File #: 2022-0016   
Type: Contract Status: Consent Calendar
File created: 1/11/2022 In control: Board of Directors - Regular Board Meeting
On agenda: 3/24/2022 Final action: 3/24/2022
Title: CONSIDER: A. AUTHORIZING the Chief Executive Officer to execute Modification No. 14 to Contract No. AE5999300 with WSP USA, Inc. to provide environmental technical work and outreach support to complete the Final Environmental Impact Statement/Environmental Impact Report (FEIS/FEIR), as well as conduct additional technical analysis to identify a cost-effective alignment route for the Slauson/A Line (Blue) to Los Angeles Union Station segment of the West Santa Ana Branch (WSAB) Transit Corridor Project in the amount of $13,601,672, increasing the Total Contract Value from $29,786,881 to $43,388,553 and to extend the Contract Period of Performance through June 30, 2023; and B. INCREASING Contract Modification Authority (CMA) specific to Contract No. AE5999300 in the amount of $1,000,000 from $2,476,120 to $3,476,120 to support additional environmental assessment work, and any other future technical work identified through future coordination efforts and/or as directed by the Board. HAH...
Sponsors: Planning and Programming Committee
Indexes: Alignment, Artesia, Board approved a Motion, Budgeting, Cerritos, Contracts, Environmental Impact Report, Environmental impact statements, Eric Garcetti, Federal Transit Administration, Fernando Dutra, Gateway Cities (Southeast LA County) Service Sector, Gateway Cities subregion, Hilda Solis, Holly J. Mitchell, Janice Hahn, Los Angeles Union Station, Metro Rail A Line, Motion / Motion Response, Outreach, Procurement, Project, West Santa Ana Branch Corridor - Administration (Project), West Santa Ana Branch Transit Corridor, West Santa Ana Branch Transit Corridor (WSAB) Project
Attachments: 1. Attachment A - Procurement Summary, 2. Attachment B - Contract Modification Log, 3. Attachment C - DEOD Summary, 4. Presentation
Related files: 2022-0270

Meeting_Body

REVISED

PLANNING AND PROGRAMMING COMMITTEE

MARCH 16, 2022

 

Subject

SUBJECT:                     WEST SANTA ANA BRANCH TRANSIT CORRIDOR PROJECT

 

Action

ACTION:                     APPROVE RECOMMENDATIONS

 

Heading

RECOMMENDATION

 

Title

CONSIDER:

 

A.                     AUTHORIZING the Chief Executive Officer to execute Modification No. 14 to Contract No. AE5999300 with WSP USA, Inc. to provide environmental technical work and outreach support to complete the Final Environmental Impact Statement/Environmental Impact Report (FEIS/FEIR), as well as conduct additional technical analysis to identify a cost-effective alignment route for the Slauson/A Line (Blue) to Los Angeles Union Station segment of the West Santa Ana Branch (WSAB) Transit Corridor Project in the amount of $13,601,672, increasing the Total Contract Value from $29,786,881 to $43,388,553 and to extend the Contract Period of Performance through June 30, 2023; and

 

B.                     INCREASING Contract Modification Authority (CMA) specific to Contract No. AE5999300 in the amount of $1,000,000 from $2,476,120 to $3,476,120 to support additional environmental assessment work, and any other future technical work identified through future coordination efforts and/or as directed by the Board.

 

HAHN AMENDMENT:

 

The cities of Cerritos and Artesia have requested confirmation that Metro will be assessing the aerial segment at the intersection of 183rd and Gridley for this possibility of cut-and-cover, to see if that can be done at a lower cost.

 

In addition, Cerritos has requested evaluation of a possible future station in the city, to be located between Studebaker Road and Gridley Road. I’d like to request that, as part of this action before us today, that a possible future station in Cerritos, between Studebaker Road and Gridley Road, also be included in this assessment.

 

 

Issue

ISSUE

 

A Contract Modification is necessary to conduct technical analysis and provide the outreach and procedural support necessary to complete the federal and state environmental processes (i.e., FEIS/FEIR) for the WSAB Project. Additional technical analysis and community engagement will also be conducted to identify a cost-effective alignment route for the Slauson/A Line (Blue) to Los Angeles Union Station (LAUS) segment, as well as to identify interim bus connections to connect Slauson/A Line (Blue) to LAUS. Board approval is required to execute this contract modification, and to increase the CMA for any additional environmental assessment work identified through future coordination efforts and/or as directed by the Metro Board.

 

Background

BACKGROUND

 

In September 2016, the Board awarded the technical contract with WSP USA, Inc. (then Parsons Brinckerhoff, Inc.) to complete the environmental clearance study for the WSAB Project. The scope of work and associated costs to complete the FEIS/FEIR (to be authorized by the Board at the conclusion of the Draft EIS/EIR) were included in the Contract as Scenario 1, Option 2.

 

At its January 2022 meeting, the Board received the Draft EIS/EIR for the WSAB Project, approved LAUS as the northern terminus, and selected Slauson/A Line (Blue) to Pioneer Station as the Locally Preferred Alternative (2021-0724). The Board further directed staff to conduct additional technical analysis to identify a cost-effective alignment route for the Slauson/A Line (Blue) to LAUS segment, and to identify interim bus connections to connect Slauson/A Line (Blue) to LAUS. During the January 2022 meeting, the Board also approved a motion from Directors Hahn, Solis, Garcetti, Mitchell, and Dutra (Legislative Report 2022-0023), that the Board adopt as policy that the full Project will be declared complete once it provides a single-seat ride connecting the City of Artesia (Pioneer Boulevard) to LAUS via rail. The motion also directed Metro to conduct additional technical analysis, including an assessment of above-grade/aerial sections of the LPA where cut-and-cover could be constructed at a lower cost, identification of accelerated construction and funding opportunities for the LPA segment, and other analysis.

 

Discussion

DISCUSSION

 

Since initiating the Draft EIS/EIR in 2016, the Board has approved a number of revisions to the Project definition, including expanding the range of alternatives under consideration in the northern segment, removing several stations from further study, additional grade separations, and other alignment modifications. In February 2018 (2017-0859), the Board approved expanding the northern alignment options under study in the Draft EIS/EIR, and in November 2018 (Legislative Report 2018-0404), the Board approved an updated project definition based on technical analysis and comments received during the 2017 scoping and 2018 updated scoping meetings.

 

Due to the number of revisions to the Project definition as a part of the above-Board actions, as well as additional technical analysis identified during the completion of the Draft EIS/EIR through coordination with the FTA, corridor cities, agencies and other stakeholders, the scope of work (and associated costs) have been updated to reflect these changes and to include the necessary work needed to complete the FEIS/FEIR.

 

Due to the environmental complexity of the Project, additional CMA is being requested to support additional environmental assessment and technical work resulting from future Board direction and/or additional coordination with the FTA or other stakeholders.  Additional CMA allows for flexibility and responsiveness necessary to maintain the project schedule.

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

There is no impact to safety.

 

Financial_Impact

FINANCIAL IMPACT

 

The FY21-22 budget contains $4,487,319 in Cost Center 4370 (Mobility Corridors), Project 460201 (WSAB Corridor Administration) for professional services. Since this is a multi-year contract, the Cost Center Manager and Chief Planning Officer will be responsible for budgeting in future years.

 

Equity_Platform

EQUITY PLATFORM

 

This Project will benefit communities through the addition of a new high-quality reliable light rail transit which will increase mobility and connectivity for the historically under-served and transit-dependent communities in the corridor.  Approval of the contract modification will allow staff to complete the Final environmental study and additional technical studies as directed by the Board in January 2022 and will allow corridor communities and users of the Metro system to benefit from this new transit service. As described above, the technical contract for the Project included an option (to be authorized by the Board at the conclusion of the Draft EIS/EIR) for WSP USA, Inc. to complete the Final EIS/EIR. Due to the number of revisions to the Project definition resulting from Board actions, as well as additional technical analysis identified during the completion of the Draft EIS/EIR, a contract modification is necessary to update the scope of work (and associated costs) to complete the Final EIS/EIR. The contract modification also includes the additional technical work as directed by the Board in January 2022. Key roles for Disadvantaged Business Enterprise (DBE) team members have been included for this additional work, at approximately 26.58% of the modification value, to ensure that the overall DBE participation goal (25.03%) is met.

 

Since initiating the Project study, staff has conducted extensive outreach efforts for corridor communities, and has continued to engage project stakeholders through a variety of forums and platforms, including special outreach efforts to reach out to people of color, low income, and limited English proficiency populations, and persons with disabilities. As a result of this extensive outreach, Metro made numerous changes to the Project Definition resulting from the comments received during the scoping process, as well as ongoing coordination with the corridor cities and continued technical analysis. These changes include alignment and vertical configuration changes, removing three stations from further study, as well as other Project design changes.

 

Metro will continue to engage corridor communities during the completion of the Final EIS/EIR, allowing the public, local jurisdictions, and other stakeholders the opportunity to provide their comments and feedback on the Project.  Staff will also reengage communities to help define the project, including alignment profile, station locations, and design, that meets the changing mobility needs of Little Tokyo, Arts District, LAUS and surrounding area residents, employees, and businesses.

 

Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

The Project supports the following strategic plan goals identified in Vision 2028: Goal 1: Provide high-quality mobility options that enable people to spend less time traveling, Goal 3: Enhance communities and lives through mobility and access to opportunity and Goal 5: Provide responsive, accountable, and trustworthy governance within the Metro organization.

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

The Board could choose not to approve the contract modification. Delaying this contract modification to a future date would pose significant delays to the overall project schedule and risk that the project would be unable to meet its Measure M schedule.

 

Next_Steps

NEXT STEPS

 

Upon Board approval, staff will execute Modification No. 14 to Contract No. AE5999300 with WSP USA Inc. for environmental technical work and outreach support to complete the Final Environmental Impact Statement/ Environmental Impact Report (FEIS/FEIR), as well as conduct additional technical analysis to identify a cost-effective alignment route for the Slauson/A Line (Blue) to LAUS segment. These activities are needed to continue advancing the Project per Board direction.  Staff will also report back to the Board in April 2022 to provide an update on the items included in the January 2022 motion from Directors Hahn, Solis, Garcetti, Mitchell, and Dutra.

 

Attachments

ATTACHMENTS

 

Attachment A - Procurement Summary

Attachment B - Contract Modification/Change Order Log

Attachment C - DEOD Summary

 

Prepared_by

Prepared by: Matthew Abbott, Principal Transportation Planner, Countywide Planning & Development (213) 922-3071

Meghna Khanna, Senior Director, Countywide Planning & Development, (213) 922-3931

Dolores Roybal-Saltarelli, DEO, Countywide Planning & Development, (213) 922-3024

Allison Yoh, EO, Countywide Planning & Development, (213) 922-7510

David Mieger, SEO, Countywide Planning & Development, (213) 922-3040

 

Reviewed_By

Reviewed by: James de la Loza, Chief Planning Officer, (213) 922-2920

Debra Avila, Deputy Chief Vendor/Contract Management Officer, (213) 418-3051