Meeting_Body
OPERATIONS, SAFETY, AND CUSTOMER EXPERIENCE COMMITTEE
NOVEMBER 19, 2026
Subject
SUBJECT: ZERO EMISSION BUS (ZEB) PROGRAM UPDATE
Action
ACTION: RECEIVE AND FILE
Heading
RECOMMENDATION
Title
RECEIVE AND FILE status update on the ZEB Program.
Issue
ISSUE
This report provides a status update on the ZEB transition plan, including bus acquisition, division electrification, and upcoming program activities.
Background
BACKGROUND
At its July 2017 meeting, the Board approved Motion 50 by Directors Bonin, Garcetti, Najarian, Hahn, and Solis (Attachment A), which endorsed a ZEB Strategic Plan to transition Metro’s entire bus fleet to zero-emission by 2030. This was contingent upon cost and performance equivalence with Compressed Natural Gas (CNG) buses, as well as continued advancements in charging infrastructure. In 2018, the California Air Resources Board (CARB)’s Innovative Clean Transit (ICT) regulation required all transit agencies in the state to operate zero-emission fleets by 2040. In addition, ICT ZEB purchase requirements for large transit agencies require 25% of bus purchases to be zero emission by 2023, 50% by 2026, and 100% by 2029.
Metro has met all state-mandated program requirements. Furthermore, since October 2020, Metro has powered its bus fleet with 100% Renewable Natural Gas. Since the Board endorsed the ZEB Strategic Plan, staff prepared a ZEB Master Plan in 2022 and a Master Plan Update in 2023. In September 2024, staff prepared a more detailed plan to deliver a 100% ZEB fleet by 2035. This ensures Metro can continue providing reliable bus service, including the availability of operations and maintenance funding to support the full seven million annualized revenue service hours planned through the NextGen Bus Plan.
At its April 2024 meeting, the Board approved Motion 31.1 by Directors Yaroslavsky, Bass, Krekorian, Dupont-Walker, and Solis (Attachment B), which directed staff to provide quarterly program updates beginning in January 2025 to the Operations, Safety, and Customer Experience Committee on progress toward accomplishing the ZEB transition plan. The Motion directed that the ZEB conversion schedule should ensure Metro’s ability to continue providing reliable bus service, including availability of operations and maintenance funding to support the full seven million annualized revenue service hours as planned through the NextGen Bus Plan.
In 2021, Metro electrified the G Line, which has accumulated more than six million miles of zero-emission service to date. In 2025, Metro installed all charging infrastructure to electrify the J Line. Electrification of Division 9 (El Monte) is currently in the commissioning phase, and design is underway for Divisions 18 (Carson) and 7 (West Hollywood).
Discussion
DISCUSSION
FY26 Program Milestones
In FY26, Metro’s ZEB program reached many critical bus, charging infrastructure, funding, and pilot milestones. These milestones include the following:
• Division 18 (Carson) & 7 (West Hollywood) Progressive Design Build Operate Maintain contract awarded
• Division 9 (El Monte) civil construction completed
• J Line charging infrastructure installed and commissioned
• G Line chargers replaced with new charging equipment
• 19 chargers installed across 5 divisions and stations, including Division 18, LAX Airport Connector, and the G Line.
• 70 new battery electric buses (BEBs) delivered
• Ebusco long-range BEB pilot completed
• Universal/Studio City Station, North Hollywood Transit Center, and Division 8 & 15 opportunity charging sites entered design phase
• Division 8 charge management system pilot initiated and completed
• $100,208,900 in funding secured comprised of $33,456,900 in federal and $66,751,000 in state funding
Current ZEB Fleet and Incoming Deliveries
Metro currently owns 143 ZEBs (representing 6.7% of the total bus fleet). An additional 2 BYD K9MD model buses are pending delivery.
Repairs to the BYD K9MDs remain a priority to restore electrification on the J Line fully. Approximately 50% of weekday service and 70% of weekend service on the J Line is currently zero-emission.
Shortly after the K9MDs were placed in revenue service in December 2025, several reducer failures led to the discovery of a fleet defect affecting 26 K9MD buses. A reducer in an electric bus is the gearbox that converts high speed motor output into usable wheel speed and torque while mechanically coupling the motor to the drive axle or wheel. Fifteen buses have been fixed with replacement reducers, but additional issues have been discovered, including oil transfer/contamination and the axle components not being centered. BYD has not provided an adequate root cause analysis or a long-term solution for this critical system issue.
As of the end of October, 49 out of 85 K9MDs assigned to divisions are out of service due to reducer issues, door problems, structural defects, and other mechanical failures.
Metro will receive a transfer of 19 New Flyer BEBs from Lane Transit District in FY27, with an average age of 4 years, pending final regulatory approvals.
New Bus Acquisitions
Additional ZE Bus Acquisitions are currently in process and include the following:
• Contract awarded in October to ENC (ElDorado National) for a base order of 220 40’ BEBs with options of up to 1,600
• In the process of placing an order for 26 40’ BEBs with Solaris Bus and Coach North America through the Washington State Department of Enterprise Services contract
Division Electrification
Metro’s bus fleet operates from 10 directly operated and two contract-operated bus divisions. Metro’s current plan to electrify its fleet anticipates the electrification of all bus divisions no later than 2035.
Since the last program update, Division 9 (El Monte) commissioning activities have advanced. Two of four charging clusters were commissioned, releasing 60 charging positions under the gantry for bus operations. Commissioning activities will continue through the end of the calendar year.
Divisions 18 (Carson) & 7 (West Hollywood) are approaching 30% design. Through the Progressive Design Build Operate Maintain (PDBOM) delivery approach, Metro staff are collaborating with the Contractor to develop the best solution for Metro’s charging needs. The project will construct charging infrastructure to power more than 400 BEBs between the two divisions. Metro has also submitted its application to the Southern California Edison Charge Ready Transport incentive program and expects to execute the agreement by the end of the calendar year, before the program’s sunset date.
Funds for Division 2 (Los Angeles) electrification, the next division in the sequence, and the subsequent divisions have not yet been secured. While staff continues to advance an aggressive grant strategy for the ZEB program, funding shortfalls represent a schedule risk for program delivery. In the event of a funding shortfall for full electrification of Division 2, the project could be scaled to available funding. Staff will continue to seek grant opportunities for the project.
In September, staff released an RFP for a battery energy storage system (BESS) charging pilot project. The project will evaluate the viability of using grid-independent batteries to power charging equipment. BESS charging represents one approach to enhancing resiliency of charging equipment during a grid power outage. In the event of an outage, chargers connected to the BESS would remain available to charge Metro’s BEB fleet. Staff continue to explore this and other strategies that will help ensure resilient power systems and reliable service delivery as the agency integrates BEBs into its fleet.
En Route Charging Projects
Several stations across Metro’s bus network have been identified as candidates to install en route charging to support BEBs that operate on lines with long bus blocks that cannot be completed without additional charging time during the workday. These lines include the North San Fernando Valley Transit Improvements Project, North Hollywood to Pasadena BRT, G Line, and J Line.
Construction at Pasadena City College began in July 2026, and opportunity charger installation is scheduled to begin later this calendar year. Opportunity charging position design for North Hollywood Transit Center, Universal/Studio City Station, and Divisions 8 (Chatsworth) & 15 (Sun Valley) has surpassed 30%. The team has procured charging equipment, submitted utility requests, and targeted construction for 2028.
Equity_Platform
EQUITY PLATFORM
This ZEB program update provides a general status update on program activities. Advancing bus acquisitions and division electrification projects will improve air quality and public health by reducing vehicle emissions. These impacts will benefit some of LA County’s most vulnerable communities, many of which are Metro Equity Focus Communities (EFC). Division 9 (El Monte) is located within a Very High Need EFC, and 59% of the total communities served by bus service from this division are designated EFCs. Total communities with bus service from Divisions 18 (Carson) and 7 (West Hollywood), the next two divisions to be electrified, consist of 70% and 52% EFCs, respectively. Division 2 (Los Angeles) resides within an EFC, and 68% of the total communities served by Metro bus service from this division are designated EFCs.
Vehicle_Miles_Traveled_Outcome
VEHICLE MILES TRAVELED OUTCOME
VMT and VMT per capita in Los Angeles County are lower than national averages, the lowest in the SCAG region, and on the lower end of VMT per capita statewide, with these declining VMT trends due in part to Metro’s significant investment in rail and bus transit.* Metro’s Board-adopted VMT reduction targets align with California’s statewide climate goals, including achieving carbon neutrality by 2045. To ensure continued progress, all Board items are assessed for their potential impact on VMT.
As part of these ongoing efforts, this item is expected to contribute to further reductions in VMT. This item supports Metro’s systemwide strategy to reduce VMT through operational activities that will maintain and further encourage transit ridership, ridesharing, and active transportation. Metro’s Board-approved VMT reduction targets were designed to build on the success of existing investments, and this item aligns with those objectives.
*Based on population estimates from the United States Census and VMT estimates from Caltrans’ Highway Performance Monitoring System (HPMS) data between 2001-2019.
Implementation_of_Strategic_Plan_Goals
IMPLEMENTATION OF STRATEGIC PLAN GOALS
The report supports Goal #3 to enhance communities and lives through mobility and access to opportunity as well as Goal #4 to transform LA County through regional collaboration and national leadership.
Next_Steps
NEXT STEPS
Staff will continue delivering the depot charging infrastructure projects at Divisions 9 (El Monte), 18 (Carson), and 7 (West Hollywood). For BEB acquisition, staff will finalize contract awards and initiate bus orders.
Attachments
ATTACHMENTS
Attachment A - Board Motion 50 Strategic Plan for Metro’s Transition to Zero Emission Buses
Attachment B - Board Motion 31.1 Related to Item 31: Zero Emission Bus Program Update
Prepared_by
Prepared by: S. Miller, Deputy Executive Officer, Project Management
A. Romero, Deputy Executive Officer, Project Management
M. Dake, Deputy Chief Operations Officer, Vehicle Maintenance & Engineering
Reviewed_By
Reviewed by: C. Cheung, Chief Operations Officer