File #: 2024-1141   
Type: Project Status: Agenda Ready
File created: 12/17/2024 In control: Planning and Programming Committee
On agenda: 3/19/2025 Final action:
Title: AUTHORIZE: A. the reallocation of $25.74 million of Proposition C discretionary funds from the Access Services (Access) budget to fulfill unprogrammed STP-L funding program balances and; B. the Chief Executive Officer (CEO) or their designee to execute STP-L balance fulfillment agreements with local agencies, allowing them to receive their unprogrammed STP-L balances using available non-federal Metro funds.
Sponsors: Program Management (Department), Maria Luk
Indexes: Access Services Inc., Budget, Budgeting, Call For Projects, Congestion Mitigation And Air Quality Improvement Program, Federal Highway Administration, Federal Transit Administration, Grant Aid, Housing, Local transportation, Multi County Goods Movement Action Plan, Paratransit services, Program, Project, Safety, Southern California Association Of Governments, Strategic planning
Attachments: 1. Attachment A - Summary STP-L Balances for Agencies in Los Angeles County, 2. Presentation
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Meeting_Body

PLANNING AND PROGRAMMING COMMITTEE

                                                               MARCH 19, 2025

 

Subject

SUBJECT:                     COMPLETION OF SURFACE TRANSPORTATION PROGRAM-LOCAL (STP-L) ANNUAL APPORTIONMENTS TO LOCAL AGENCIES

 

Action

ACTION:                     APPROVE RECOMMENDATION

 

Heading

RECOMMENDATION

 

Title

AUTHORIZE:

 

A.                     the reallocation of $25.74 million of Proposition C discretionary funds from the Access Services (Access) budget to fulfill unprogrammed STP-L funding program balances and;

 

B.                     the Chief Executive Officer (CEO) or their designee to execute STP-L balance fulfillment agreements with local agencies, allowing them to receive their unprogrammed STP-L balances using available non-federal Metro funds.

 

Issue

ISSUE

 

Metro had historically apportioned, on an annual basis, $31 million of Federal (STBG) formula funding by Metro to agencies in Los Angeles County based on population through the STP-L funding program to deliver basic maintenance projects that did not have air quality impacts, such as pavement rehabilitation and slurry seal projects. In 2021 and 2022, the federal government issued Corrective Actions to Caltrans and the Southern California Association of Governments (SCAG), respectively, finding that this practice was out of compliance with STBG funding requirements. While Metro can no longer apportion STBG funds to agencies based on population, several agencies still have STP-L fund balances from previous apportionments.

 

During the outreach process for the first SCAG Corrective Action Call for Project Nominations, several agencies and subregions requested that Metro develop a method by which the STP-L balances could be fulfilled by Metro with non-federal funds.  The proposed action will shift an equivalent amount of local discretionary funds from Access, the Consolidated Transportation Services Agency (CTSA) that provides paratransit services throughout Los Angeles County, Proposition C budget to fulfill the fund balances from the former STP-L program to local jurisdictions.

 

 

Background

BACKGROUND

 

Since the early 1990s, Metro has,on an annual basis, subvented approximately $31 million of the STBG funding apportioned to Los Angeles County to all 88 agencies and the County of Los Angeles based on each agency's share of the County’s population.  This program was called the Surface Transportation Program-Local (STP-L).  Each agency was responsible for obligating those funds to projects through the Federal Transportation Improvement Program (FTIP) process.  Agencies were allowed to accumulate their annual STP-L apportionments until they had sufficient funding to complete a project.  It was common for agencies to carry a balance of STP-L funds over from year to year.  Attachment A lists the existing STP-L balances for each agency grouped by subregion.

 

In April 2021, the Federal Highway Administration (FHWA) and Federal Transit Administration (FTA) issued a Corrective Action to Caltrans on the administration of the STBG and Congestions Mitigation and Air Quality (CMAQ) Improvement Programs. The findings require Caltrans to ensure that sub-recipients of STBG and CMAQ funds throughout the state administer these programs in compliance with federal program guidance and regulations. Subsequently, in August 2022, FHWA and FTA jointly issued a Corrective Action to SCAG, requiring a review of Caltrans’ STBG and CMAQ administrative policies and the development of a process that ensures compliance with federal program guidelines and regulations for the administration of the STBG and CMAQ programs.  Also, Metro has discontinued the STP-L funding program because of these Corrective Actions.

 

SCAG developed and adopted a STBG/CMAQ Compliance Action Plan, which outlines the regional approach for addressing the Corrective Action to ensure that any new project or new project phase funded with CMAQ and/or STBG funds are subject to a competitive project selection process.   The specific issues the SCAG compliance plan addresses are:

 

• Replacing the current federal transportation funding suballocations by population or mode to agencies and counties with a performance-based approach.

 

• Modifying the eligibility screening conducted for compliance with Federal program guidance and regulations.

 

• Modifying the project selection process so federally funded transportation projects are selected by SCAG as the designated Metropolitan Planning Organization (MPO).

 

In 2024 SCAG held its first nomination process for STBG and CMAQ funds, and Board approval was obtained in March 2024 for the project ranking list for Los Angeles County.

 

Discussion

DISCUSSION

 

With the Corrective Action, STP-L funds that were programmed in the first four years of 2023 FTIP (FFY23-FFY26) before July 1, 2023, are considered “Grandfathered.”.  In the current 2025 FTIP, Grandfathered STP-L are only allowed to be programmed in FFY25 and FFY26, which must be obligated with an E-76 through Caltrans by December 31, 2026, or the funds will be lost permanently.

 

Conversely, the $25.74M of STP-L balances are funds that are not programmed, grandfathered, or allowed to enter the FTIP.  Per Board action in June 2023, local funds for Access operating and capital budget can be replaced with federal STBG. Through this Board action, Metro staff coordinated with Access to allocate an equivalent amount of STBG in exchange for its Proposition C discretionary funds to fulfill STP-L balances.

 

Adoption of the recommendations would allow Metro to provide a one-time fulfillment of the unprogrammed STP-L balances to agencies using Proposition C discretionary funds from the Access budget.

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

Approval of this item will not directly impact the safety of Metro customers or employees. However, as some of the projects eligible for these funds include safety enhancements, avoiding potential risks and maintaining the grant funding helps to ensure the timely realization of the projects’ anticipated safety benefits.

 

Financial_Impact

FINANCIAL IMPACT

 

Adoption of the recommendations would allow Metro to provide a one-time fulfillment of the unprogrammed STP-L balances to agencies with Proposition C discretionary funds from the Access budget.

 

Impact to Budget

This fulfillment does not impact Metro’s or Access's budgets, given that Access had previously received an equivalent amount of Surface Transportation Block Grant (STBG) funds. Per Board action in June 2023, local funds for Access's operating and capital budget can be replaced with federal STBG.  The source of funding for this action will come from local funding sources that are eligible for bus and rail operations.

 

 

Equity Platform

EQUITY PLATFORM

 

STP-L funds are intended to provide a flexible funding source to local agencies for transportation projects and programs. The Board action will provide one-time funding to advance transit and other multimodal plans, programs, and infrastructure improvements throughout Los Angeles County, including lower-resourced communities, areas of concentrated poverty, and historically disadvantaged communities.  The types of projects historically funded by local agencies with STP-L include street and sidewalk maintenance as well as the operation of local transit services.  These projects have provided benefits to bicyclists, pedestrians, and transit riders.

 

SCAG’s competitive grant process implements a process that allows agencies to secure funding based on the merit of their project as opposed to the STP-L program, which apportioned funds based on population. Through the competitive CMAQ/STBG grant process a small city can now compete for a much larger funding amount than they would have received based solely on their population.

 

 

Vehicle_Miles_Traveled_Outcome
VEHICLE MILES TRAVELED OUTCOME

 

VMT and VMT per capita in Los Angeles County are lower than national averages, the lowest in the SCAG region, and on the lower end of VMT per capita statewide, with these declining VMT trends due in part to Metro’s significant investment in rail and bus transit.*  Metro’s Board-adopted VMT reduction targets align with California’s statewide climate goals, including achieving carbon neutrality by 2045. To ensure continued progress, all Board items are assessed for their potential impact on VMT.

 

This initiative provides funding for surface transportation projects, typically pavement maintenance projects. Some projects may include active transportation and pedestrian safety treatments that may help reduce VMT.  Local agencies have historically funded projects such as street and sidewalk maintenance and the operation of local transit services with STP-L. These projects have benefitted bicyclists, pedestrians, and transit riders.  Traditionally, projects funded with STP-L do not increase capacity by adding new lanes but rather focus on improving the pavement conditions on local roadway safety through pavement maintenance and resurfacing. 

 

Overall, this project may increase Vehicle Miles Traveled (VMT), as improvements in travel time could encourage more vehicle trips. However, any increase in VMT resulting from these projects is expected to be minimal. Additionally, the safety improvements and the benefits for cyclists, pedestrians, and transit users will help offset any potential growth in VMT.

 

*Based on population estimates from the United States Census and VMT estimates from Caltrans’ Highway Performance Monitoring System (HPMS) data between 2001-2019.

 

Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

Approval of these recommendations will support the following Strategic Plan Goals:

 

Goal 3: Enhance communities and lives through mobility and access to opportunity by securing funding to conduct planning, create and enhance programs, and build infrastructure that accelerates infill development, facilitates housing supply, choice, and affordability, affirmatively furthers fair housing, and reduces VMT.

 

Goal 4: Transform LA County through regional collaboration and national leadership by facilitating partnerships to deliver transportation projects with significant geographic or regionwide benefits.

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

The Board may choose not to approve the recommended actions. Staff does not recommend this alternative because without the reallocation of $25.74M of Proposition C 40% from the Access Services budget to the STP-L program, local agencies will not be able to receive their unprogrammed STP-L balances.

 

Next_Steps

NEXT STEPS

 

Planning staff will work with County Counsel to develop the STP-L balance fulfillment agreement so that local agencies can receive their unprogrammed STP-L balances.  Staff will then contact cities with unprogrammed STP-L balances and provide them with a deadline of December 31, 2026, and directions for the final one-time opportunity for Metro to fulfill their STP-L balances with local funds.  Staff will also ensure that all eligible agencies in Los Angeles County are aware of future CMAQ/STBG/ funding through SCAG’s Call for Nomination.  The next SCAG Call for Nominations will start in the Spring of 2025, and Metro, as the County Transportation Commission, will lead the competitive call for projects for the Los Angeles County region.

 

Attachments

ATTACHMENTS

 

Attachment A - Summary STP-L Balances for Agencies in Los Angeles County

 

Prepared_by

Prepared by:                      Michael Richmai, Senior Manager, Countywide Planning & Development, (213) 922-2558

Nancy Marroquin, Senior Director, Countywide Planning & Development, (213) 418-3086

                     Mark Yamarone, Executive Officer, Countywide Planning & Development, (213) 418-3452

                     Laurie Lombardi, Senior Executive Officer, Countywide Planning & Development, (213) 418-3251

 

Reviewed_By

Reviewed by:                      Ray Sosa, Chief Planning Officer, (213) 547-4274