File #: 2023-0163   
Type: Budget Status: Passed
File created: 3/1/2023 In control: Construction Committee
On agenda: 9/21/2023 Final action: 9/28/2023
Title: AUTHORIZE: A. an increase to the total authorized funding for Contract No. AE76301MC081 with Zephyr Rail, for pending and future task orders to provide Construction Management Support Services (CMSS), in an amount not to exceed $5,750,000.00, increasing the total contract value from $3,519,211 to $9,269,211; and B. the Chief Executive Officer to execute individual Task Orders (TOs) and Contract Modifications within the Board approved contract funding amount.
Indexes: Budget, Budgeting, Capital Project, Capital Project Funds, Construction, Construction management, Construction Support, Contracts, Joint development, Procurement, Professional Services, Program Management, Project management
Attachments: 1. Attachment A - Procurement Summary, 2. Attachment B - Task Order / Modification Log, 3. Attachment C - DEOD Summary

Meeting_Body

CONSTRUCTION COMMITTEE

SEPTEMBER 21, 2023

 

Subject

SUBJECT:                     CONSTRUCTION MANAGEMENT SUPPORT SERVICES FOR METRO CAPITAL PROJECTS

 

Action

ACTION:                     APPROVE RECOMMENDATIONS

 

Heading

RECOMMENDATION

 

Title

AUTHORIZE:

 

A.                     an increase to the total authorized funding for Contract No. AE76301MC081 with Zephyr Rail, for pending and future task orders to provide Construction Management Support Services (CMSS), in an amount not to exceed $5,750,000.00, increasing the total contract value from $3,519,211 to $9,269,211; and

 

B.                     the Chief Executive Officer to execute individual Task Orders (TOs) and Contract Modifications within the Board approved contract funding amount.

 

Issue

ISSUE

 

In October 2021, the Metro Board awarded contract AE76301MC081 to Zephyr Rail, a Metro Small Business Enterprise and female-owned firm, for CMSS for Capital Projects in an amount of $3,519,211 for a term of three years, inclusive of two one-year options. Staff has awarded task orders totaling $2,773,000 and now has approximately $746,211 of the authorized funding remaining.  The amount remaining is not sufficient to support capital projects that are currently in planning or under contract.

 

Background

BACKGROUND

 

The primary role of Zephyr Rail is to provide skilled and qualified staff to augment Metro staff in the performance of construction management services for Metro’s capital projects as well as adjacent projects and joint development. Both Metro and Zephyr Rail staff work side-by-side in Integrated Project Management Offices (IPMO). In essence, the Zephyr Rail contract allows Metro to augment Metro construction management staff efficiently and effectively as required, so that the proper resources required to manage a contract are available to Metro both in terms of staff availability and technical expertise.  This contract is funded solely through Board approved life of project budgets or annual project budgets, and funds are authorized by issuing separate task orders for various projects using labor classifications and rates set forth in the contract.  This method of funding and task allocation under the contract results in more efficient cost and schedule management, since task orders and modifications to existing task orders are negotiated and issued as the work or changed work is identified and defined. Metro prepares a scope of work and an estimate of hours for each task order or modification, and Zephyr Rail subsequently provides a proposal. If there is a discrepancy, Metro and Zephyr Rail will fact-find and negotiate the hours. After an agreement, the task order is issued, and the work proceeds. 

 

Discussion

DISCUSSION

 

The initial $3,519,211 contract award was calculated based on three years of small to midsize task orders, primarily for Resident Engineers, Office Engineers, Inspectors, and night-time oversight on construction job sites for capital projects. However, due to the technical expertise of Zephyr Rail’s staff, their team has also been able to assist Metro with other needs, such as constructability reviews, cost and schedule analysis, and railroad flagging operations.  Zephyr Rail’s services are also being used to support projects funded by departments outside of Program Management. For example, Zephyr Rail was able to provide inspection support for Metro Facilities grouting and repairs within the Red Line tunnel, and oversight for adjacent development construction along multiple rail lines. Metro construction management is currently supporting 102 projects related to joint development, adjacent development, and overhead and underground utilities, a project workload that is anticipated to grow to over 140 projects in the next two years. Therefore, due to the substantial growth of the adjacent and joint development efforts, many of which support Metro and the City of Los Angeles’ affordable housing goals, and Zephyr’s ability to support additional transportation projects, the contract value and construction modification authority were consumed at a more rapid pace than anticipated at the time of award.

Budget forecasts project future needs with a total value of $5,750,000 in staff augmentation for projects related to adjacent projects, joint development, and underground and overhead utility coordination work.  A listing of the current task orders, proposed projects, and a forecasted task order estimate is included in Attachment B.  As shown in the attachment, the requested contract value is $9,269,211.

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

This action will have no detrimental impacts on safety.

 

Financial_Impact

FINANCIAL IMPACT

 

Task Orders will be issued and funded from the associated budgets. The funding source differs depending on the individual project. The contract task orders can only be issued when there is sufficient funding within the approved budget for each respective project.

Since this is a multi-year contract, the cost center manager and Chief Program Management Officer will be responsible and accountable for budgeting the cost of the annual work program for the current and future fiscal years for the term of the contract, including any option(s) exercised.

Impact to Budget

Funding for this action will come from various sources eligible for rail facilities capital expenditures and major construction projects funded with specific grant and local sales tax sources.  Additional funding will be provided from private third-party adjacent developments and adjacent utility projects which Metro bills on a case-by-case basis, reflecting their impact to Metro’s ROW. The annual budget for these projects has been able to provide significant funds which enable Metro to execute task orders to the contract for the staffing (CMSS) needed. Due to a broader push for development near Metro Transit, there has been a significant increase in construction impacting Metro’s property. Based on data tracked since FY20, we have seen a trend with an increase in the total amount of projects year-over-year by approximately 30%.

 

Equity_Platform

EQUITY PLATFORM

 

Proper safety and inspection is critical to reduce the potential impact of interruption to service which would negatively affect our ridership. This contract will continue to support ongoing maintenance of the bus and rail systems to ensure reliability and reduce disruption to the system so many Angelenos rely on for their means of transportation in the region.  Further, this contract is being awarded to a company that qualifies as a Small Business within the Small Business Enterprise Program. To ensure maximum opportunity for participation in this contract, Metro staff performed extensive outreach to the small business community, including those within the Disadvantaged Veterans Business Enterprise and the Small Business Enterprise programs. The solicitation was advertised through periodicals of general circulation, posted on Metro’s Vendor Portal, and an e-mail notice to small businesses with applicable NAICS codes. The Construction Management Team presented at TBAC and attended meetings with the Small Business Community to further define the experience and background for this solicitation. The Proposal Evaluation Team was comprised of department personnel that were age, race, and gender diverse. DEOD established a goal of 27% SBE and 3% DVBE.  The selected firm committed to achieving a 69% SBE goal and 5% DVBE.

 

Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

The Project is consistent with the following Metro Vision 2028 Goals and Objectives:

 

Goal 1: Providing high-quality mobility options that enable people to spend less time traveling.

 

Goal 3: Enhance communities and lives through mobility and access to opportunity.

 

Goal 4: Transform LA County through regional collaboration and national leadership.

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

The Board may elect to discontinue using Zephyr Rail for CMSS.  Staff does not recommend this alternative as the construction projects are in various degrees of completion and the loss of staff would cause these projects to be significantly impacted. 

Another alternative would be to hire Metro staff to perform the required services. This alternative is also not recommended since the intent of the CMSS is to augment Metro staff in terms of technical expertise and availability of personnel. CMSS is typically required on a periodic or short-term basis to accommodate for peak workloads or specific tasks over the life of the projects. Further, for some projects, the specific technical expertise required may not be available within the ranks of Metro staff, whereas the CMSS consultant can provide the technical expertise on an as-needed basis.

 

Next_Steps

NEXT STEPS

 

Upon Board approval, staff will issue a contract modification and issue task orders, as needed.

 

Attachments

ATTACHMENTS

 

Attachment A - Procurement Summary

Attachment B - Task Order / Modification Log

Attachment C - DEOD Summary

 

 

Prepared_by

Prepared by: Michelle McFadden, Deputy Executive Officer, Project Management, (213) 922-3026

John Jaramillo, Director, Project Management, (213) 418-3149

Brad Owen, Interim Senior Executive Officer, Project Management, (213) 418-3143

Debra Avila, Deputy Chief Vendor/Contracts Management Officer, (213) 418-3051

 

Reviewed_By

Reviewed by:

Sameh Ghaly, Interim Chief Program Management Officer, (213) 418-3369