File #: 2023-0738   
Type: Contract Status: Passed
File created: 12/4/2023 In control: Operations, Safety, and Customer Experience Committee
On agenda: 1/18/2024 Final action: 1/25/2024
Title: AUTHORIZE the Chief Executive Officer to: A. AWARD Contract No. HR5000-2023 to the Hyundai Rotem Company for the manufacturing and delivery of 182 heavy rail vehicles (HRVs), in the amount of $663,688,303 for the base contract buy, exclusive of one (1) contract option for an additional 50 HRVs, totaling 232 HRVs, subject to resolution of the protest submitted to Metro; B. APPROVE a combined Life of Project (LOP) budget of $730,057,133, which includes the cost of the vehicle contract of $663,688,303 and Contract Modification Authority of $66,368,830; and C. NEGOTIATE AND EXECUTE future contract modifications to the Contract up to $1,000,000.
Sponsors: Board of Directors - Regular Board Meeting
Indexes: Budget, Budgeting, Construction, Contractors, Contracts, Metro Rail D Line, Metro Vision 2028 Plan, Olympic games, Plan, Procurement, Request For Proposal, Revenue Service, Rolling stock, Safety, System safety, Twenty-eight by '28 Initiative, Westside Subway Extension/Purple Line Extension Phase 1, Westside Subway Extension/Purple Line Extension Phase 2, Westside Subway Extension/Purple Line Extension Phase 3
Attachments: 1. Attachment A - Procurement Summary, 2. Attachment B - DEOD Summary, 3. Attachment C - Funding and Expenditure Plan, 4. Presentation
Related files: 2023-0496, 2024-0125

Meeting_Body

OPERATIONS, SAFETY, AND CUSTOMER EXPERIENCE COMMITTEE

JANUARY 18, 2024

 

 

Subject

SUBJECT:                     HR5000 HEAVY RAIL VEHICLE (HRV) PROCUREMENT

 

Action

ACTION:                     APPROVE RECOMMENDATIONS

 

Heading

RECOMMENDATION

 

Title

AUTHORIZE the Chief Executive Officer to:

A.                     AWARD Contract No. HR5000-2023 to the Hyundai Rotem Company for the manufacturing and delivery of 182 heavy rail vehicles (HRVs), in the amount of $663,688,303 for the base contract buy, exclusive of one (1) contract option for an additional 50 HRVs, totaling 232 HRVs, subject to resolution of the protest submitted to Metro;

 

B.                     APPROVE a combined Life of Project (LOP) budget of $730,057,133, which includes the cost of the vehicle contract of $663,688,303 and Contract Modification Authority of $66,368,830; and

 

C.                     NEGOTIATE AND EXECUTE future contract modifications to the Contract up to $1,000,000.

 

Issue

ISSUE

 

New HRVs are required to meet the revenue service requirements and enhanced service capacity for Westside D (Purple) Line Extensions (PLE) 2 & 3, as specified in the 30/10 Initiative, as well as replace the existing A650 HRV fleets when they have reached the end of their useful lives. 

 

Background

BACKGROUND

 

In December 2022, the Board authorized staff to issue a federally funded solicitation for a Best Value Request for Proposals (RFP) utilizing competitive negotiations pursuant to PCC § 20217 for the procurement of the 182 Base Order and 50 Option HRVs.  Metro’s Rail Fleet Management Plan FY2020 - FY2040, describes the rail fleet requirements to accommodate anticipated growth in ridership, support line extensions and replace vehicles reaching the end of their useful revenue service lives.   

 

The existing A650 HRV fleets consist of 100 vehicles; 30 Base Buy, DC-motor HRVs of which four (4) have been retired, and 74 Option Buy, AC-motor HRVs.  Based on a 30-year useful life, the Base Buy vehicles were scheduled to be retired between 2022 and 2023, and the Option Buy vehicles starting between 2027 and 2029. 

 

The HR4000 HRV procurement project will deliver 64 new HRVs by mid-2025; thirty will be used to replace the original 30 A650 Base Buy HRVs, and the remaining 34 HRVs will be used to support the expanded service with the opening of Purple Line Extension 1. 

 

The intent of the HR5000 program is to procure the additional one hundred eighty-two (182) Base Order HRVs anticipated to be needed for PLE Sections 2 & 3, System Service Expansion, and replacement of the existing seventy-four (74) A650 Options Order vehicles.

 

Discussion

DISCUSSION

 

Staff’s recommendation presents the firm that is most advantageous to Metro. Hyundai Rotem Company’s offer represents the Highest Rated and Best Value to Metro when all technical and price factors are considered in accordance with the RFP evaluation criteria, including US content and Employment Plan. The Best Value evaluation is inclusive of the vehicle quantities for the Contract Base and Contract Option. The Procurement Summary (Attachment A) further provides the detailed evaluation results and rankings for all proposers, including the weighted scores associated with each evaluation factor.

 

The 182 HRV Base Order will address the operational service requirements of PLE Section 2; PLE Section 3, replacement of the existing A650 Option vehicles, which will be reaching the end of their useful revenue service lives in approximately ten (10) years; and fulfilling the headway commitment as well as supporting Metro’s planned HRV Line service expansion.

 

If the Board approves this Contract, Hyundai Rotem Company is expected to deliver 42 new HRVs by April of 2028, as indicated in their current schedule to support the 2028 Olympics in Los Angeles. The balance will be delivered by the end of April 2030 to support committed levels of service for service expansions.

 

The contract includes incentives to complete delivery of the first three married-pairs (6 pilot HRVs) by May  1, 2027, thirty-nine (39) months following the issuance of NTP. Thirty-six production vehicles are scheduled to be delivered by the end of April  2028. The contract also includes provisions to impose liquidated damages for late deliveries.

 

The Contract contains one (1) option for up to 50 additional vehicles, as part of this procurement action, but the authority to award the option is not included in the staff recommendation.  Should Metro determine the need to exercise this option, approval to do so will be requested.

 

This procurement complies with Buy America and Metro’s Manufacturing Careers Policy.

 

On November 21, 2023, Stadler US filed an official protest of the determination of the HR5000 Contractor selection. The protest questioned Metro’s final scoring calculations and Hyundai Rotem’s performance beyond the 10-year reporting term required by the Request for Proposals. The protest is anticipated to be resolved by the January 2024 board meeting date.

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

The approval of this contract award will have a direct and positive impact on system safety, service quality, system reliability and overall customer satisfaction. The procurement of 182 new HRVs will feature the most current safety systems and augment service levels in addition to replacing the existing A650 series HRVs.

 

Financial_Impact

FINANCIAL IMPACT

 

The total requested LOP budget is a combination of contract amount for the 182 Base Order HRVs of $663,688,303 and 10 percent (10%) Contract Modification Authority, which equals $730,057,133.  The base order impacts three projects:  HR5000 Heavy Rail Vehicle Acquisitions, PLE Section 2, and PLE Section 3.

 

Since this is a multi-year contract, the cost center managers, project managers, Chief Operations Officer, and Chief Program Management Officer will ensure that costs will be budgeted in their respective projects for future years.

 

Impact to Budget

 

The FY24 planned expenditure of $70,000,000 is included in the combined annual budget for  HR5000 Heavy Rail Vehicle Acquisition project, Cost Center 3043, Rail Vehicle Acquisition, and in PLE Sections 2 and 3 projects, Cost Center 8510, Construction Contracts/Procurement. The current sources of funds for this action affecting PLE Sections 2 and 3 are a combination of Federal New Starts, TIFIA, Measure R 35%, and Measure M 35%. Due to the four minute headway requirement for the PLE projects and the difference between estimated vs. actual cost per vehicle, it is anticipated that PLE projects may seek an increase to their LOP in the future to reflect the new vehicle cost and number of vehicles needed. Funding sources for the PLE Sections 2 and 3 are planned for the design, construction, and rolling stock procurement efforts; these funds are not eligible for operations. Funding for the replacement vehicles share of the procurement is Proposition A 35%, which is eligible for rail operations.  Upon Board approval of the Recommendations, staff will pursue additional eligible federal and state funding sources to augment the funding for the projects.

 

Equity_Platform

EQUITY PLATFORM

 

Part of the new HR5000 rail vehicles will be used to replace the existing aged A650 Option vehicles and the remaining will be used on the D Line Extensions.  Approving the recommendations in this board report will support the identified fleet expansion and service needs and will encourage fair, competitive bidding processes for the selection of best value, qualifying contractor to deliver new vehicles on Metro’s existing heavy rail vehicle lines The existing B and D Heavy Rail Lines currently serve passengers in majority Equity Focus Communities (EFC) who rely on public transportations to commute to their jobs and other life commitments. With the D Line Extensions, EFC will have expanded access to opportunities in the Westside Cities/West Central Los Angeles subregions.  The new HR5000 fleet is required to accommodate such expansions.    Based on the 2019 Customer Survey, the B and D Heavy Rail Lines serve the following ridership:

 

                     27.7% below the poverty line

                     56.4% had no car available

 

Rider Ethnicity:

 

                     Latino 38.9%;

                     Black 13.1%;

                     White 25.8%;

                     Asian/Pacific Islander 15.2%;

                     Other 6.5%

 

In addition, these areas include Union Station to Downtown LA, Koreatown (Wilshire/Western), Hollywood, Universal City, and North Hollywood. 

 

Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

These recommendations support Metro Strategic Plan Goal No. 5) to “provide responsive, accountable, and trustworthy governance within the Metro organization”. This goal strives to position Metro to deliver the best possible mobility outcomes and improve business practices so that Metro can perform more effectively and adapt more nimbly to the changing needs of our customers.

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

The Board of Directors may choose not to authorize the contract award for this project; however, this alternative is not recommended as this project is critical to support the Purple Line Extensions, committed level of service to FTA, Olympic service need, and retirement the oldest HRVs in the fleet.

 

Next_Steps

NEXT STEPS

 

Upon Board approval of the Recommendations, a Contract will be executed and a Notice-to-Proceed will be issued to the Hyundai Rotem Company once all insurance and bonding requirements are met. Metro and the Hyundai Rotem Company will then mobilize required resources to ensure timely completion of deliverables by the Vehicle Contractor. Staff will also begin solicitation for consultant services to assist Metro with the Project Management/Control and Technical Support Services. Here are the top-level project milestones:

 

Board Award Approval                                                                                                         January 2024

Issue NTP                                                                                                                                                   February 2024

Pilot Car Delivery & Acceptance (6 cars)                                                               May 2027

Complete delivery of first 36 base order cars                                          April 2028

Complete delivery of all 182 base order cars                                          April 30, 2030 (NTP + 75 months)

 

Attachments

ATTACHMENTS

 

Attachment A - Procurement Summary

Attachment B - DEOD Summary

Attachment C - Funding & Expenditure Plan

 

Prepared_by

Prepared by:                      Annie Yang, Deputy Executive Officer, Operations Rail Vehicle Acquisitions (213) 925-1044
Jesus Montes, Sr. Executive Officer, Vehicle Engineering & Acquisitions (213) 418-3277
Matthew Dake, Deputy Chief Operations Officer, (213) 922-4061

Debra Avila, Deputy Chief Vendor/Contract Management Officer, (213) 418-3051

 

Reviewed_By

Reviewed by:                      Conan Cheung, Chief Operations Officer, (213) 418-3034