File #: 2021-0119   
Type: Program Status: Passed
File created: 3/9/2021 In control: Board of Directors - Regular Board Meeting
On agenda: 5/27/2021 Final action: 5/27/2021
Title: AUTHORIZE: A. An increase to the total authorized funding for Contract No. PS54007 with PQM, Inc, for pending and future Task Orders to provide Quality Management Consulting services in the amount of $19,947,286 increasing the authorized funding limit from $5,378,518 to $25,325,804 through FY22 and FY23; and B. The Chief Executive Officer or their designee to execute individual Task Orders and Contract Modifications changes within the Board approved funding limit.
Sponsors: Construction Committee
Indexes: Audit, Budgeting, Capital Project, Capital Project Funds, Construction, Construction management, Contractors, Contracts, Databases, Measure M, Measure R, Metro Rail D Line, Metro Vision 2028 Plan, Procurement, Professional Services, Program, Program Management, Project, Project delivery, Project management, Steering, Twenty-eight by '28 Initiative, Westside Subway Extension/Purple Line Extension Phase 1, Westside Subway Extension/Purple Line Extension Phase 2, Westside Subway Extension/Purple Line Extension Phase 3
Attachments: 1. Attachment A - Procurement Summary, 2. Attachment B - Contract Task Order Modification Log, 3. Attachment C - DEOD Summary, 4. Attachment D - QMO Best Practice Initiative
Related files: 2021-0440

Meeting_Body

CONSTRUCTION COMMITTEE

MAY 20, 2021

 

 

Subject

SUBJECT:                     QUALITY MANAGEMENT CONSULTANT

 

Action

ACTION:                     APPROVE RECOMMENDATIONS

 

Heading

RECOMMENDATION

 

Title

AUTHORIZE:

 

A.                     An increase to the total authorized funding for Contract No. PS54007 with PQM, Inc, for pending and future Task Orders to provide Quality Management Consulting services in the amount of $19,947,286 increasing the authorized funding limit from $5,378,518 to $25,325,804 through FY22 and FY23; and

 

B.                     The Chief Executive Officer or their designee to execute individual Task Orders and Contract Modifications changes within the Board approved funding limit.

 

Issue

ISSUE

 

In 2019, the Board approved awarding a seven-year (plus three (3) one-year options), cost plus fixed fee Contract No. PS54007 to PQM, Inc, to provide Quality Management Consultant Services that assist Metro in the delivery of voter approved Measures R, M, and other Board approved Capital Improvement projects.

 

The primary objective of the Quality Management Consultant is to implement Metro’s Quality Management Oversight (QMO) Program which is a risk-based management oversight program to monitor Metro's consultants' and contractors' activities and performance throughout project delivery.  Monitoring activities include the implementation of management plans as well as design and construction work products. The QMO program provides Metro with a more consistent, effective way for project teams to oversee and manage their Capital Improvement projects. The QMO Program is a key component to Metro’s improved Quality Management System which is in the process of seeking ISO 9001: 2015 registration. 

 

The QMO Program approach can be utilized by Metro in areas in addition to quality, it can be used in any business area that has requirements, processes, and deliverables, both for internal and external stakeholders. This initiative is part of Metro’s Best Practices report, please see Attachment D. 

The recommended action will provide funding authority for Task Orders (TO) during the next 24 months, FYs 2022 and 2023. This funding request is in anticipation of continued support of Westside Purple Line Extension Sections 2 & 3 and an additional 9 projects during FY22 and FY23.  Life of Project budgets currently include funding for quality oversight, this request is to allow those funds to be utilized within Contract No. PS54007.

 

Staff intends to return to the Board in two years to request necessary funding authorization as the implemented Quality Management Oversight program matures and is applied to future projects.

 

 

Background

BACKGROUND

 

Over the past 24 months, the Program Management Department, with the support and expertise of the Quality Management Consultant, has begun to implement an improved Quality Management System to support the delivery of Measures R & M projects more effectively.  The improvements include a Quality Management Oversight (QMO) Program which has documented processes and procedures to assist Metro with overseeing the work of contractors delivering projects.  The QMO Program is a systemized, risk-based approach that verifies that contractors are meeting contract requirements.  Westside Purple Line Extension Sections 2 & 3 began implementing the QMO Program 14 months ago. Currently 60% of the QMO Program procedures are being utilized on these projects, and the results of the program have been favorable for Metro and well received by the contractors. 

 

The Quality Management Department has completed a gap analysis which identifies the gaps in the current Quality Management System as compared to the ISO 9001: 2015 standard.  The results from this report have been the topics of Quality Management Committee Meetings which focus on the best options for closing these gaps.  The Program Management Department, based on the results of the committee meetings, has determined that the most effective way for Metro to oversee projects is by implementing the QMO Program on all capital improvement projects, excluding small, low risk projects. 

 

The Quality Management Department has also completed a thorough review and revision of all quality related contract documents to ensure consistency in language and references within the procurement documents.  This exercise was done to ensure that potential contractors are clear on Metro’s policy for managing quality and that the results of their performance will be transparent to all project stakeholders. 

 

Discussion

DISCUSSION

 

Metro is currently undertaking the largest transportation construction program in the nation.  Recognizing that a consistent application of oversight is key to effective project delivery, Metro has implemented a systemized approach to project oversight. The Quality Management Oversight (QMO) Program, currently implemented on Westside Purple Line Extension Sections 2 & 3, has proven to provide the following benefits to Metro:

 

                     Improved confidence and accountability to project stake holders through the transparent results of performance on key design and construction activities throughout the life of the project

                     Improved communications to project participants through monthly QMO Program reports and Quarterly reviews

                     Improved productivity of staff resources, through training on the revised approach and reallocation of resources within both the quality department and project teams

                     Improved quality of contract requirements because of the review and analysis of Metro policy’s, plans, procedures, and procurement documents

 

Scope of the QMO Program

 

To support the aggressive project implementation schedule for delivering Metro’s Capital Program, Metro has implemented the QMO Program that follows the ISO 9001:2015 standard for quality management systems, and measures the contractor’s performance during design and construction of both end-products and management processes against the contract and project specific requirements, using risk-based priority planned assessments that provide evidence of conformance or non-conformance for corrective actions, and ultimately for Metro’s project teams to have the confidence to accept the work.

 

The process leverages integrated database technology with workflow capability for all project oversight participants to complete their tasks of the oversight processes. The data is collected and analyzed for identifying trends and key performance outcomes reviewed by the project teams and included in the QMO Program monthly reports. Quarterly quality management reviews are also conducted on each project and the program to review the contractor performance status and trends, identify lessons learned, and determine actions. The QMO Database also has a Lessons Learned module that provides increased effectiveness and efficiency to Metro’s lessons learned program, to formally capture, report, and disseminate lessons, and implement improvement actions to the benefit of future projects.

 

The Quality Management Department is working toward the ISO 9001: 2015 registration for the capital program projects. This effort follows a plan, schedule, and progress tracking.  An ISO Steering Committee has been established to lead this effort through to registration. 

 

Continued implementation of the QMO Program on current and newly added projects is the primary focus over the next two years. Metro plans to award multiple major capital improvement projects in FY22 and FY23, most of which will utilize the QMO Program.  Contract funds are authorized by issuing separate TOs for various projects using labor classifications and rates set forth in the contract, with funding solely supported through the Life of Project budgets.  This method of contracting results in more efficient cost and schedule management, since TOs and modifications to existing TOs are negotiated and issued as additional work is identified. For each TO or modification, Metro prepares a scope of work and an estimate of hours, and PQM subsequently provides a proposal.

 

Results of this scope of work are expected to include tangible and intangible savings such as:

                     Fewer resources are required to perform construction inspection activities (construction assessments) as a result of using risk-based sampling and priority planning that is effective by focusing more on higher risk activities

                     The implementation of Final Acceptance and use of the Acceptance Dashboard of the QMO Database, enables a very efficient means of progressive closeout as the work is completed. This results in fewer FTEs required for project closeout

                     Efficiencies in the execution of oversight activities are realized through the implementation of the user-based workflow of QMO Database. This provides a systemized way of retrieving and extracting data, communicating with project stakeholders, and tracking project issues

                     A pro-active method is used to use the collected performance measurement data and perform data analysis to identify trends in performance and systemic issues. This, and the resulting feedback to the contractors, facilitates a greater focus on continuous improvement and preventative actions, leading to less rework (Research in 2005 by the Construction Industry Institute reveals that direct costs caused by rework average 5% of total construction costs)

                     The assessments are based on requirements, and include the objective evidence of the work either conforming or nonconforming to the requirements. This provides a fair, objective, and defensible means of oversight, which can result in less conflict and potential claims.

 

 

Consultant Services

 

The scope of services being provided by the PQM includes, but is not limited to, the continued development and implementation of an ISO 9001: 2015 based QMO Program which is led by quality management subject matter experts with decades of experience in applying this proven oversight approach to transportation capital programs and mega-projects. Consultant team members are integrated into Metro’s Quality Management Department and work with senior management and executive staff from Metro’s capital program and project teams to implement the QMO Program. They provide expertise, guidance, and training, and are transferring knowledge to Metro. They participate and are often responsible for QMO Program activities at the project level. The consultant is responsible for supporting the Metro project teams in the implementation of the QMO Program and conducts internal audits of that effort to identify opportunities to implement improvements.  Other activities include:

 

                     Project level management system audits and process assessments of the project contractors

                     Coordination of design and construction assessments performed by the project team’s engineering and field staff

                     Quality improvement methodologies to support continuous improvement of Metro’s Quality Management System

                     Reviews of technical documents for upcoming projects; partnering with project teams in the planning phase to ensure technical documents have consistent language reflecting Metro’s quality management requirements

                     Preparation for registering Metro’s quality management system to the ISO 9001: 2015 standard; this includes a program registration plan, ISO 9001: 2015 and leading an active steering committee

                     Implementing the QMO Program training and communications plan, developing content for both live training (virtual now and later resuming in-person), and web-based training modules.

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

The Board action will not have any adverse safety impacts on Metro’s Construction projects, Operations, our employees, and/or patrons.

 

Financial_Impact

FINANCIAL IMPACT

 

The recommended amount of $19,947,286 is based on the anticipated level of services for the term. A scope of work for each fiscal year is developed for overall QMO Program project level activities.  Fiscal year 2022 portion for these services are included within the impacted projects’ proposed budget for FY22.    Since this is a multiyear program, the program manager, respective project managers and Chief Program Management Officer are responsible for budgeting in future year.  The issued project level TOs are funded by the life-of-project (LOP) budgets that are approved by the Board.  

 

A portion of the contract scope of services will require an annual budget allotment for program-wide quality oversight elements and activities to be funded through an annual overhead fund. A scope of services for each fiscal year is developed for overall QMO Program level activities, for which a TO is issued.

 

It is anticipated that the overhead allotment for the QMO Program will be offset by cost savings resulting from a reduction of engineering and construction management consultant staff resources on the projects. This is due to the implementation of the risk-based priority planning and sampling methods, progressive acceptance and related accelerated project closeout, and the efficiencies of executing the oversight activities through the integrated QMO database that all project participants use to execute their role in the processes. These savings are augmented with mitigations of potential claims, rework, and scope creep, that is achieved through the defensible requirements-based approach to oversight that places a greater focus on activities with higher risk and overall continuous improvements on the projects.

 

Aside from the annual overhead allotment, the recommendations for this item have no financial impacts beyond what the Board authorizes through the life-of-project (LOP) budgets. 

 

Impact to Budget

 

Funding for QMO Program project specific TOs issued under this action will be provided by the specific project benefiting from the services. The sources for these funds are from the respective projects’ funding plans and may consist of federal and/or state grants as well as local funds. Many state-of-good-repair and capital improvement projects are funded with local funding sources that are eligible for rail and bus operations.

.

 

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

Recommendation supports Strategic Plan Goals #1 and #5 and is also a Metro Best Practice Initiative.

 

Goal # 1 - Provide high-quality mobility options that enable people to spend less time traveling.

 

Goal # 5 - Provide responsive, accountable, and trustworthy governance within the Metro organization.  Specifically, 5.4 which states “Metro will apply prudent commercial business practices to create a more effective agency.”

 

This will be accomplished through the implementation of a consistent, ISO 9001: 2015 compliant approach to quality management across projects which creates transparency of oversight efforts, accountability of the contractor’s responsibilities, efficiencies, and increased effectiveness of project teams in the delivery of Measures R & M projects. 

 

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

The Board may reject the funding authorization. Staff does not recommend this alternative.  Due to the length of time needed to deliver major capital improvement projects, it is very inefficient and disruptive to change the consultant during project delivery. The authorization of approved contract funds will allow for PQM to continue the work that has progressed over the past 26 months without disruption.  The use of PQM has allowed the agency to secure highly technical expertise without increases in Metro long term labor costs. By limiting funding to two years, greater accuracy of project scope and cost requirements can be provided to the Board every two years

 

 

Next_Steps

NEXT STEPS

 

Upon Board approval, staff will extend the TOs for Program Level QMC Support Services, Westside PLE 2&3 and execute TOs as needed for AMC, LINK US, Sepulveda PDA, East San Fernando Valley, and other projects that may fall within the approved timeframe.

 

Attachments

ATTACHMENTS

 

Attachment A - Procurement Summary

Attachment B - Task Order Summary

Attachment C - DEOD Summary

Attachment D - QMO Best Practice Initiative

 

Prepared_by

Prepared by:                      

 

Herman Gallardo, Sr. Director Quality Management (410-336-7003)

Camelia Davis, Deputy Executive Officer Quality Management

(213-210-7086)

 

 

Reviewed_By

Reviewed by:                      

 

Bryan Pennington, Interim Chief Program Management Officer (213) 922-7449

Debra Avila, Chief Vendor/Contract Management Officer (213) 418-3051