File #: 2019-0502   
Type: Contract Status: Agenda Ready
File created: 6/17/2019 In control: Construction Committee
On agenda: 7/18/2019 Final action:
Title: AUTHORIZE the Chief Executive Officer to NEGOTIATE and EXECUTE: A. A three-year cost plus fixed fee type contract for AE59600 with HDR Engineering, Inc. for Supplemental Engineering Services for Engineering Design of Transit Rail Projects on a task order basis, plus two one-year options. The amount for the three-year base contract is $50,000,000 and the amount for the two one-year options is $20,000,000 for a total contract value not to exceed $70,000,000; subject to resolution of protest(s), if any; and B. Individual Task Orders and modifications within the Board approved contract amount.
Sponsors: Construction Committee
Indexes: Airport Metro Connector (AMC) Station Project, Blue Line Improvement, Budgeting, Capital Improvement Program, Capital Project, Construction, Contracts, Emergency Operations Center, Gold Line Foothill Extension 2B, Grade separations, Heating, cooling and ventilation equipment, Maintenance of way, Measure M, Metro Blue Line, Metro Center Street Project, Metro Crenshaw Line, Metro Exposition Line, Metro Gold Line, Metro Green Line, Metro Orange Line, Metro Purple Line, Metro Rail A Line, Metro Rail C Line, Metro Rail D Line, Metro Rail E Line, Metro Rail K Line, Metro Rail L Line, Metro Vision 2028 Plan, Pico Station, Procurement, Professional Services, Project, Rail transit, Railroad facilities, Regional Connector Transit Corridor Project, Safety, State Of Good Repair, Strategic planning, Terminal 27, Traffic control, Twenty-eight by '28 Initiative, Westside Subway Extension/Purple Line Extension Phase 1, Westside Subway Extension/Purple Line Extension Phase 2, Westside Subway Extension/Purple Line Extension Phase 3, Willowbrook/Rosa Parks Station
Attachments: 1. Attachment A - Procurement Sumamry, 2. Attachment B - DEOD Summary, 3. File Summary, 4. File Summary, 5. Staff Report
Related files: 2019-0600
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Meeting_Body

CONSTRUCTION COMMITTEE

JULY 18, 2019

 

Subject

SUBJECT:                     SUPPLEMENTAL ENGINEERING SERVICES (SES) CONSULTANT SERVICE CONTRACT

 

Action

ACTION:                     AWARD PROFESSIONAL SERVICES CONTRACT

 

Heading

RECOMMENDATION

 

Title

AUTHORIZE the Chief Executive Officer to NEGOTIATE and EXECUTE: 

 

A.                     A three-year cost plus fixed fee type contract for AE59600 with HDR Engineering, Inc. for Supplemental Engineering Services for Engineering Design of Transit Rail Projects on a task order basis, plus two one-year options.  The amount for the three-year base contract is $50,000,000 and the amount for the two one-year options is $20,000,000 for a total contract value not to exceed $70,000,000; subject to resolution of protest(s), if any; and

 

B.                     Individual Task Orders and modifications within the Board approved contract amount.

 

Issue

ISSUE

Metro’s staff engineers, architects and CADD designers in the Engineering Group are currently fully engaged supporting our current Major Rail Transit Projects (Crenshaw, Regional connector and Purple Line sections 1, 2 and 3), Metro Emergency Security Operations Center (ESOC), Metro Capital Improvements projects (CIP) such as the Patsaouras Plaza project and the Willowbrook / Rosa Parks Station Improvement Project and the State of Good Repairs Projects (SOGR) such as the Metro Blue Line (MBL) Signaling Rehabilitation and Operational Improvements project, Metro Orange Line (MOL) Improvements and the I-210 Barriers Replacement project.

The passage of Measure M has added a considerable workload to the Metro Engineering group with projects that are starting or that are completing design in the next five years such as the Airport Metro Connector 96th Street Station (AMC), West Santa Ana Branch Transit Corridor, the Gold Line Foothill Extension to Claremont, and the BRT Connector Orange / Red Line to the Gold Line, which all have groundbreakings within the next five years.

In addition, important motions by Board of Directors require considerable engineering work to evaluate the feasibility and develop conceptual alternative designs to validate engineering solutions for the projects called by the motions: This includes, but not limited to the MBL Wardlow Grade Separation study, the MBL Washington/ Flower Wye Improvement or Grade Separation, and the Pico Station Grade Separation.

Background

BACKGROUND

The funding limit for our existing Supplemental Engineering Services (SES) contract (Contract No. AE36687) has almost reached its limit. This new SES will enable Metro the flexibility to supplement internal resources on an as-needed basis for the work detailed above, when we either do not have the sufficient capacity, or lack the particular expertise necessary to perform a particular specialty task in a timely manner. Metro Engineering staff does not possess the resources or, in some cases, technical expertise to carry out certain specialized tasks such as Traffic Control Plans, three-dimensional nonlinear soils-structure interaction analysis, Noise and Vibration Control or Corrosion Control. There is not currently a need for full-time resources for these specific specialties. Therefore, it is more efficient to use consultants on an as-needed basis.

Discussion

DISCUSSION

Metro Engineering has developed this SES Contract to supplement Metro’s engineering efforts. The SES consultant team shall be capable of supporting its engineering group’s technical disciplines. This Contract will be issued for a term of three years with two one-year optional extensions for a maximum total duration of five years. The Procurement Summary for this Contract is included as Attachment A.

This Contract called for the proposers to demonstrate their capabilities and technical expertise listed in the Statement of Work for this RFP. The technical proficiencies required for this SES contract (AE59600) are very comprehensive and include all engineering and specialties disciplines which Metro may require in support of its projects. These include the following:

General Services include:

1.                     Preliminary and Final Design of Transit Rail Projects.

2.                     Design Review Support & Coordination for CIP projects & other special projects.

3.                     Production of Project Status, Technical and Engineering Reports.

4.                     Design of Structures, Stations and Guideways.

5.                     Facilities/Systems Interface Coordination.

6.                     Surveying Services.

7.                     Cost Estimating.

8.                     Intra/Inter Disciplinary Coordination.

9.                     Scheduling and Cost Management for Task Orders.

10.                     Post Design Services including; Bid and Design Support during Construction.

11.                     Administrative Tasks associated with General Engineering Support Services.

Specific Rail Facilities and Third Party Utility Design Services include:

12.                     Engineering Services for Review and Approval of Metro Projects.

13.                     Development of Technical Specifications, Drawings and Reference Documents.

14.                     Engineering Services for support of Metro Rail Operations and Maintenance.

15.                     Land Surveying and Legal Description.

16.                     Potholing.

17.                     Geotechnical Services, Borings and Reports.

18.                     Civil & Utility Engineering

19.                     Drainage Design and Hydraulic Calculations.

20.                     Structural Engineering.

21.                     Bridges and Aerial Structure Design.

22.                     Tunnels, Trenches and Underground Station Design.

23.                     Track Work Engineering, Plan and Profile.

24.                     CPUC Grade Crossing Application including attendance to field diagnostic meetings.

25.                     Yard and Shop Rail Maintenance Facility Design.

26.                     Architectural Design.

27.                     Station Site Development.

28.                     Urban Design Integration.

29.                     Landscape Architecture.

30.                     Traffic Control Plans including Striping Drawings and Signal Drawings.

31.                     CADD and MicroStation Drawings.

32.                     BIM Services and Training.

33.                     Project Presentation including Three Dimensional Rendering.

34.                     Corrosion Control Measures and Cathodic Protection.

35.                     Value Engineering and Cost Reduction.

36.                     Noise and Vibration Analysis including Site Visits, Measurement and Mitigation.

37.                     Any other engineering or technical discipline not listed above that is ancillary to the Statement of Work and consistent with the general requirements of an approved Task Order.

38.                     HVAC design including HVAC and emergency ventilation.

39.                     Electrical Design.

40.                     Plumbing Design.

41.                     Fire  Protection Design

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

This SES Contract is not directly related to a specified safety issue. However, the services provided via this SES Contract will reduce Metro’s dependency on limited internal resources and, thus, is generally in support of safety initiatives.

 

 

Financial_Impact

FINANCIAL IMPACT

As specific engineering design or support needs arise, task orders will be issued and funded from the associated project budget, upon approval by the responsible Project Manager. 

Since this is a multi-year project, the Chief Program Management Officer, Project Managers and respective Cost Center Managers will be responsible for budgeting for costs of future task orders related to this contract.

Impact to Budget

The funding for the task orders are provided by the specific project requiring the services. The source for these funds are in line with the respective projects’ funding plans and fund sources may consist of federal and/or state grants as well as local funds. Many of the state of good repair projects are funded with local funding sources that are eligible for rail and bus operations.

 

 

Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

Supporting this recommendation supports Metro’s strategic plan goal 1. By supporting the recommendation for HDR Engineering, Inc. to provide supplemental engineering services, the Board is supporting strategic plan goal 1 which promotes trip reliability, reduces trip disruptions as well as deliver of world-class transit service by ensuring our transit assets are in a state of good repair.

 

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

1.                     Solicit qualifications proposals for each individual task when the requirement arises: This alternative is not recommended as it would require extensive additional staff time to process each individual task and would result in project delays due to the lead time required to complete each procurement cycle. Additionally, procuring services on a per-assignment basis would impose significant additional burden on the Engineering and Vendor/Contract Management departments.

2.                     Utilize existing engineering staff to provide the required technical support: This alternative is also not feasible as Metro’s current engineering capacity is fully utilized to support the existing major, CIP and SOGR projects. Due to these commitments, it is anticipated that the current staff would be challenged to provide the necessary additional technical support required for the up-coming capital projects which will be under concurrent development. If this alternative were exercised, Metro would need to hire additional staff with expertise in several currently underrepresented disciplines to perform this work. Such an action is not practical nor cost-effective.

 

Next_Steps

NEXT STEPS

Upon Board approval, staff will complete the process to award the contract. Specific task orders will then be issued on an as needed basis.

 

Attachments

ATTACHMENTS

 

Attachment A - Procurement Summary

Attachment B  -DEOD Summary

 

 

Prepared_by

Prepared by: Androush Danielians, Executive Officer (213) 922-7598

 