICAL EXPLORATION ALONG VAN NUYS BLVD (OXNARD ST TO SAN FERNANDO RD)

 

Heading

RECOMMENDATION

 

Title

AUTHORIZE the Chief Executive Officer (CEO) to execute Modification No. 18 to Contract No. AE58083E0129 with Gannet Fleming, Inc. for the East San Fernando Valley Transit Corridor Project, for geotechnical exploration along Van Nuys Blvd. (Oxnard St. to San Fernando Rd.), in the amount of $987,531 increasing the total Contract value from $71,062,041  to $72,049,572.

 

 

Background

BACKGROUND

 

The East San Fernando Valley (ESFV) Light Rail Transit Project (Project) is a light rail system that will extend north from the Van Nuys Metro Orange Line station to the Sylmar/San Fernando Metrolink Station, a total of 9.2 miles with 14 at-grade stations. Light rail trains will operate in the median of Van Nuys Boulevard for 6.7 miles to San Fernando Road. From there, the tracks will transition onto existing Metro right-of-way and follow a shared corridor with Metrolink and freight for 2.5 miles to the Sylmar/San Fernando Metrolink Station.

 

On June 28, 2018, the Metro Board approved the Locally Preferred Alternative (LPA) as Alternative 4: Light Rail Transit (LRT). The Final Environmental Impact Statement (EIS) / Environmental Impact Report (EIR) were presented to the Metro Board in December 2020. At that time, the Board certified the document followed by a Record of Decision (ROD) in January 2021 by the FTA.

 

 

Issue

ISSUE

 

The recommended Contract Modification includes geotechnical exploration along Van Nuys Blvd. based upon the Metro approved Subsurface Exploration and Testing Plan that includes geotechnical field borings, pavement corings, laboratory testing and documenting within a geotechnical data report and geotechnical design reports. Gannett Fleming, Inc., the ESFV Engineering Consultant for Metro, will conduct this exploration work as part of their Phase 1 work to advance the design for incorporation into the design build procurement documents.

 

Geotechnical exploration will provide additional information to address a major risk in any new rail project. The design of Project components, such as track, station platforms, maintenance facility, walls and pavement improvements, require geotechnical input in addition to the evaluation of the impacts on existing structures along the proposed alignment. This approach has proven to be a lesson learned and best practice on Metro projects. This action will greatly assist in mitigating risk.

 

 

Discussion

DISCUSSION

 

In 2019, Metro awarded to Gannett Fleming, Inc. a cost plus fixed fee (CPFF) contract for Architecture Engineer (AE) services to advance the design for incorporation into the design build procurement documents (Phase 1), support during the solicitation process (Phase 2) and design support during construction (Phase 3) for the Project. As part of Phase 1 scope of work, Gannett Fleming assembled existing geotechnical data for the Project and complied this information into a Geotechnical Planning Report that Metro reviewed and approved. Based upon this report, Gannett Fleming prepared a detailed Subsurface Exploration and Testing Plan outlining the required locations and quantity of geotechnical field borings, pavement corings, and laboratory testing to support the design of the Project components; Metro reviewed and approved this Plan. The geotechnical investigation is based upon this Plan and will consist of field investigation work at specific locations along Van Nuys Blvd.

 

For this geotechnical investigation work, the locations and quantities do not warrant the necessity to segment the work as done on previous contract modifications as this work is isolated to specific locations located throughout the 6.7 miles of Van Nuys Blvd. Therefore, this contract modification can be managed with this approach. 

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

This Board action will not have an adverse impact on safety standards for Metro. 

 

Financial_Impact

FINANCIAL IMPACT

 

This Project is funded on a fiscal year basis under Project number 865521 East San Fernando Valley Transit Corridor, cost center 8510, under various accounts including Professional/Technical Services and $45.2M is included in the FY21 Adopted Budget. This is a multi-year project requiring expenditure authorizations in fiscal year increments until a Board Authorized Life of Project Budget is adopted. It is the responsibility of the Cost Center Manager, Project Manager and Chief Program Management Officer to budget for this project in the future fiscal years and within the cumulative budget limit for the affected fiscal year.

 

Impact to Budget

 

Sources of funds for the recommended actions are Measure M 35% and State Grants. There is no impact to Operations eligible funding. No other funds were considered.

 

Alternatives Considered

ALTERNATIVES CONSIDERED

 

The Metro Board could decide not to approve this contract modification.  Staff does not recommend this alternative because this geotechnical investigation work is necessary for Gannett Fleming to develop a thorough design and procurement documents that the Design Build contractors may rely on and thus reduce risk.

 

Next_Steps

NEXT STEPS

 

Upon Metro Board adoption, staff will complete negotiations and execute the contract modifications.

 

 

Attachments

ATTACHMENTS

 

Attachment A: Procurement Summary

Attachment B: Contract Modification / Change Order Log

Attachment C: DEOD Summary

 

Prepared by:                      Monica Born, Deputy Executive Officer, Program Management, (213) 418-3097

 

                     Rick Meade, Senior Executive Officer, (213) 922-7917

 

 

Reviewed by:                      

Bryan Pennington, Interim Chief Program Management Officer, (213) 922-7449

 

Debra Avila, Chief Vendor / Contract Management Officer, (213) 418-3051