File #: 2025-0842   
Type: Contract Status: Agenda Ready
File created: 9/17/2025 In control: Planning and Programming Committee
On agenda: 11/19/2025 Final action:
Title: AUTHORIZE the Chief Executive Officer to: A. EXECUTE Modification No.10 to Contract No. AE60979000 with Michael Baker International (MBI) in the amount of $4,833,337 to provide additional professional services for the Westbound State Route 91 - Alondra Boulevard to Shoemaker Avenue Improvements Project (WB SR-91) - Plans, Specifications and Estimate phase (PS&E) or Final Design, increasing the contract value from $12,614,738 to $17,448,075; and extending the period of performance from December 31, 2025 to December 31, 2030; B. AMEND the existing Cooperative Agreement with Caltrans to add $2,081,000 in funding to complete final design, prepare all necessary documents, and advertise, award, and approve the project for construction; and C. EXECUTE a third-party Cooperative Agreement with the Mountains Recreation and Conservation Authority (MRCA) to fulfill the Regional Water Quality Control Board (RWQCB) Section 401 permit compensatory mitigation requirement for this project's permanen...
Sponsors: Program Management (Department), Maria Luk
Indexes: "Hot Spots" Program, Americans With Disabilities Act, Artesia, Bicycling, Budgeting, Cerritos, Complete streets, Conservation, Construction, Contracts, Gateway Cities subregion, Grant Aid, I-405, I-5, I-605, I-605 Hot Spots- Wb (Westbound) Sr-91 Improvements From Alondra To Shoemaker (Project), Interchanges, Measure M, Measure R, Mitigation, Multimodal, National Environmental Policy Act Of 1969, Norwalk, Procurement, Professional Services, Project, Ramps (Interchanges), Safety, Sidewalks, Southern California Highways, Strategic planning, Traffic safety, Transfers, Water control
Attachments: 1. Attachment A - Project Location Map, 2. Attachment B - Existing Conditions, 3. Attachment C - Procurement Summary, 4. Attachment D - Contract Modification/Change Order Log, 5. Attachment E - DEOD Summary, 6. Presentation
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Meeting_Body

PLANNING AND PROGRAMMING COMMITTEE

NOVEMBER 19, 2025

 

Subject

SUBJECT:                     WESTBOUND STATE ROUTE 91 - ALONDRA TO SHOEMAKER IMPROVEMENT PROJECT

 

Action

ACTION:                     APPROVE RECOMMENDATION

 

Heading

RECOMMENDATIONS

 

Title

AUTHORIZE the Chief Executive Officer to:

 

A.                     EXECUTE Modification No.10 to Contract No. AE60979000 with Michael Baker International (MBI) in the amount of $4,833,337 to provide additional professional services for the Westbound State Route 91 - Alondra Boulevard to Shoemaker Avenue Improvements Project (WB SR-91) - Plans, Specifications and Estimate phase (PS&E) or Final Design, increasing the contract value from $12,614,738 to $17,448,075; and extending the period of performance from December 31, 2025 to December 31, 2030;

 

B.                     AMEND the existing Cooperative Agreement with Caltrans to add $2,081,000 in funding to complete final design, prepare all necessary documents, and advertise, award, and approve the project for construction; and

 

C.                     EXECUTE a third-party Cooperative Agreement with the Mountains Recreation and Conservation Authority (MRCA) to fulfill the Regional Water Quality Control Board (RWQCB) Section 401 permit compensatory mitigation requirement for this project's permanent wetland impacts, in the amount of $126,000.

 

Issue

ISSUE

 

The Modification for Contract No. AE60979000 is necessary to complete the Project’s final design, transfer the project to Caltrans to manage final design and construction, and prepare all required documents and approvals for advertisement, award, and construction. The modification will also support execution of the corresponding amendment to the existing Cooperative Agreement with Caltrans, which will define roles and responsibilities and provide funding for Caltrans staff to review the design work.

 

Through a separate agreement with the Mountains Recreation and Conservation Authority (MRCA), Metro-via Caltrans-will fund MRCA to implement restoration, preservation, and/or creation of habitat prior to any project-related disturbance or vegetation removal.

 

Background

BACKGROUND

 

The Project is located on SR-91 and Interstate 605 (I-605) in the cities of Artesia and Cerritos, from Shoemaker Avenue to the I-605 Interchange, and on I-605 from Alondra Boulevard to the I-605/SR-91 Interchange (Attachment A). Westbound SR-91 is a critical transportation and goods movement corridor within Los Angeles County, located within the Gateway Cities Subregion. The 3-mile segment has closely spaced freeway entrances and exit ramps, which, combined with the deficient capacity of the existing two-lane connector for westbound SR-91 to northbound and southbound I-605, contribute to a high concentration of collisions compared to the statewide average for similar facilities (see Attachment B). According to the Statewide Integrated Traffic Records System (SWITRS), 438 collisions have occurred within the project limits since Metro commenced the PAED and PS&E phases in 2016. Of these, 79% are rear-end collisions caused by the safety deficiencies in the current on and off-ramp and roadway configuration

 

The Project will improve safety in the area by reducing traffic weaving by lengthening merging and diverging distances for drivers with the addition of a general-purpose lane, auxiliary lanes, and interchange modifications. The Project would improve the transition from westbound SR-91 to I-605 by adding a one-lane I-605 southbound connector and a two-lane I-605 northbound connector.

 

The Project will also construct new sound walls and retaining walls, widen and realign ramps, replace the Gridley Road Overcrossing (OC) and Bloomfield Avenue OC, widen Studebaker Road Undercrossing (UC), construct new Pioneer westbound on-ramp OC and Norwalk westbound on-ramp OC structures, update signing and striping, and modify/improve drainage systems.

 

The Project also includes complete streets elements and upgrades compliant with the Americans with Disabilities Act (ADA).  Complete street improvements include a Class II bicycle lane on Pioneer Boulevard, ADA-compliant sidewalks, pedestrian and bicycle signage, and LED lighting. Additional improvements will consist of sidewalks on both sides of the new Gridley Road OC and five-foot roadway shoulders. The freeway improvements are within Caltrans right-of-way and will not require residential property acquisitions. These improvements advance the mobility needs of people and goods in LA County by supporting traffic mobility, enhanced safety, economic vitality, equitable impacts, access to opportunity, regional sustainability, and resiliency for affected local communities and the region. This project is consistent with Metro’s Objectives for Multimodal Highway Investment.

 

In March 2013, Metro completed a feasibility study for improvements on I-605 and intersecting corridors (I-405, SR-91, I-105, I-5, and SR-60) to identify congestion “Hot Spots” and develop preliminary improvement concepts as part of the SR-91/I-605/I-405 Hot Spots Program funded by Measure R (Expenditure Line 35) and Measure M (Expenditure Line 61). One of the identified congestion Hot Spots was the I-605/SR-91 Interchange.

 

In April 2016, the Board approved a contract with Michael Baker International, Inc. (MBI) in the amount of $7,762,669, for professional services to prepare the Project Approval and Environmental Document (PAED) for WB SR-91 improvements that included the identified I-605/SR-91 Interchange. Subsequently, in October 2019, the Board approved a contract with MBI to prepare Plans, Specifications, and Estimates (PS&E) for the project. A complete list of contract modifications is outlined in Attachment D.

 

Discussion

DISCUSSION

 

The project achieved final design status in May 2024 with the initial advertisement planned for July 2024. In June 2024, Metro and Caltrans secured $69.67 million in Senate Bill 1 (SB 1) Trade Corridor Enhancement Program (TCEP) grant funds for the construction phase. The advertisement was postponed to November 2024 to complete Board-required pre-construction public outreach and to update the PS&E package to comply with Caltrans’ latest standard plans update. The award was expected in December 2024, but discussion to transfer the construction phase to Caltrans delayed the schedule. By late 2024, Caltrans agreed to assume procurement and construction, extending the project’s timeline and budget.

 

Mitigation Requirements

 

As part of the Regional Water Quality Control Board Section 401 permit, Metro has agreed to off-site mitigation involving re-establishing 0.28 acres of stream channel on the MRCA’s Dayton Canyon property. This mitigation will satisfy the compensatory mitigation requirement for the project’s permanent impacts. The MRCA's Dayton Canyon property is in Los Angeles County, within the Los Angeles River Watershed. Caltrans is the project’s California Environmental Quality Act (CEQA) and National Environmental Policy Act (NEPA) lead agency and holds the Section 401 permit. Metro has agreed to fund the implementation of the required mitigation measures.

 

Cooperative Agreement

 

The recommended contract modification and Cooperative Agreement Amendment will fund the additional professional services and oversight needed for Metro to transfer the WB SR-91 project to Caltrans for construction. This shift aligns with Caltrans’ statutory role in freeway construction and allows Metro to focus on its core transit mission while leveraging Caltrans’ expertise to deliver the project.

 

This change will add approximately $6.9 million ($4.8 million in design costs and $2.1 million for Caltrans oversight) in project costs and extend the schedule by approximately 18 months to complete all the necessary design revisions and to avoid jeopardizing the TCEP grant. Metro will sponsor the project construction and Caltrans will implement the construction phase. The project scope and public benefits remain unchanged.

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

Approval of this item will have no adverse impact on the safety of Metro’s patrons, employees, or users of these facilities. Caltrans and local safety standards will be adhered to during the implementation of the proposed Project improvements.

 

Financial_Impact

FINANCIAL IMPACT

 

The total FY26 budget for the Westbound SR-91 Project includes $14,830,000 under Cost Centers 4720, 6510, and 8510, under Project No. 462314. No budget adjustment is needed currently. Staff will revisit the already-established departmental budget to make any necessary adjustments in the current Fiscal Year.

 

Since this is a multi-year project, the Project Manager and the Chief Planning Officer will be responsible for coordinating the programming and budgeting costs in future fiscal years.

 

Impact to Budget

 

There are multiple fund sources for the WB SR-91, including Measure R Highway Capital (20%) and Trade Corridor Enhancement Program (TCEP) funds.

 

The balance of $57,505,000 in Measure R Highway Capital funds programmed for WB SR-91 under MR315.74 as part of the Gateway Cities I-605 Corridor “Hot Spot” Interchange Improvements Program is available to cover the costs and contract modifications.

 

These fund sources are not eligible for bus and rail (transit) capital and operations expenses.

 

Equity_Platform

EQUITY PLATFORM

 

Approving the recommendations will support the proposed safety and mobility improvements to WB SR-91. This project provides a more comprehensive and multimodal approach to improving the regional highway system, advancing Metro’s Objectives for Multimodal Highway Investment to provide a more equitable, sustainable, and multimodal transportation system that improves local communities while also improving the flow of people and goods throughout the region. 

 

The Project area is not located within or directly adjacent to Equity Focus Communities (EFCs). The implementation of the Project will not result in the displacement of or other negative impacts to disadvantaged or low-income communities. However, EFCs are located approximately two  miles west of the Project location terminus. While this distance precludes direct physical impacts, the Project is designed to provide regional benefits such as improving safety and congestion and eliminating current transportation deficiencies on the freeway system, all in support of local communities that use this freeway. These improvements will enhance different modes of transportation for all users. The Project will implement complete streets and active transportation improvements by enhancing bike lanes and crosswalks, installing ADA curb ramps and intersection enhancements, and improving signal timing for pedestrians.

 

While Metro remains committed to encouraging mode shift or carpooling when feasible, the primary mode of transportation for the residents of these cities is commuting by car. For example, 87.9% of Artesia’s residents use this mode as their primary form of transportation (U.S. Census Bureau, 2019-23). This data underscores the importance of the targeted safety and mobility improvements to WB SR-91. By enhancing WB SR-91, the project invests in the primary mode of travel for the community while also supporting other modes to create a safer, more equitable transportation system for all users.

 

Michael Baker International (MBI) made a 23.02% Disadvantaged Business Enterprise (DBE) commitment on this contract. However, the U.S. Department of Transportation (USDOT) has issued an Interim Final Rule (IFR) that makes changes to the DBE Program, including suspension of goals and enforcement, effective October 3, 2025.  Metro is currently reviewing the Interim Final Rule (IFR) to identify necessary program and procedural changes to ensure full compliance.  Although the DBE commitment is not a factor in the staff’s recommendation, there are seven certified small businesses participating in this contract.  This is noteworthy since small businesses are vital for the economy as they drive job creation, foster innovation, and strengthen local communities.


Vehicle_Miles_Traveled _Outcome
VEHICLE MILES TRAVELED OUTCOME

 

Vehicle Miles Traveled (VMT) and VMT per capita in Los Angeles County are below the national average, the lowest within the Southern California Association of Governments (SCAG) region, and among the lowest in the state. These declining trends are partly attributed to Metro’s significant investment in rail and bus transit.* Metro’s Board-adopted VMT reduction targets are aligned with California’s statewide climate goals, including the objective of achieving carbon neutrality by 2045. To support progress toward these goals, all Board items are evaluated for their potential impact on VMT.

 

While the agency remains committed to reducing VMT through transit and multimodal investments, some projects may induce or increase personal vehicle travel. However, these individual projects aim to ensure the efficient and safe movement of people and goods.

 

This Board item will likely increase VMT in LA County, as it includes an investment that encourages driving alone. Although this item may not directly contribute to the achievement of the Board-adopted VMT Reduction Targets, the VMT Targets were developed to account for the cumulative effect of a suite of programs and projects within the Metro region, which individually may increase VMT. Additionally, Metro has a voter-approved mandate to deliver freeway projects while ensuring the efficient and safe movement of people and goods.

 

Mitigation Considerations

Mitigation on the State Highway System is generally limited to on-site options under Caltrans’ authority. Off-site measures often fall under the jurisdiction of local land use, or in this case, Metro. Some on-site mitigation strategies to be considered for the Project area include:

                     Complete streets enhancements

                     Additional 200 linear feet of bicycle lane

                     Intelligent transportation systems

 

* Based on population estimates from the United States Census and VMT estimates from Caltrans’ Highway Performance Monitoring System (HPMS) data between 2001-2019.


Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

The Project is consistent with the following Metro Vision 2028 Strategic Plan Goals:

 

1.                     Provide high-quality mobility options that enable people to spend less time traveling by alleviating the current operational deficiencies and improving mobility along SR-91.

 

2.                     Transform LA County through regional collaboration by partnering with the Gateway Cities Council of Governments and Caltrans to identify the needed improvements on State highways and take the lead in development and implementation of highway improvement projects.

 

Also, the Project supports Metro’s Objectives for Multimodal Highway Investment to:

 

1.                     Advance the mobility needs of people and goods within LA County by developing projects and programs that support traffic mobility and enhanced safety, economic vitality, equitable impacts, access to opportunity, regional sustainability, and resilience for affected local communities.

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

The Board may choose not to accept staff recommendations. However, this alternative is not recommended because this project is included in the Measure R and Measure M Expenditure Plans, has received a significant state TCEP funding award that will be at risk if the project does not advance, and reflects regional consensus on the importance of the Project in improving corridor mobility and safety.

 

Next_Steps

NEXT STEPS

 

Upon Board approval, staff will execute Modification No. 10 to Contract No. AE60979000 with MBI to provide the additional design services that have been requested by Caltrans; amend the existing design Cooperative Agreement with Caltrans; and execute the MRCA Cooperative Agreement.

 

Attachments

ATTACHMENTS

 

Attachment A - Project Location Map

Attachment B - Existing Conditions

Attachment C - Procurement Summary

Attachment D - Contract Modification/Change Order Log

Attachment E - DEOD Summary

 

Prepared_by

Prepared by:                      Andres Roa, Transportation Planner, Complete Streets and Highways, (213) 348-4797
Carlos J. Montez, Deputy Executive Officer, Complete Streets and Highways, (213) 418-3241

Michelle Smith, Executive Officer, Complete Streets and Highways, (213) 547-4368

Michael Cano, Senior Executive Officer (interim), Multimodal Integrated Planning, (213) 418-3010

Avital Barnea, Senior Executive Officer, Multimodal Integrated Planning, (213) 547-0936

Nicole Ferrara, Deputy Chief Planning Officer, Countywide Planning & Development, (213) 547-4322

Carolina Coppolo, Deputy Chief, Vendor/Contract Management Officer, (213) 922-4471

 

Reviewed_By

Reviewed by:                     Ray Sosa, Chief Planning Officer, (213) 547-4274