File #: 2021-0712   
Type: Program Status: Passed
File created: 10/26/2021 In control: Board of Directors - Regular Board Meeting
On agenda: 1/27/2022 Final action: 1/27/2022
Title: CONSIDER: A. APPROVING $103,609,000 in additional programming within the capacity of the Measure R Highway Subregional Programs and funding changes via the updated project list shown in Attachment A for: * I-405, I-110, I-105, SR-91 Interchange Improvements (South Bay) * I-605 Corridor "Hot Spots" Interchange Improvements in Gateway Cities * I-710 South Local Streets and Community-Benefiting Early action projects in Gateway Cities. B. APPROVING deobligation of $250,000 of previously approved Measure R Highway Subregional Program funds for re-allocation to the MR306.05 - I-710 Integrated Corridor Management project. C. AUTHORIZE the CEO or designee to negotiate and execute all necessary agreements for the Board-approved projects.
Sponsors: Planning and Programming Committee
Indexes: "Hot Spots" Program, 405 110 105 Sr91 Ramp&Interch (Project), Agreements, Budget, Budgeting, Construction, Eb Sr91 Atlantic Avenue /Cherry Avenue Auxiliary Lane Improvement (Project), Gateway Cities (Southeast LA County) Service Sector, Gateway Cities subregion, Grant Aid, Highway Operational Improvements In Arroyo Verdugo Subregion (Project), Highway planning, Hwy Opr Imp Virgenes/Malibu (Project), I-105, I-110, I-405, I-5, I-605, I-605 Beverly Interchange Imp (Project), I-605 Corridor "Hot Spot" (Project), I-605 Hot Spots- Wb (Westbound) Sr-91 Improvements From Alondra To Shoemaker (Project), I-605 South St Interchnge Imp (Project), I-605/Sr-60 Interchange Improvements (Project), I-605/Valley Blvd Interchange Improvement Project (Project), I-710, I-710 Early Action Projects- Soundwall Package 1 (Project), I-710 Early Action Projects- Soundwall Package 2 (Project), I-710 Early Action Projects- Soundwall Package 3 (Project), I710 South Early Action Project (Project), Interchange Improvements (Project), Interchanges, Las Virgenes/Malibu subregion, Long Beach, Manhattan Beach, Measure R, Professional Services, Program, Project, Project management, Ramps (Interchanges), Safety, Senate Bill 1, South Bay Cities subregion, Southern California Highways, Sr-138 Capacity Enhancements - Additional Segments (Project), Sr-91 Acacia Court To Central Avenue Improvement Project (Project), Strategic planning, Subsidies, Union Station Gateway Improvement
Attachments: 1. Attachment A - Projects Receiving Measure R Funds
Related files: 2022-0109
Meeting_Body
PLANNING AND PROGRAMMING COMMITTEE
JANUARY 19, 2022

Subject
SUBJECT: MEASURE R HIGHWAY SUBREGIONAL PROGRAM SEMI-ANNUAL UPDATE

Action
ACTION: APPROVE RECOMMENDATIONS

Heading
RECOMMENDATION
Title
CONSIDER:

A. APPROVING $103,609,000 in additional programming within the capacity of the Measure R Highway Subregional Programs and funding changes via the updated project list shown in Attachment A for:

* I-405, I-110, I-105, SR-91 Interchange Improvements (South Bay)

* I-605 Corridor "Hot Spots" Interchange Improvements in Gateway Cities

* I-710 South Local Streets and Community-Benefiting Early action projects in Gateway Cities.

B. APPROVING deobligation of $250,000 of previously approved Measure R Highway Subregional Program funds for re-allocation to the MR306.05 - I-710 Integrated Corridor Management project.

C. AUTHORIZE the CEO or designee to negotiate and execute all necessary agreements for the Board-approved projects.

Issue
ISSUE

The Measure R Highway Subregional Program update allows the Metro Highway Program and each subregion or lead agency to revise delivery priorities and amend project budgets for the implementation of the Measure R Highway subregional projects. The attached updated project lists include projects which have received prior Board approval, as well as proposed changes related to schedules, scope and funding allocations for projects. The Board's approval is required as the updated project lists serve as the basis for Metro to enter into agreements with the respective implementing agencies.

Background
BACKGROUND

Lines 31, 32, 33, 35, 37, 38, 26 of the 2008 Measure R Expenditure Plan address Highway Operational Improvement subfunds. The Highway Programs group in Countywide Planning and Development leads the implementation and development of multi-jurisdictional and regionally significant highway and arterial projects. Staff also lead projects on behalf of local jurisdictions at their request or assist in t...

Click here for full text