Subject
SUBJECT: WESTSIDE PURPLE LINE EXTENSION SECTION 2
Action
ACTION: APPROVE RECOMMENDATION
Heading
RECOMMENDATION
Title
AMEND the Life-of-Project (LOP) budget for the Westside Purple (D) Line Extension Section 2 Project (Project) by $296,000,000 from $2,574,969,299 to $2,870,969,299 using the fund sources as summarized in Attachment A and consistent with the provisions of the Board-adopted Measure R and Measure M Unified Cost Management Policy (Attachment B).
Issue
ISSUE
The Project is in its ninth year of construction and is 95% complete as of September 2026. To date, the Project has experienced unexpected conditions and unanticipated additional cost obligations that have drawn down the Project Contingency below the 3% Project reserve threshold which means there may be insufficient funds to cover the remaining costs required for Project completion.
The LOP budget increase request accounts for costs of settlement of a time-related claim that has been in negotiations with the Design-Build contractor, provides additional funding that is needed for additional construction costs, real estate, and professional services impacted by schedule delays, and provides contingency to account for potential future impacts and risks to the Project.
Background
BACKGROUND
The Project is the second of three sections of the nine-mile Purple (D) Line Extension. The Project runs westward from the recently opened Wilshire/La Cienega Station (that is part of the Section 1 Project) through Beverly Hills to Century City. The Project is located entirely underground, primarily following Wilshire Boulevard, and includes the design and construction of approximately 2.59 miles of double-track heavy rail subway and two new stations, as well as the purchase of 20 heavy rail vehicles. The Beverly Dr Station is within the jurisdiction of the City of Beverly Hills, and the Century City Station is within the jurisdiction of the City of Los Angeles.
At its January 2017 meeting <https://boardagendas.metro.net/board-report/2016-0971/>, the Metro Board approved the LOP Budget of $2,440,969,299 for the Project, excluding Finance Charges of $88,700,000. Metro awarded a 3,100-calendar day Design-Build Contract (C1120) to Tutor Perini/O&G (TPOG) and issued Notice to Proceed on April 26, 2017.
At its July 2023 meeting <https://boardagendas.metro.net/board-report/2023-0316/>, the Board authorized a $134,000,000 or 5.5% increase to the LOP budget. The 2023 LOP budget increase assumed the most favorable outcome for the issues and risks identified at that time. The 2023 LOP budget increase did not account for any time-related impacts due to excusable and compensable delays to the Design-Build Contract at that time. Furthermore, as indicated in the July 2023 Board Report, the FTA performed an independent 50% risk assessment in early February 2023. The assessment concluded that the budget (at that time) was insufficient. The FTA assessment model identified a shortfall of $232 million at the 65% confidence level for the Project in 2023. When in 2023 the Board authorized an amended LOP increase of $134 million, it resulted in a funding gap of $98 million as compared to the FTA assessment model value for the 65% confidence level for the Project.
Discussion
DISCUSSION
Findings
According to the policy adopted by the Board at its September 2012 meeting, the Board is required to be notified of the drawdown on Project contingency funds below the 3% Project reserve threshold to cover Project costs. The Metro Board was notified of the dip below the threshold via the February 2025 Monthly Project Status Report.
The Project’s Contingency drawdowns to date can be categorized into the following three major categories:
1. Previously Undefined Scope -$265,140,000
2. Professional Services -$127,670,000
3. Third Party Requirements -$80,160,000
All Contract Modifications and Change Orders have been subject to oversight from the Office of the Inspector General (OIG) and included in both the Program Management Major Project Status Reports and the Program Management Quarterly Change Reports regularly issued to the Board.
As of September 2026, the Project’s remaining unallocated contingency is $6,737,389. This is insufficient to support the Project through the end of construction.
The table below outlines the contingency drawdowns, and the remaining contingency as of September 2026:

A significant cost exposure that also developed since the 2023 LOP budget increase is a secondary tunnel liner which added approximately $75 million to the cost exposure to the C1120 Contract. This scope entailed procurement of special materials, disposal of previously procured material and construction and installation of a special secondary liner in both running tunnels.
Another significant cost exposure that developed since the 2023 LOP budget increase is a time-related claim that was submitted by TPOG. The original submitted amount for the claim was over $200 million. Additionally, the contractor submitted other claims and notices of intent to claim that increased the potential value of the disputed issues to over $357 million. The time-related claim was reviewed with TPOG, discussed and a final settlement amount of $151 million was negotiated as final compensation for the disputed issues.
Lessons Learned
• Metro has applied lessons learned and more collaborative forms of project delivery (Progressive Design-Build and CM/GC) to move away from specifying rain days by month as historical data and projections by month were prone to inaccuracy, especially given the increasing unpredictability of weather patterns.
• Metro to better define requirements for permanent design of new utilities to avoid disputes / delays with City and contractor (significant cause of storm drain / sewer delays at CCS).
• Metro has implemented new geotechnical procedures (not available at time PLE 2 contract awarded to TPOG) to better identify subsurface obstructions and avoid/minimize potential claims by contractors.
• Confirm rates of liquidated damages and cap on liquidated damages are sufficient (but risk of higher bid price).
• New Master Cooperative Agreement with City of Los Angeles (not available at time PLE2 contract awarded to TPOG) will enable expedited reviews by City for Metro projects and expedited dispute resolution, where necessary.
Summary
The settlement also resulted in a revision to the C1120 Contract milestone dates. The revised forecast for substantial completion shifts from Spring 2027 to Fall 2027.
In addition to the C1120 Contract, there are other time-related cost exposures to the Project that have accrued or might be expended in the future. These costs include real estate and professional services, as well as the replenishment of the contingency in the Project LOP, based on open risks and potential Project time adjustments before the planned Revenue Service Date.
In summary, the table below provides a breakdown of potential future cost exposures:
Project staff will continue to assess ongoing and future Project risks and the potential impact they may have on the Project, while continuing to manage risks to control costs and schedule.
Metro Cost Benefit Analysis and Economic Impact
At its July 2025 meeting <https://boardagendas.metro.net/board-report/2025-0543/>, the Board approved a methodology framework for a Cost Benefit Analysis (CBA) to be conducted on Metro capital projects at key milestones to support investment and funding decisions, such as increases to LOP budgets.
As part of the CBA, a Benefit Cost Ratio was conducted to compare monetized costs of the Project, including the latest LOP capital cost, as well as anticipated maintenance and operating costs, to a set of monetizable benefits of the Project. While not all Project benefits and costs are monetizable, the Metro BCR analysis does include monetized values of travel time savings, accident cost savings, emission cost savings, and active transportation health benefits over a 20-year operating period, through 2047.
Regional economic benefits also are included, which are created from the Metro investment in the Project construction and operation and from the expected increase in ridership that provides access to jobs and personal consumption. The economic benefits from the increased ridership and mobility extend beyond the effects of construction, operations and maintenance spending, which were previously calculated by LAEDC, (on behalf of Metro), and reported publicly by Metro.
Together, the CBA and evaluation of regional economic impact find that with an increased LOP Budget, the PLE2 segment performs as follows:
• For every dollar invested, the Project is expected to produce approximately $6.97 in monetizable benefits for the region over 20 years after starting revenue service.
• The total Project investment (on capital, operations and maintenance) is estimated to generate an annual average of [1,016] new jobs and about $9.0 billion in economic output for the Los Angeles County economy through FY 2047 (in 2026 dollars). The economic output is due to direct spending on construction and operations, indirect spending on supporting industries (materials and services), and induced spending by the workers that are supported by the Project.
• The Project improves regional mobility, as it expands the heavy rail system and results in an estimated 20,300 new daily additional rail boardings in 2035. This increase is expected to provide access to employment and create an annual average of 13,094 new jobs. The increased employment is expected to generate additional economic activity and sales of goods and services, increasing economic output in Los Angeles County. The improved mobility will also increase personal consumption and the sale of goods and services. Total economic output is estimated to increase by 80 billion from 2028 to 2047 due to the Project’s mobility improvements.
Determination_Of_Safety_Impact
DETERMINATION OF SAFETY IMPACT
This Board action will not have an impact on established safety standards for Metro’s construction projects.
Financial_Impact
FINANCIAL IMPACT
Adoption of the recommended action would increase the Project’s LOP budget by $296 million, funded by Measure R 35% through the proposed funding strategy below.
Impact to Budget
Funds required for fiscal year 2027 are included in the FY27 Adopted Budget.
Since this is a multi-year capital Project, the Chief Program Management Officer and the Project Manager are responsible for budgeting costs in future fiscal years.
The sources of funds for the recommended actions are Federal New Starts and local Measure R 35% Transit Capital. These funds are not Subregional Equity Program funds and are not eligible for operating costs.
Multi-year Impact
The sources of funds for the Project are capital funds identified in the recommended Funding/Expenditure Plan as shown in Attachment A. With respect to the requested $296,000,000 increase, Attachment B shows the Measure R and Measure M Unified Cost Management Policy (the Policy) analysis and funding strategy required for cost increases to Measure R projects.
This report identifies additional funding resources consistent with the Policy approved by the Board in 2018. Attachment B provides a detailed discussion of the Policy. In summary, the Policy was developed in recognition that some projects would need additional funding. The Policy provides a consistent and equitable process to ensure that any financial impacts are limited to the local area where the Project is located and does not have a region-wide impact.
To comply with the Policy of the Metro Board of Directors, Metro staff has evaluated potential offsetting cost reductions, including scope reductions, value engineering, and shortening segments. Because the Project is so far along, these actions are no longer feasible. Additional funding is the only option.
The source of funds to address the LOP budget increase is Measure R 35 Transit Capital. The Measure R ordinance includes $4,074,000,000 that can be expended on the Project, and the Board has previously approved transfers of Measure R from other Measure R projects to the Westside Subway Extension totaling $415,391,156, making a total of $4,489,391,156 of Measure R for the Westside Subway Extension Sections 1, 2, and 3, and for Division 20. Measure R has been fully programmed to these projects, but $296,000,000 of Measure R from Division 20 can be made available for the Project by programming Proposition A 35 to Division 20 as a replacement. Division 20 is eligible for Proposition A 35 because it is mostly above ground and not new subway, which is prohibited from use due to The Act of 1988.
Equity_Platform
EQUITY PLATFORM
The Project will enhance service frequency, reliability and accessibility for communities relying on the Metro transit system for housing, employment, education, healthcare and entertainment. This extension of the Purple (D) Line specifically extends access, via the opening of the Beverly Dr and Century City stations for riders of the system that travel along or connect to the Red (B) and Purple (D) Line Corridors. The Project expands community development and economic growth in Los Angeles and neighboring cities. By way of each new station, streamlining of public transit to Beverly Hills and Century City will also create more opportunities to explore the Westside to existing, new Metro customers and global visitors alike.
The U.S. Department of Transportation (USDOT) has issued an Interim Final Rule (IFR) that makes changes to the DBE Program and DBE regulations at 49 C.F.R. Part 26, effective October 3, 2025. During this transition period, certain provisions contained in the contract documents related to contract goals, enforcement, and counting of participation have been paused. To the extent provisions are not impacted by the application of the IFR, said provisions, such as prompt payment to all subcontractors, prior Metro written approval for termination and substitution of DBE firms, and adding subcontractors, remain effective.
Vehicle_Miles_Traveled_Outcome
VEHICLE MILES TRAVELED OUTCOME
VMT and VMT per capita in Los Angeles County are lower than national averages, the lowest in the SCAG region, and on the lower end of VMT per capita statewide, with these declining VMT trends due in part to Metro’s significant investment in rail and bus transit.* Metro’s Board-adopted VMT reduction targets align with California’s statewide climate goals, including achieving carbon neutrality by 2045. To ensure continued progress, all Board items are assessed for their potential impact on VMT.
As part of these ongoing efforts, this item is expected to contribute to further reductions in VMT. This item supports Metro’s systemwide strategy to reduce VMT through investment activities that will improve/benefit and further encourage transit ridership. Metro’s Board-adopted VMT reduction targets were designed to build on the success of existing investments, and this item aligns with those objectives.
Specifically, this Project will result in a reduction of Vehicle Miles Traveled (VMT) on the highway system, leading to decreased roadway congestion, pollutant emissions, and fossil fuel consumption. “The Locally Preferred Alternative (LPA) will have a beneficial effect on the regional transportation network by reducing VMT, Vehicle Hours Traveled (VHT), and peak-hour trips compared to both existing conditions and future projections. For example, in 2035, the LPA (Century City Constellation Option) is expected to result in approximately 581,000 fewer regional VMTs compared to the No Build Alternative." (Source: Westside Subway Extension, Final Environmental Impact Statement/Environmental Impact Report (EIS/EIR), January 2012).
*Based on population estimates from the United States Census and VMT estimates from Caltrans’ Highway Performance Monitoring System (HPMS) data between 2001-2019.
Implementation_of_Strategic_Plan_Goals
IMPLEMENTATION OF STRATEGIC PLAN GOALS
The recommendation supports Strategic Plan Goal Number 1 - Provide high-quality mobility options that enable people to spend less time traveling.
Alternatives_Considered
ALTERNATIVES CONSIDERED
The Board may choose not to move forward with amending the LOP budget. This is not recommended as Metro will be unable to provide funding to complete the Project according to the current schedule, as demonstrated by the FTA’s risk assessment.
The LOP Budget may be partially amended at this time; however, this is also not recommended since doing so would require the Project to return to the Board at a later date for approval of an additional LOP Increase.
Next_Steps
NEXT STEPS
Upon Board approval, the LOP budget will be amended as recommended.
Attachments
ATTACHMENTS
Attachment A - Funding/Expenditure Plan
Attachment B - Measure R and Measure M Unified Cost Management Policy Analysis
Attachment C - Projected Breakdown of Cost Allocation for $296,000,000
Prepared_by
Prepared by: Z. Varley, Sr. Executive Officer, Project Management
M. Martin, Deputy Executive Officer, Program Control
C. Hoshijima, Executive Officer, Countywide Planning
Reviewed_By
Reviewed by: T. Lindholm, Chief Program Management Officer
R. Sosa, Chief Planning Officer
M. Antonelli, Chief Vendor/Contract Management Officer