File #: 2023-0586   
Type: Informational Report Status: Agenda Ready
File created: 9/11/2023 In control: Construction Committee
On agenda: 10/19/2023 Final action:
Title: RECEIVE AND FILE Quarterly Status Report on Program Management change orders.
Sponsors: Board of Directors - Regular Board Meeting
Indexes: Budgeting, Construction, Informational Report, Program Management
Attachments: 1. Attachment A - Quarterly Change Orders Log for Reporting Period of 06/01/23 - 08/31/23, 2. Attachment B - OIG Construction Change Order Spot Checks
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Meeting_Body

CONSTRUCTION COMMITTEE

OCTOBER 19, 2023

 

Subject

SUBJECT:                     PROGRAM MANAGEMENT QUARTERLY CHANGE REPORT

 

Action

ACTION:                     RECEIVE AND FILE

 

Heading

RECOMMENDATION

 

Title

RECEIVE AND FILE Quarterly Status Report on Program Management change orders.

 

Issue
ISSUE

 

This board report provides a quarterly update from Program Management on change orders related to our capital program which are greater than $500,000.  Greater detail is provided in Attachment A - Quarterly Change Orders Log for Reporting Period of June 1, 2023 - August 31, 2023.

 

Background

BACKGROUND

 

In January 2017, the MTA Board approved a one-year pilot to delegate the CEO the authority to execute project agreements up to the Life-of-Project (LOP) budget for the Crenshaw/LAX, Regional Connector, and Purple Line Extension Section 1 & 2 projects.  The purpose of the pilot was to save time and minimize disruption due to the typical contract change administration approval process.

 

The pilot program was effective, generated cost savings and avoided costly construction delays. At the January 26, 2018 Board meeting, the Board approved the continuation and expansion of the delegation of authority within Life of Project (LOP) budget management on all Transit and Regional Rail Capital Projects.  Staff was directed to provide quarterly reports to the Board on change orders and modifications that are above $500,000.  CEO Board delegated authority of changes is very beneficial to expedite contract changes and avoid costly construction delays. Since inception of the program up to 2,438 concurrent workdays or concurrent 9.4 years, aggregated across the program, have been saved. (For more information, refer to Attachment B entitled OIG Construction Change Order Spot Checks CEO Delegated Authority Total Delays Avoided). 

 

Discussion
DISCUSSION

 

The change activities for the reporting period between June 1, 2023 - August 31, 2023 are included in Attachment A.   

 

Financial_Impact
FINANCIAL IMPACT

 

The changes included in this report are included in the approved life-of-project budget for each project.

 

Equity_Platform

EQUITY PLATFORM

 

Crenshaw/LAX

Equity - 8 of 8 stations (100%) are within or adjacent to Equity Focus

Westside Purple Line Ext 1

Equity - This project is not located within or adjacent to Equity Focus Communities

Westside Purple Line Ext 2

Equity - This project is not located within or adjacent to Equity Focus Communities

Westside Purple Line Ext 3

Equity - 1 of 2 stations (50%) are within or adjacent to Equity Focus Communities

Division 20

Equity - 100% of the project is within or adjacent to Equity Focus Communities

Metro Center Project (ESOC)

Equity - This project is not located within or adjacent to Equity Focus Communities

 

Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

The recommendation supports strategic plan goal # 5 to provide responsive, accountable, and trustworthy governance within the Metro organization by keeping the Board informed of the Projects’ change orders and modifications via submitting the Change Order log on a quarterly basis.

 

Next_Steps
NEXT STEPS

 

The next Change Order Log will cover the period of September 1, 2023 through November 30, 2023 and will be presented to the January 2024 Construction Committee.

 

Attachments

ATTACHMENTS

 

Attachment A - Quarterly Change Orders Log for Reporting Period of June 1, 2023 - August 31, 2023

 

Attachment B - OIG Construction Change Order Spot Checks CEO Delegated Authority Delays Avoided

 

Prepared_by

                     Crenshaw/LAX - Sameh Ghaly, Deputy Chief Program Management Officer, (213) 418-3369

                     Westside Purple Line Ext 1 - James Cohen, Senior Executive Officer, Projects Engineering (Interim), (323) 900-2114

                     Westside Purple Line Ext 2 - Michael McKenna, Senior Executive Officer, Projects Engineering (Interim), (424) 551-4447

                     Westside Purple Line Ext 3 - Kimberly Ong, Senior Executive Officer, Projects Engineering (Interim), (424) 551-4501

                     Division 20 Portal - Albert Soliz, Deputy Executive Officer, Project Management, (213) 922-4002

                     Soundwall Package 10 - Tim Lindholm, Deputy Chief Program Management Officer, (213) 922-7297

                     Metro Center Project - Albert Soliz, Deputy Executive Officer, Project Management, (213) 922-4002

                     Gold Line Foothill 2B - Tim Lindholm, Deputy Chief Program Management Officer, (213) 922-7297

                     Metro G Line Improvements - Tim Lindholm, Deputy Chief Program Management Officer, (213) 922-7297

                     1-105 Express Lanes - Tim Lindholm, Deputy Chief Program Management Officer, (213) 922-7297

                     Report - Julie Owen, Senior Executive Officer, Program Control, (213) 922-7313

 

Reviewed_By

Reviewed by:

Darcy Buryniuk, Chief Program Management Officer (213) 922-2250