File #: 2022-0668   
Type: Informational Report Status: Filed
File created: 9/15/2022 In control: Construction Committee
On agenda: 10/20/2022 Final action: 10/20/2022
Title: RECEIVE AND FILE Status Report on Program Management Quarterly Change Report.
Sponsors: Board of Directors - Regular Board Meeting
Indexes: Budgeting, Capital Project, Construction, Informational Report, Program Management, Project management
Attachments: 1. Attachment A - Change Order Log, 2. Attachment B - OIG Spot Check CEO Delegated Authority Delays Avoided

Meeting_Body

CONSTRUCTION COMMITTEE

October 20, 2022

 

Subject

SUBJECT:                     PROGRAM MANAGEMENT QUARTERLY CHANGE REPORT

 

Action

ACTION:                     RECEIVE AND FILE

 

Heading

RECOMMENDATION

 

Title

RECEIVE AND FILE Status Report on Program Management Quarterly Change Report.

 

Issue

ISSUE

 

This board report is a receive and file that provides program management quarterly changes from capital projects greater than $500,000.  Greater detail is provided in Attachment A - Quarterly Change Orders Log for Reporting Period of June 1, 2022 - August 31, 2022.

 

Background

BACKGROUND

 

In January 2017, the Metro Board approved a one-year pilot to delegate the CEO the authority to execute project agreements up to the Life-of-Project (LOP) budget for the Crenshaw/LAX, Regional Connector, and Purple Line Extension Section 1 & 2 projects.  The purpose of the pilot was to save time and minimize disruption due to the typical contract change administration approval process.

 

The pilot program was effective, generated cost savings, and avoided costly construction delays. At the January 26, 2018, Board meeting, the Board approved the continuation and expansion of the delegation of authority within Life of Project (LOP) budget management on all Transit and Regional Rail Capital Projects.  Staff was directed to provide quarterly reports to the Board on change orders and modifications above $500,000.  CEO Board delegated authority of changes is very beneficial to expedite contract changes and avoid costly construction delays. Since the program’s inception, up to 2,075 concurrent workdays or concurrent 8.0 years, aggregated across the program, have been saved. (Attachment B)

 

Discussion

DISCUSSION

 

The change activities for the reporting period between June 1, 2022, and August 31, 2022, are included in Attachment A.   

 

Financial_Impact

FINANCIAL IMPACT

 

The changes in this report are included in the approved life-of-project budget for each project.

 

Equity_Platform

EQUITY PLATFORM

 

Crenshaw/LAX

Equity - 8 of 8 stations (100%) are within or adjacent to Equity Focus.

Regional Connector

Equity - 3 of 3 stations (100%) are within or adjacent to Equity Focus.

Westside Purple Line Ext 1

Equity - This project is not located within or adjacent to Equity Focus Communities

Westside Purple Line Ext 2

Equity - This project is not located within or adjacent to Equity Focus Communities

Westside Purple Line Ext 3

Equity - 1 of 2 stations (50%) are within or adjacent to Equity Focus Communities.

Division 20

Equity - 100% of the project is within or adjacent to Equity Focus Communities

Airport Metro Connector

Equity - 100% of the project is within or adjacent to Equity Focus Communities

Rail to Rail

Equity - 100% of the project is within or adjacent to Equity Focus Communities

Systemwide Signage

Equity - 55% of the project is within or adjacent to Equity Focus Communities

I-5 North County Enhancements

Equity - This project is not located within or adjacent to Equity Focus Communities

 

Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

The recommendation supports strategic plan goal # 5 to provide responsive, accountable, and trustworthy governance within the Metro organization by keeping the Board informed of the Projects’ change orders and modifications via submitting the Change Order log on a quarterly basis.

 

Next_Steps

NEXT STEPS

 

The next Change Order Log will cover the period of September 1, 2022, through November 30, 2022, and will be presented to the January 2023 Construction Committee.

 

Attachments

ATTACHMENTS

 

Attachment A - Quarterly Change Orders Log for Reporting Period of June 1, 2022 - August 31, 2022.

 

Attachment B - OIG Construction Change Order Spot Checks CEO Delegated Authority Delays Avoided

 

Prepared_by

Prepared by:

                     Crenshaw/LAX - Sameh Ghaly, Deputy Chief Program Management Officer, (213) 418-3369

                     Regional Connector - Mathew Antonelli, Project Manager, (213) 893-7114

                     Westside Purple Line Ext 1 - James Cohen, EO Projects Eng., (323) 900-2114

                     Westside Purple Line Ext 2 - Michael McKenna, EO Projects Eng.,

      (424) 551-4447

                     Westside Purple Line Ext 3 - Kimberly Ong, EO Projects Eng., (424) 551-4501

                     Division 20 Portal - Sameh Ghaly, Deputy Chief Program Management Officer, (213) 418-3369

                     Airport Metro Connector - Tim Lindholm, Deputy Chief Program Management Officer, (213) 922-7297

                     Metro Blue Line Resignaling - Tim Lindholm, Deputy Chief Program Management Officer, (213) 922-7297

                     Rail to Rail - Tim Lindholm, Deputy Chief Program Management Officer, (213) 922-7297

                     Systemwide Signage - Tim Lindholm, Deputy Chief Program Management Officer, (213) 922-7297

                     I-5 North Country Enhancements - Tim Lindholm, Deputy Chief Program Management Officer, (213) 922-7297

                     Report - Julie Owen, Sr. EO Program Control, (213) 922-7313

 