File #: 2024-0910   
Type: Informational Report Status: Agenda Ready
File created: 9/12/2024 In control: Construction Committee
On agenda: 10/23/2024 Final action:
Title: RECEIVE AND FILE status report on the Program Management Quarterly Change Report.
Sponsors: Board of Directors - Regular Board Meeting
Indexes: Budgeting, Capital Project, Construction, Informational Report, Program Management
Attachments: 1. Attachment A - Quarterly Change Orders Log for Period of 6/1/24 - 8/31/24, 2. Attachment B - OIG Con. Change Order Spot Checks, 3. Presentation
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Meeting_Body

CONSTRUCTION COMMITTEE

OCTOBER 23, 2024

 

Subject

SUBJECT:                     PROGRAM MANAGEMENT QUARTERLY CHANGE REPORT

 

Action

ACTION:                     RECEIVE AND FILE

 

Heading

RECOMMENDATION

 

Title

RECEIVE AND FILE status report on the Program Management Quarterly Change Report.

 

Issue
ISSUE

 

A summary of the use of Board delegated authority to the CEO for contract changes for transit and regional rail construction projects greater than $500,000 is provided quarterly.

 

Background

BACKGROUND

 

In January 2017, the Board approved a one-year pilot to delegate the CEO the authority to execute project agreements up to the Life-of-Project (LOP) budget for the Crenshaw/LAX, Regional Connector, and Purple Line Extension Section 1 & 2 projects.  The purpose of the pilot was to save time and minimize disruption due to the typical contract change administration approval process.

 

The pilot program was effective, generated cost savings, and avoided costly construction delays. At its January 2018 meeting, the Board approved the continuation and expansion of the delegation of authority within the LOP budget on all Transit and Regional Rail Capital Projects.  Staff was directed to provide quarterly reports to the Board on change orders and modifications that are above $500,000 (Attachment A).  Board delegated authority to the CEO of changes is very beneficial to expedite contract changes and avoid costly construction delays. Since inception of the program up to 2,765 concurrent workdays or concurrent 10.7 years, aggregated across the program, have been saved (Attachment B). 

 

Discussion
DISCUSSION

 

The change activities for the reporting period between June 1, 2024 - August 31, 2024 are included in Attachment A.

 

Equity_Platform

EQUITY PLATFORM

 

The following table summarizes Equity Focus Communities (EFC) percentage data for the projects covered in this report. Going forward, Program Management will complete an equity section baseline, which is expected to be included starting with the January 2025 Quarterly Change Report.

 

Regional Connector

Equity - 3 of 3 stations (100%) are within or adjacent to Equity Focus Communities

Westside Purple Line Ext 1

Equity - This project is not located within or adjacent to Equity Focus Communities

Westside Purple Line Ext 2

Equity - This project is not located within or adjacent to Equity Focus Communities

Westside Purple Line Ext 3

Equity - 1 of 2 stations (50%) are within or adjacent to Equity Focus Communities

Division 20

Equity - 100% of the project is within or adjacent to Equity Focus Communities

Airport Metro Connector

Equity - 100% of the project is within or adjacent to Equity Focus Communities

Soundwall Package 11

Equity - 25% of the project is within or adjacent to Equity Focus Communities

Rail to Rail

Equity - 90% of the project is within or adjacent to Equity Focus Communities

I-5 North County Enhancements

Equity - This project is not located within or adjacent to Equity Focus Communities

I-105 Express Lanes

Equity - 92% of the project is within or adjacent to Equity Focus Communities

East San Fernando Valley Transit Corridor

Equity - 70% of the project is within or adjacent to Equity Focus Communities

 

 

Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

The recommendation supports strategic plan goal # 5 to provide responsive, accountable, and trustworthy governance within the Metro organization by keeping the Board informed of the Projects’ change orders and modifications via submitting the Change Order log on a quarterly basis.

 

Next_Steps
NEXT STEPS

 

The next Program Management Quarterly Change Report will cover the period of September 1, 2024, through November 30, 2024, and will be presented to the January 2025 Construction Committee.

 

Attachments

ATTACHMENTS

 

Attachment A - Quarterly Change Orders Log for Reporting Period of June 1, 2024 - August 31, 2024.

 

Attachment B - OIG Construction Change Order Spot Checks CEO Delegated Authority Delays Avoided (Through August 2024)

 

Prepared_by

Prepared by:

                     Regional Connector - Mathew Antonelli, Deputy Chief Program Management Officer, (213) 893-7114

                     Westside Purple Line Ext 1 - James Cohen, Senior Executive Officer, Projects Engineering, (323) 900-2114

                     Westside Purple Line Ext 2 - Zephaniah Varley, Executive Officer, Projects Engineering, (424) 551-4449

                     Westside Purple Line Ext 3 - Kimberly Ong, Senior Executive Officer, Projects Engineering, (424) 551-4501

                     Division 20 Portal - Albert Soliz, Deputy Executive Officer, Project Management, (213) 922-4002

                     Airport Metro Connector - Rafie Zamani, Executive Officer, Projects Engineering, (213) 418-3140

                     Soundwall Package 10 - Mathew Antonelli, Deputy Chief Program Management Officer, (213) 893-7114

                     Soundwall Package 11 - Mathew Antonelli, Deputy Chief Program Management Officer, (213) 893-7114

                     Rail to Rail - Tim Lindholm, Chief Program Management Officer (Interim), (213) 922-7297

                     I-5 North Country Enhancements - Mathew Antonelli, Deputy Chief Program Management Officer, (213) 893-7114

                     I-105 Express Lanes - James Wei, Deputy Executive Officer, Program Management, (213) 922-7258

                     East San Fernando Valley Transit Corridor - Mathew Antonelli, Deputy Chief Program Management Officer, (213) 893-7114

                     Link Union Station - Michael McKenna, Deputy Chief Program Management Officer (Interim), (424) 551-4447

                     Report - Julie Owen, Senior Executive Officer, Program Control, (213) 922-7313

 

 

Reviewed_By

Reviewed by:

Tim Lindholm, Chief Program Management Officer, (213) 922-7297