File #: 2022-0402   
Type: Informational Report Status: Filed
File created: 6/8/2022 In control: Construction Committee
On agenda: 8/18/2022 Final action: 8/18/2022
Title: RECEIVE AND FILE status report on Program Management Quarterly Change Report.
Sponsors: Construction Committee
Indexes: Budgeting, Capital Project, Construction, Informational Report, Program Management, Project management
Attachments: 1. Attachment A - Change Order Log, 2. Attachment B - OIG Spot Check CEO Delegated Authority Delays Avoided

Meeting_Body

 

CONSTRUCTION COMMITTEE

August 18, 2022

 

Subject

SUBJECT:                     PROGRAM MANAGEMENT QUARTERLY CHANGE REPORT

 

Action

ACTION:                     RECEIVE AND FILE

 

Heading

RECOMMENDATION

 

Title

RECEIVE AND FILE status report on Program Management Quarterly Change Report.

 

Issue
ISSUE

 

This board report is a receive and file that provides program management quarterly changes from capital projects greater than $500,000.  Greater detail is provided in Attachment A - Quarterly Change Orders Log for Reporting Period of March 1, 2022 - May 31, 2022.

 

 

 

Background

BACKGROUND

 

In January 2017, the Metro Board approved a one-year pilot to delegate the CEO the authority to execute project agreements up to the Life-of-Project (LOP) budget for the Crenshaw/LAX, Regional Connector, and Purple Line Extension Section 1 & 2 projects.  The purpose of the pilot was to save time and minimize disruption due to the typical contract change administration approval process.

 

The pilot program was effective, generated cost savings and avoided costly construction delays. At the January 26, 2018 Board meeting, the Board approved the continuation and expansion of the delegation of authority within Life of Project (LOP) budget management on all Transit and Regional Rail Capital Projects.  Staff was directed to provide quarterly reports to the Board on change orders and modifications that are above $500,000.  CEO Board delegated authority of changes is very beneficial to expedite contract changes and avoid costly construction delays. Since the inception of the program up to 1,992 concurrent workdays or concurrent 7.6 years, aggregated across the program, have been saved. (Attachment B)

 

Discussion
DISCUSSION

 

The change activities for the reporting period between March 1, 2022 and May 31, 2022 are included in Attachment A.

 

Financial_Impact
FINANCIAL IMPACT

The changes included in this report are included in the approved life-of-project budget for each project.

 

Equity_Platform

EQUITY PLATFORM

 

Crenshaw/LAX

Equity - 8 of 8 stations (100%) are within or adjacent to Equity Focus Communities

Westside Purple Line Ext 1

Equity - This project is not located within or adjacent to Equity Focus Communities

Westside Purple Line Ext 2

Equity - This project is not located within or adjacent to Equity Focus Communities

Westside Purple Line Ext 3

Equity - 1 of 2 stations (50%) are within or adjacent to Equity Focus Communities

Division 20

Equity - 100% of the project is within or adjacent to Equity Focus Communities

Airport Metro Connector

Equity - 100% of the project is within or adjacent to Equity Focus Communities

Metro Center Project (ESOC)

Equity - This project is not located within or adjacent to Equity Focus Communities

Blue Line Resignaling

Equity - 100% of the project is within or adjacent to Equity Focus Communities

I-5 North County Enhancements

Equity - This project is not located within or adjacent to Equity Focus Communities

Note: This EFC analysis was conducted with the 2019 EFC map. Future analysis will be updated to reference the 2022 EFC map.

 

Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

The recommendation supports strategic plan goal # 5 to provide responsive, accountable, and trustworthy governance within the Metro organization by keeping the Board informed of the Projects’ change orders and modifications via submitting the Change Order log on a quarterly basis.

 

Next_Steps
NEXT STEPS

 

The next Change Order Log will cover the period of June 1, 2022, through August 31, 2022, and will be presented to the September 2022 Construction Committee.

 

Attachments

ATTACHMENTS

 

Attachment A - Quarterly Change Orders Log for Reporting Period of March 1, 2022- May 31, 2022.

 

Attachment B - OIG Construction Change Order Spot Checks CEO Delegated Authority Delays Avoided.

 

Prepared_by

Prepared by:

                     Crenshaw/LAX - Sameh Ghaly, Deputy Chief Program Management Officer, (213) 418-3369

                     Westside Purple Line Ext 1 - James Cohen, EO Projects Eng., (323) 900-2114

                     Westside Purple Line Ext 2 - Michael McKenna, EO Projects Eng,(424) 551-4447

                     Westside Purple Line Ext 3 - Kimberly Ong, EO Projects Eng., (424) 551-4501

                     Division 20 Portal - Bryan Pennington, Chief Program Management Officer, (213) 922-7449

                     Airport Metro Connector - Tim Lindholm, Deputy Chief Program Management Officer, (213) 922-7297

                     Metro Center - Jeanet Owens, Sr. EO Project Mgmt., (213) 418-3189

                     Metro Blue Line Resignaling - Tim Lindholm, Deputy Chief Program Management Officer, (213) 922-7297

                     I-5 North Country Enhancements - Tim Lindholm, Deputy Chief Program Management Officer, (213) 922-7297

                     Report - Julie Owen, Sr. EO Program Control, (213) 922-7313

 

 

Reviewed_By

Reviewed by:

Tim Lindholm, Deputy Chief Program Management Officer, (213) 922-7297

Sameh Ghaly, Deputy Chief Project Management Officer, (213) 418-3319

Bryan Pennington, Chief Program Management Officer, (213) 922-7449

Sharon Gookin, Deputy Chief Executive Officer, (213) 418-3101