File #: 2017-0102   
Type: Informational Report Status: Filed
File created: 2/15/2017 In control: Finance, Budget and Audit Committee
On agenda: 3/15/2017 Final action: 3/15/2017
Title: RECEIVE AND FILE FY18 Budget Development Update.
Sponsors: Finance, Budget and Audit Committee
Indexes: 7th Street/Metro Center Station, Airport Metro Connector (AMC) Station Project, All Door Boarding, Azusa, Budget, Budgeting, Bus Acquisitions, Bus Maintenance Projects, Bus rapid transit, Construction, Crenshaw/LAX Transit Corridor Project, Gold Line Foothill Extension 2A, Gold Line Foothill Extension 2B, Informational Report, Labor, Light rail transit, Light rail vehicles, Los Angeles International Airport, Los Angeles Union Station, Maintenance, Maintenance of way, Measure M, Measure R, Metro Blue Line, Metro Crenshaw Line, Metro Divisions, Metro Exposition Line, Metro Gold Line, Metro Green Line, Metro Purple Line, Metro Rail A Line, Metro Rail C Line, Metro Rail E Line, Metro Rail K Line, Metro Rail L Line, Metro Red Line, Metro Vision 2028 Plan, Non-revenue Vehicles, Outreach, Patsaouras Plaza Busway Station, Procurement, Purchasing, Rail transit, Railroad commuter service, Railroad facilities, Regional Connector Transit Corridor Project, Revenue Service, Ridership, Rolling stock, Safety, Safety and security, Security, State Of Good Repair, Transit buses, Transit centers, Transit System, Twenty-eight by '28 Initiative, Vehicle fleets, Vehicle maintenance, Willowbrook/Rosa Parks Station
Attachments: 1. Attachment A - Metro Blue Line FY18 State of Good Repair Projects, 2. Presentation - Item 25 Budget
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Meeting_Body

FINANCE, BUDGET, AND AUDIT COMMITTEE

MARCH 15, 2017

 

Subject/Action

SUBJECT: FY18 BUDGET DEVELOPMENT UPDATE

ACTION: RECEIVE AND FILE

 

Heading

RECOMMENDATION

 

Title

RECEIVE AND FILE FY18 Budget Development Update.

 

Issue

ISSUE

Metro is continuing the development of its FY18 Budget. This is the second in a series of monthly updates to the Board on this process. This report will present and describe projects and programs that will account for more than half of Metro’s FY18 budget. Further, these elements demonstrate the incorporation of Measure M priorities, which put additional requirements on existing staff and will require the creation of new projects and addition of new staff in FY18.

This report provides a budget development update on the following topics:

                     Public outreach efforts

                     Fare revenue projections, based on preliminary assumptions for ridership

                     Projections for service levels for directly-operated Metro bus and rail services

                     Budget and descriptive information on efforts to maintain a state of good repair for our bus and rail fleet and facilities, as well as for regional transit facilities, like Union Station.

                     Transit construction projects, which are funded through Measures R and M

 

Discussion
DISCUSSION

Public Outreach Update

The prior FY18 Budget update report provided a comprehensive overview of the public and key stakeholder outreach efforts that are being included as part of the FY18 Budget development process.

An interactive Online Budgeting Tool, which engages the public in the budgeting process by walking users through a series of questions to garner input on their individual transportation priorities, was made available on February 12, 2017. The first round of stakeholder Budget workshops will be completed in March at the regularly scheduled Service Council Meetings, as well as at internal stakeholder meetings for the Technical Advisory Committee, Streets & Freeways Subcommittee, Bus Operations Subcommittee, Citizens Advisory Council, and Local Transit Systems Subcommittee. These workshops will outline the framework for the budget development process, including agency goals and how resource allocation will align with those goals. The presentations will also include sales tax assumptions and inflation projections to help shape expectations for each of the jurisdictions in the region. Finally, a review of bus and rail service levels, Metro’s plans for maintaining assets, and the Measure R and Measure M projects underway will show the foundation for what is planned for LA County. The next round of Budget presentations is scheduled for May.

To date, staff has promoted outreach efforts in print ads run in community publications across the County and brochures placed on Metro vehicles. Owned channels, including the rotating banners on metro.net, Metro’s blog and email subscriber list of more than 300,000 have also been utilized to drive engagement with the FY18 budget. In coming weeks, paid social media posts will also be used to notify the public of opportunities to engage with the budget process.

An interactive Telephone Town Hall on FY18 Budget development is also being put together, as requested by the Board of Directors. An automated telephone system will randomly call LA County residents to invite them to participate in a telephone meeting. Individuals will also be able to call into the meeting directly and that information will be added to the webpage metro.net/budgetcomments. The meetings will be simulcast in both English and Spanish. Additional details on the Telephone Town Hall meeting will be included in a Board Box item delivered separately.

Fare Revenues

Fare per Boarding
Annual fare revenues are estimated by multiplying the fare per boarding by the estimated annual number of boardings. Since the latest fare restructuring took effect at the end of the first quarter of FY15, fare per boarding has remained stable at $0.78. Therefore, FY18 fare per boarding is proposed at $0.78.

Projected Boardings
In 2016, systemwide boardings were 6% below the previous year. Accordingly, Metro is taking on various initiatives to increase ridership, with the goal of stopping the decline in boardings in FY18. As a result, projected boardings remain at 2016 levels of 415 million annually, with an increase in BRT/rail ridership offset by a slight decrease in bus ridership.

Ridership Initiatives
Immediate near term ridership initiatives for FY18 are focused in three areas. First, the new multi-agency policing contract will provide the vehicle for increased security throughout the system, and an immediate systemwide security surge will be implemented to encourage increased ridership through safety and security improvements. In addition, system speed improvements will be pursued on both the bus and rail systems. Past successes in this area, such as All-Door Boarding, will be considered in development of future pilot programs. Finally, the Regional Ridership Task Force convened in FY17 will work to address ridership impacts at the local level as well as countywide.

Figure 1 shows total boardings, fare revenues, and fare per boarding for the past 10 years, including a projection for FY18.

Figure 1:

Based on the projected $0.78 fare per boarding and retaining the current ridership level, Metro is estimating FY18 fare revenue to be $323.9 million.

Bus & Rail Service Levels

Bus service is projected to remain at FY17 budgeted services levels of 7 million revenue service hours. However, Operations anticipates right-sizing service levels along bus lines that parallel the Expo Line and reallocating those resources to improve the Owl Network and to increase peak-hour frequencies on select bus lines. 

In FY17, rail scheduled service levels on the Expo and Gold Lines were limited by vehicle availability. FY18 marks the first year when sufficient rail cars will be available to meet the growing demand on the two lines. As a result, revenue vehicle service hours for rail are anticipated to increase 9% over the currently scheduled base rail service levels. In addition, rail special event service is proposed to increase by 60% to meet the growing demand for rail service to sports venues and special events.

Figure 2 below shows the changes in rail services that are projected for FY18 as a result of sufficient rail car availability for both the Expo and Gold Lines and their extensions.

Figure 2:

State of Good Repair

In support of our continued operation of a transit system with nearly 1.4 million daily boardings, Metro continues to maintain its fleet, rail lines, bus and rail stations, and facilities in a State of Good Repair. Major expenses in FY18 include the acquisition of light rail vehicles, heavy rail vehicles, and buses, plus midlife and component overhaul of buses and light rail vehicles. The FY18 budget also includes rehabilitation of bus and rail facilities, stations, and Maintenance of Way, as well as installation of systems on our regional transit centers. Figure 3 below shows total State of Good Repair expenses planned in FY18. Figure 3 is followed with additional details regarding each of the categories and budgeted expenses.

For a separate table showing State of Good Repair efforts on the Blue Line, our oldest rail line, refer to Attachment A. Blue Line State of Good Repair expenses are currently estimated at $173.6 million, with an additional $4.9 million pending approval.

Figure 3:

Bus Acquisition
Metro will spend $59.8 million on bus acquisition activities. This effort includes procurement of two types of buses: fifty three (53) new Compressed Natural Gas (CNG) buses will replace existing CNG buses scheduled for retirement, and ten (10) new electrical buses will be received and tested on the Metro Orange and Silver Lines. Buses delivered in FY18 will reduce average fleet age in FY19 and beyond, as well as reduce our fleet maintenance costs.

Bus Maintenance
Bus maintenance focuses on midlife maintenance and engine replacement for $31.9 million in FY18. This work maximizes utilization of our buses through a total refurbishment, including structural integrity checks, corrective repairs, component change-outs, and performance and repair campaigns based on conditional fleet assessments. Performing these tasks increases bus reliability, reduces parts replacement costs, and reduces other preventative maintenance expenses once a bus is deployed back into revenue service.

Bus Facilities Improvements
Bus facilities improvement activities total $21 million and will address State of Good Repair maintenance requirements for bus divisions. Metro is developing master plans for facility upgrades, refurbishment, and site reconfigurations to upgrade critical facilities. Other safety initiatives include upgrades to fire and life safety equipment, ventilation, and emergency generators. To ensure regulatory compliance, we are also conducting underground fuel storage tank replacement.

Rail Vehicle Acquisition
The FY18 budget includes $134.2 million for rail vehicle delivery. Two major rail vehicle procurements are underway, for both light rail and heavy rail vehicles. In FY18, delivery of light rail vehicles continues, with another 48 vehicles - four per month - anticipated to arrive in the fiscal year. By the conclusion of FY18, we will have received 138 of the total 235 vehicles being purchased through the light rail vehicle contract. These new vehicles are going toward line extensions (e.g. Expo 2 and Gold Line Foothill 2A), new lines (e.g. Crenshaw/LAX), and vehicle replacement (e.g. Blue Line). Also in FY18, we are ramping up the heavy rail vehicle procurement approved by the Board in FY17 for the Purple Line Extension and for the replacement of aging fleet. The heavy rail vehicle procurement contract is in initial design and engineering phases, with the new cars scheduled to arrive in FY21.

Rail Vehicle Maintenance
Starting in FY18, Metro is initiating two major rail vehicle overhauls, in order to maximize the usefulness of existing light and heavy rail fleet that are halfway into their anticipated 30-year lifespans. In our light rail fleet, Metro will be overhauling 52 vehicles that currently serve the Blue, Green and Expo Lines. The light rail vehicle overhaul is scheduled to complete in FY21. In our heavy rail fleet, Metro will be overhauling the 74 AC-powered vehicles that serve both the Red and Purple Lines. The heavy rail fleet overhaul is scheduled to complete in FY22, before the Purple Line Segment 1 to La Cienega is scheduled to open for revenue service.

Rail Facilities and Wayside Systems Improvements
Rail Facilities and Wayside Systems State of Good Repair efforts are directed toward rehabilitating the oldest lines in the rail network, such as the Blue Line. In the coming months, Metro plans to award a contract to address Blue Line State of Good Repair for Overhead Catenary System (OCS) replacements, signalization improvements, added interlocks, and other needed improvements. Continuing efforts to improve safety on our rail system, the Blue Line Pedestrian Safety at Grade Crossing project remains ongoing in FY18. Green Line improvements are also in progress as track circuits and control systems are upgraded to provide seamless travel to LAX and beyond upon completion of the Crenshaw LAX Transit project.

Non-Revenue Vehicles
Eight million dollars is slated for non-revenue vehicle and equipment purchases. Non-revenue vehicles consist of sedans, trucks, and other vehicles that allow Metro staff to get to locations to operate service and maintain system infrastructure across the agency’s eleven bus divisions and six rail divisions. Non-revenue equipment includes bus lifts, utility vans, forklifts scrubbers, emergency generators, and high-rail response vehicles. These assets need to be replaced as they age, when mileage and condition standards are surpassed.

Information Technology & Communications
Metro remains steadfast in ensuring that our data is protected and secured from cyber-attacks by maintaining our equipment and infrastructure at industry standards. Upgrades and improvements will begin on our obsolete telephone system to a unified digital communication system with voice, email, and video conferencing capabilities. Wi-Fi continues to be installed at more rail lines and new buses for improved customer experience and security. These technology efforts will expend around $17 million in FY18.

Regional Transit Centers, Stations & Fare Collection
Regional Transit Centers include Union Station, Patsaouras Plaza Bus Station, El Monte Transit Center, and Willowbrook/Rosa Parks Station. The FY18 Budget includes $26.3 million, with $18.0 million going to design and construction costs for Willowbrook/Rosa Parks Station and $8.3 million going to the Patsaouras Plaza Bus Station. Regional projects, budgeted for $21.9 million in FY18, provide benefits that span multiple regions and/or operators. These projects include TAP, Ticket Vending Machines (TVMs), regional signage improvements, bicycle projects at rail locations, and parking guidance system installations at Metro-owned Park and Ride lots.

Metro Blue Line State of Good Repair
Since opening in 1990, the Blue Line remains Metro’s oldest rail line, and the FY18 budget includes $173.6 million to enhance safety and improve service reliability. These efforts represent a fiscal year slice of a $1.1 billion Life of Project total budget across all State of Good Repair projects benefiting the Blue Line. Planned expenses in FY18 include light rail vehicle fleet replacements and vehicle maintenance projects. The table in Attachment A shows a detailed list of projects occurring within the Blue Line Corridor as well as systemwide projects that provide a tangible benefit for Blue Line interoperability.

Transit Construction Projects

Planning Phase
Many Measure R projects are currently in an active planning phase, which has been further supplemented by Measure M funding and accelerated for select projects. As shown on lines 4-6 of Figure 4 below, some near-term Measure M transit projects will incur planning-related expenses in FY18, such as EIR/EIS, preliminary engineering, and public outreach. These projects include Orange Line Improvements, the BRT Connector between Orange/Red Line and the Gold Line, and the Vermont Transit Corridor. The projects are anticipated to start the planning phases and will kick start about $23.6 billion (Figure 4) of the total Measure M transit construction and highway projects. These projects are required by the Measure M Ordinance and are valued at $40.6 billion (in 2015 dollars) over the next 40 years. These planning activities and expenses are incurred for at least 4 years in advance of the target construction groundbreaking dates.

Figure 4:

Construction Phase
The FY18 budget continues to focus on the big three Measure R and M transit construction projects: (a) Crenshaw/LAX, (b) Regional Connector, and (c) Purple Line Extension (Sections 1, 2, and 3). The FY18 Budget includes $1.55 billion in construction expenses for these three projects, including (a) $432 million for Crenshaw/LAX, (b) $202 million for Regional Connector, and (c) $906 million for Purple Line Extension. As shown in Figure 5, this funding will bring the construction status to 88% complete for Crenshaw/LAX, with revenue operations anticipated in FY20. The Regional Connector is forecast to finish FY18 with 43% of construction complete, with revenue operations anticipated for the start of FY22. Purple Line Segment 1 construction is forecast to achieve 35% completion by the end of FY18, with an opening planned for Nov 2023.

Measure M mandates the groundbreaking for the Airport Metro Connector in FY18 and groundbreaking for the Gold Line Foothill Extension 2B from Azusa to Montclair in FY19. As a result, $93 million in planning and construction expenses for these two projects is budgeted in FY18, including $71 million for the Airport Metro Connector and $22 million for Gold Line Foothill 2B.

Figure 5:

Financial_Impact
FINANCIAL IMPACT

Forecast ridership and bus and rail service levels will continue to guide the development of the FY18 Budget, and they may be adjusted as more specific information and guidance becomes available. Transit construction, state of good repair, bus and rail transit service levels, and project planning costs will account for three-fourths of the total FY18 budget.

Alternatives_Considered
ALTERNATIVES CONSIDERED

The annual budget serves as the legal authority to obligate and spend funds. Failure to adopt the budget would severely impact Metro’s stated goal of improving transportation in Los Angeles County.

Next_Steps
NEXT STEPS

As stated previously, this report is the second in a series of monthly updates to the Board regarding the FY18 Budget development process. The remaining reports - and their expected content - are shown below, culminating in Final Board Approval in May 2017 for the FY18 Budget year that begins July 1, 2017.

                     April 2017:

o                     Preliminary FY18 Budget proposal, including Federal, State, and Local Revenues, and non-labor expenses

o                     Agencywide labor expenses, including contract and non-contract positions

o                     Outreach status update

                     May 2017:

o                     Public Hearing - May 17, 2017

o                     Final Board Adoption - May 25, 2017
(in accordance with State Public Utilities Code Section 130051.12)

Attachments

ATTACHMENTS

A.                     Metro Blue Line FY18 State of Good Repair Projects

 

Prepared_by

Prepared by:                     Office of Management and Budget (OMB) Team

Luke H. Klipp, Principal Transportation Planner, (213) 922-7412

 

Reviewed_By

Reviewed by:                     Nalini Ahuja, Chief Financial Officer, (213) 922-3088