File #: 2024-0435   
Type: Informational Report Status: Agenda Ready
File created: 6/10/2024 In control: Construction Committee
On agenda: 7/17/2024 Final action:
Title: RECEIVE AND FILE status report on Program Management quarterly changes.
Sponsors: Board of Directors - Regular Board Meeting
Indexes: Budgeting, Capital Project, Construction, Informational Report, Pilot studies, Program Management
Attachments: 1. Attachment A - Quarterly Change Orders Log for 030124 – 053124, 2. Attachment B - OIG Con. Change Order Spot Checks (Thru May '24), 3. Presentation
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Meeting_Body

CONSTRUCTION COMMITTEE

JULY 17, 2024

 

Subject

SUBJECT:                     PROGRAM MANAGEMENT QUARTERLY CHANGE REPORT

 

Action

ACTION:                     RECEIVE AND FILE

 

Heading

RECOMMENDATION

 

Title

RECEIVE AND FILE status report on Program Management quarterly changes.

 

Issue
ISSUE

 

This board report provides a summary of quarterly contract changes for capital projects greater than $500,000 that are managed by Program Management. This report covers change activities for the reporting period between March 1, 2024 - May 31, 2024.

 

Background

BACKGROUND

 

In January 2017, the Board approved a one-year pilot program to delegate to the CEO the authority to execute project agreements up to the Life-of-Project (LOP) budget for the Crenshaw/LAX, Regional Connector, and Purple Line Extension Section 1 & 2 projects.  The purpose of the pilot program was to save time and minimize disruption due to the typical contract change administration approval process.

 

The pilot program was effective, generated cost savings, and avoided costly construction delays. At the January 26, 2018 Board meeting, the Board approved the continuation and expansion of the delegation of authority within the LOP budget on all Transit and Regional Rail Capital Projects.  Staff was directed to provide quarterly reports to the Board on change orders and modifications that are above $500,000 (Attachment A).  CEO Board delegated authority of changes is very beneficial to expedite contract changes and avoid costly construction delays. The Office of Inspector General (OIG) performs spot checks of change orders and modifications quarterly and quantifies time saving on each reviewed change based upon delegated authority. (Attachment B).  Since inception of the program based on OIG spot checks up to 2,765 concurrent workdays or concurrent 10.7 years, aggregated across the program, have been saved.

 

Discussion
DISCUSSION

 

The change activities for the reporting period between March 1, 2024 - May 31, 2024 are included in Attachment A.

Equity_Platform

EQUITY PLATFORM

 

Westside Purple Line Ext 1

Equity - This project is not located within or adjacent to Equity Focus Communities

Westside Purple Line Ext 2

Equity - This project is not located within or adjacent to Equity Focus Communities

Westside Purple Line Ext 3

Equity - 1 of 2 stations (50%) are within or adjacent to Equity Focus Communities

Division 20

Equity - 100% of the project is within or adjacent to Equity Focus Communities

Airport Metro Connector

Equity - 100% of the project is within or adjacent to Equity Focus Communities

Rail to Rail

Equity - 90% of the project is within or adjacent to Equity Focus Communities

I-105 Express Lanes

Equity - 92% of the project is within or adjacent to Equity Focus Communities

I-605 South Street Interchange Improvements

Equity - This project is not located within or adjacent to Equity Focus Communities

 

 

Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

The report supports strategic plan goal # 5 to provide responsive, accountable, and trustworthy governance within the Metro organization by keeping the Board informed of the Projects’ change orders and modifications via submitting the Change Order log on a quarterly basis.

 

Next_Steps
NEXT STEPS

 

The next Program Management Quarterly Change Report will cover the period of June 1, 2024 through August 31, 2024 and will be presented to the October 2024 Construction Committee.

 

Attachments

ATTACHMENTS

 

Attachment A - Quarterly Change Orders Log for Reporting Period of March 1, 2024 - May 31, 2024

 

Attachment B - OIG Construction Change Order Spot Checks CEO Delegated Authority Delays Avoided (Through May 2024)

 

Prepared_by

Prepared by:

                     Westside Purple Line Ext 1 - James Cohen, Senior Executive Officer, Projects Engineering, (323) 900-2114

                     Westside Purple Line Ext 2 - Michael McKenna, Senior Executive Officer, Projects Engineering, (424) 551-4447

                     Westside Purple Line Ext 3 - Kimberly Ong, Senior Executive Officer, Projects Engineering, (424) 551-4501

                     Division 20 Portal - Albert Soliz, Deputy Executive Officer, Project Management, (213) 922-4002

                     Airport Metro Connector - Rafie Zamani, Executive Officer, Projects Engineering, (213) 418-3140

                     Rail to Rail - Rafie Zamani, Executive Officer, Projects Engineering,, (213) 418-3140

                     I-105 Express Lanes - James Wei, Deputy Executive Officer, Program Management, (213) 922-7258

                     I-605 South Street Interchange Improvements - Brad Owen, Senior Executive Officer, Program Management, (213) 418-3143

                     Report - Julie Owen, Senior Executive Officer, Program Control, (213) 922-7313

 

 

Reviewed_By

Reviewed by:

Tim Lindholm, Chief Program Management Officer (Interim), (213) 922-7297