File #: 2018-0191   
Type: Informational Report Status: Agenda Ready
File created: 4/11/2018 In control: Construction Committee
On agenda: 5/17/2018 Final action:
Title: RECEIVE AND FILE this Office of the Inspector General report on Change Order/Modification Construction Spot Checks for the period ending February 28, 2018.
Sponsors: Construction Committee
Indexes: Budget, Budgeting, Capital Project, Construction, Construction management, Contractors, Contracts, Crenshaw/LAX Transit Corridor Project, Design build, Elevators, Escalators, Informational Report, Los Angeles International Airport, Metro Blue Line, Metro Crenshaw Line, Metro Exposition Line, Metro Gold Line, Metro Green Line, Metro Purple Line, Metro Rail A Line, Metro Rail C Line, Metro Rail D Line, Metro Rail E Line, Metro Rail K Line, Metro Rail L Line, Metro Vision 2028 Plan, Procurement, Program management, Project, Project management, Project Status Report, Regional Connector Transit Corridor Project, Tanks (Containers), Traffic control, Twenty-eight by '28 Initiative, Westside Subway Extension/Purple Line Extension Phase 1, Westside Subway Extension/Purple Line Extension Phase 2, Westside Subway Extension/Purple Line Extension Phase 3
Attachments: 1. Presentation
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Meeting_Body

CONSTRUCTION COMMITTEE

MAY 17, 2018

 

Subject

SUBJECT:                     OFFICE OF THE INSPECTOR GENERAL CHANGE

ORDER/MODIFICATION CONSTRUCTION SPOT

CHECKS

 

Action

ACTION:                     RECEIVE AND FILE

 

Heading

RECOMMENDATION

 

Title

RECEIVE AND FILE this Office of the Inspector General report on Change Order/Modification Construction Spot Checks for the period ending February 28, 2018.

 

Issue
ISSUE

 

On January 25, 2018, the Metro Board directed Office of Inspector General (“OIG”) to conduct random spot checks on the projects listed in the quarterly program management report to ensure that the delegation of authority to approve construction change orders policy is performing in the manner desired by the Board of Directors.

Discussion
BACKGROUND

 

I.                     SUMMARY

 

The OIG made four Spot Checks of approved Change Orders/Modifications exceeding $1 million each from four major transit construction projects:  Crenshaw/LAX, Regional Connector, Westside Purple Line Extension Section 1, and Westside Purple Line Extension Section 2.  We found that these Changes Orders were approved/executed on average 31.5 workdays (14, 35, 37, and 40 days) faster than the former Board approval process would have taken.  In addition, the negotiated cost for each Change Order appears reasonable:

                     First Spot Check - approved negotiated amount was $4,925 or 0.38% over Metro’s independent cost estimate (ICE),

                     Second Spot Check - approved negotiated amount was the same as the ICE,

                     Third Spot Check - approved negotiated amount was $222,174 or 9.2% under the ICE, and

                     Fourth Spot Check - issued a unilateral change that notified the Contractor to commence work while cost is being negotiated.

 

For the Change Orders/Modifications the OIG reviewed, some of the Spot Checks have shown that the delegation of authority has, in certain cases, resulted in:

                     Minimizing/reducing delay costs,

                     a negotiated amount that was reasonable for the work to be done; and

                     Minimizing construction delays.

 

This report also describes the new OIG program developed for the Construction Change Order Spot Checks and documents lessons learned that might be used to avoid future Change Orders.

 

II.                     OIG Program Description

 

The Program Management Department’s quarterly report identifies pending and approved construction project related change orders and modifications (collectively “Change Order(s)”) greater than $500,000.  The OIG has designed a spot check program (“Spot Checks”) which primarily focuses on approved change orders and modifications that exceed $1 million.  This program is accomplished by:

 

a.                     Reviewing a sample of Change Orders for a specified period identified in the Program Management Department’s Program Management Information System (PMIS), and Metro and Contractor documentation supporting execution of the change order;

b.                     Reviewing the Program Management Department’s Monthly Project Status Report (PSR);

c.                     Interviewing Project Managers, Program Controllers, and Procurement Officers with knowledge of the selected Change Order; and

d.                     Reviewing the Project Budget and Specifications or related documentation

 

 

For the selected Change Orders, the OIG Spot Checks focus on:

i.                     Scope of Work - matters such as:

a.                     Is the Change Order warranted?

b.                     Is it within the specifications?

c.                     Who is responsible for the cost of the change?

d.                     Are there any lessons learned?

e.                     Could the Change Order have been avoided?

f.                     Does the Change Order enhance safety?

g.                     Does the Change Order comply with applicable standards, rules, and regulations?

 

ii.                      Budget - matters such as:

a.                     Is the dollar amount of the Change Order within the Life of Project Budget?

b.                     Is the negotiated amount near Metro’s independent cost estimate (ICE)?

 

iii.                     Time to Execute Change Order - matters such as:

a.                     How many days did it take to execute the Change Order using the “new delegation” process? versus

b.                     How many days would it have taken to execute the Change Order using the former method of the Board approving the Change Order?  This Change Order processing time is predicated upon the Board report submission deadline to the Vendor/Contract Management department.

 

The OIG will periodically report to the Board on Spot Checks performed.

 

 

DISCUSSION

 

III.                     Spot Checks Performed in this Quarter

 

A.                     Spot Check#1 - Crenshaw/LAX Transit Project

 

This OIG Spot Check report concerns the Crenshaw/LAX Transit Project (Contract C0988), Modification (MOD-00345).  It was selected from the April Program Management Major Project Status Report (Board Item 32), covering December 2017, January 2018, and February 2018, of approved Change Orders greater than $1 million dollars.

 

Sources Reviewed

 

The information for this Spot Check was collected from the Program Management Department’s PMIS.  Also, in-person and telephonic interviews were conducted with Crenshaw Program Management, Project Control, and Procurement staff.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Facts

 

 

Conclusion

 

Scope of Work - In the original scope of work, the three Oil Water Separators (OWS) were to be located in the escalator pits for three underground stations (Expo, MLK, and Vernon).  During the review period, the Public Works Bureau of Sanitation Industrial Waste, City of Los Angeles, requested LA Metro to provide calculations for the capacity of the OWS.  The design criteria of the OWS to handle the combined load for the underground station track drain, elevators, and escalators was not clearly stated in LA Metro’s original design requirements.  When this matter was discovered, the concrete foundation for the three stations had already been poured; therefore, the contractor was unable to install a pit for the OWS as required by the City.  The agreed upon solution was to install the OWS “at grade” and have the oil and water mixture pumped up to the OWS.

 

Budget - The cost associated with this change order consists of: (1) designing and constructing an OWS for each of the three underground stations, (2) sizing an OWS large enough to hold the amount of water entering the station from a 1 hour rain event with 2 inch/hour rain intensity, and (3) designing calculations for drainage OWS outfall and the sewer outfall.  The Contractor’s proposed cost for this change was $1,678,678.  The Procurement team negotiated a reduction from the contractor’s proposal to $1,299,925, a reduction of $378,753.  The final total cost of $1,299,995 for all three underground stations is $4,925, or 0.38%, higher than Metro’s ICE amount of $1,295,000.

 

Schedule - The new delegation process allowed this change order to be initiated, processed, approved, and executed in a total elapsed time of 42 work days.  The previous Board approval process would have required at least 56 work days.  Using the former process, the earliest that this Change Order, submitted on December 11, 2017, could have been approved by the Board was the meeting on March 1, 2018 (February Board cycle). Thus, the new delegation process was 14 days quicker than the former process.

 

Recommendation

 

The Metro rail design criteria (MRDC) was updated on October 31, 2017, to reflect the addition of the elevator, escalator pit drain and underground station track drains to be processed through a clarifier to remove oil, grease, and sand.  Metro management should:

 

1.                     Update the “Lessons Learned” files regarding the OWS change to the MRDC and communicate the lesson to other Project Managers working major transit construction projects (This is consistent with recommendation 51 and 89p in the OIG’s Construction Management Best Practices Study.).

 

2.                     Investigate this change to determine:

a.                     If the scope of work of other major transit construction projects require this design update for the OWS.

b.                     If the Regional Connector and the Westside Purple Line Extension sections 1, 2, and 3 should be amended for the same OWS omission to reduce additional change orders and costs.

c.                     When should have the City been provided this information and reviewed construction plans prior to the cement being poured to avoid redesign costs.

 

 

B.                     Spot Check#2 - Regional Connector Transit Project

 

This Spot Check report concerns the Regional Connector Transit Corridor Project (Contract C0980).  Change Notice (CN-00166) was selected from the April Program Management Major Project Status Report (Board Item 32), covering December 2017, January 2018, and February 2018, of Change Orders greater than $1 million.  This Change Order has now been approved and is identified as Modification (C0980-MOD-00111).

 

Sources Reviewed

 

The information for this Spot Check was collected from the PMIS program. Also, in-person and telephonic interviews were conducted with Regional Connector Program Management, Project Control, and Procurement staff.

 

 

 

 

 

 

 

Facts

 

 

Conclusion

 

Scope of Work - During mining of the left tunnel, the Tunnel Boring Machine (TBM) struck an unforeseen steel object (I-beam) buried in its path.  This encounter damaged the TBM, which required repairs after new parts (3 large screws and 17 other components) were procured.  The scope of this modification includes: (1) engineering analysis of the broken screw, (2) repairs to the TBM, (3) a 32 calendar-day time extension for excusable/compensable delay (at $99,779 per calendar day), (4) mining delays and inefficiencies, (5) TBM - 24-hour acceleration, and (6) Flower Street surface heave repairs.  As mentioned above, the construction schedule was extended by 32 calendar days.

 

Budget - The cost associated with this Modification include excusable and compensable delays and repairs.  The Procurement team negotiated a $541,254 reduction from the contractor’s proposal of $7,603,491.  The final total cost for the Modification is $7,062,237, which is the same amount as in Metro’s ICE.

 

Schedule - The new delegation process allowed this Modification to be initiated, processed, approved, and executed in a total elapsed time of 29 work days.  Under the previous Board approval process, the earliest that this Modification could have been completed was 64 work days, since the Metro Board could not have approved the Modification until the May 24, 2018 Board Meeting (February 23, 2018 was the Metro initiated Change Order date.  The field Vendor\Contract Management staff deadline date for receipt of the change order request, was one (1) working day later on February 26, 2018.  Staff said they would not be able to perform their work and process the necessary paperwork that quickly, which would force the Change Order to the next Board meeting in May.). Thus, the new delegation process was 35 work days faster than the former process.

 

Recommendation

 

None

 

C.                     Spot Check#3 - Westside Purple Line Extensions - Section 1 Transit Project

 

The purpose of this report is to perform a Spot Check on the Westside Purple Line Extension - Section 1 Transit Project (Contract C1078).  The Change Notice (CN-11) was selected from the April Program Management Major Project Status Report (Board Item 32), covering December 2017, January 2018, and February 2018, of Change Orders greater than $1 million. This Change Order has been approved and is a Modification (C1078-MOD-00011).

 

Sources Reviewed

 

The information for this Spot Check was collected from the PMIS program.  Also, in-person and telephonic interviews were conducted with Westside Purple Line - Section 1 Program Management, Project Control, and Procurement staff.

 

Facts

 

 

Conclusion

 

Scope of Work - During the hazardous material investigation by Metro’s environmental remediation contractor, multiple underground storage tanks and buried reinforced concrete slabs were discovered.  The abatement remediation contractor had to remove these items and excavate all contaminated soil.  The hazmat abatement plan caused a schedule extension of an additional 253 unplanned days, which affected the Design-Builder’s critical path schedule.  Modification of the Scope of Work includes: compensation to the Design-Builder for all costs and schedule impacts for 253 calendar days at ($8,646 per calendar day).  The contract was extended a total of 253 days.

 

Budget - The cost associated with this Modification resulted in contractor compensation and time extension that were found excusable and compensable.  Metro’s ICE for this Modification was $2,409,650, and the Contractor’s proposal was $2,408,228.  The Procurement team negotiated a $220,752 reduction from the contractor’s proposal.  The final cost for this Modification is $2,187,476 or 9.2%, less than Metro’s ICE amount of $2,409,650.

 

Schedule - The new Delegation process allowed this Change Order to be initiated, processed, approved, and executed in a total elapsed time of 18 work days.  The previous Board approval process would have required at least 55 work days.  Using the prior process, the earliest that this Change Order, submitted on February 9, 2018, could have been approved by the Board was April 26, 2018.  Thus, the new process was 37 work days faster than the former process.

 

Recommendation

 

All Environmental Site Assessments were performed prior to excavation.  No record of underground tanks or buried reinforced concrete slabs were found by the Department of Conservation and Division of Oil, Gas, and Geothermal Resources (DOGGR). However, based on lessons learned from this site, Metro management should:

 

1.                     Conduct Ultrasonic Soil Examinations at future questionable sites to attempt to avoid unidentified hazards.  This is consistent with recommendations (88b, 88c, and 88d) in the OIG’s report on Capital Project Construction Management Best Practices Study (February 29, 2016).

 

2.                     Perform research to determine who could have installed the tanks and buried reinforced concrete slabs, and provide this information to the LA Metro Legal department for consideration of possible legal action to recover the cost of remediation under the Comprehensive Environmental Response, Compensations and Liability Act of 1980 (CERCLA).

3.                     Perform an assessment of the schedule to determine if any recovery of time is possible.

 

 

 

 

 

 

D.                     Spot Check#4 - Westside Purple Line Extension - Section 2 Transit Project

 

The purpose of this Spot Check report concerns the Westside Purple Line Extension - Section 2 Transit Project.  The Change Order (CO-00002) was selected from the April Program Management Major Project Status Report (Board Item 32), covering December 2017, January 2018, and February 2018, of Change Orders greater than $1 million.

 

Sources Reviewed

 

The information for this Spot Check was collected from the PMIS program.  Also, in-person and telephonic interviews were conducted with Westside Purple Line Extension - Section 2 Program Management, Project Control, and Procurement staff.

 

Facts

 

 

Conclusion

 

Scope of Work - The Master Schedule assumes each utility would provide their own traffic control plans.  Southern California Gas (SCG) and AT&T are scheduled to perform Advanced Utility Relocation (AUR) at the same time within close proximity of each other.  To mitigate potential work and schedule conflicts, both utilities have agreed to allow the Design Build Contractor to perform the overall traffic control.

 

Budget - This Change Order is a unilateral contract change by Metro.  The Change Order allows the Contractor to commence work and invoice for work performed while a final modification is negotiated.  Only a portion of the ICE has been issued to the contractor; negotiations have not been established at the time this report was written.

 

Schedule - The new Delegation of Authority process allowed this unilateral change to be initiated, processed, approved, and executed in an elapsed time of 34 work days.  Under the previous Board approval process, the earliest that this could have been completed was 74 work days, since the Metro Board could not have approved the change until the March 22, 2018 Board Meeting.  Thus, the new delegation process was 40 work days faster than the former process.

 

Recommendation

 

Metro management should:

1.                     Establish a single party to serve as a “clearinghouse” for all utilities relocations during construction.  The “clearinghouse” could be assumed by the Metro group, Third Party Administration.  (This is consistent with recommendations 80, 88, 89, 89j, 89n, and 89v in the OIG’s report on Capital Project Construction Management Best Practices Study.) 

 

2.                     Utilize the “clearinghouse” process to improve the Advance Utility Relocations.  (Consistent with recommendations 79, 83, 87, 89b, 89c, 89d, 89g, 89h, 89s, and 89t in the Best Practices Study.)

 

3.                     Create “Lessons Learned” for the establishment of a single clearinghouse in the initial scope of work for the Design Build Contractor to avoid future costly change orders.  (This is consistent with recommendation 89p in the Best Practices Study.)

 

Next_Steps
NEXT STEPS

The Office of Inspector General will continue reporting to the Board the results of Construction Change Order Spot Checks selected from the Program Management Major Project Status Quarterly Report. The next OIG Construction Spot Check report will be in July.

 

Prepared_by

Prepared by: Suzanna Sterling, Construction Specialist Investigator, (213) 244-7368

                                          

Reviewed_By

Reviewed by: Karen Gorman, Inspector General, (213) 244-7337