File #: 2020-0195   
Type: Informational Report Status: Agenda Ready
File created: 3/9/2020 In control: Construction Committee
On agenda: 4/16/2020 Final action:
Title: CONSIDER amending the Life-of-Project (LOP) budget by $90,000,000 for the Crenshaw/LAX Transit Project (Project) of $2,058,000,000 to $2,148,000,000, consistent with the provisions of the Board-adopted Measure R and Measure M Unified Cost Management Policy (Attachment B).
Sponsors: Construction Committee
Indexes: Alignment, Aviation/LAX Station, Budget, Budgeting, Congestion Mitigation And Air Quality Improvement Program, Construction, Construction management, Contractors, Contracts, Crenshaw/Lax Transit Corridor (Project), Crenshaw/LAX Transit Corridor Project, Division 16, El Segundo, Funding plan, Hawthorne, Informational Report, Inglewood, Light rail transit, Long range planning, Long Range Transportation Plan, Los Angeles International Airport, Measure M, Measure R, Measure R and Measure M Unified Cost Management Policy, Metro Crenshaw Line, Metro Exposition Line, Metro Green Line, Metro Rail A Line, Metro Rail C Line, Metro Rail E Line, Metro Rail K Line, Plan, Policy, Policy analysis, Pomona, Professional Services, Project, Project management, Revenue Service, San Gabriel, South Bay Cities subregion
Attachments: 1. Attachment A - Funding-Expenditure Plan ($90), 2. Attachment B - Crenshaw-LAX Transit Project Measure R and Measurement M.._
Related files: 2020-0319
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Meeting_Body

CONSTRUCTION COMMITTEE

APRIL 16, 2020

 

Subject

SUBJECT:                     CRENSHAW/LAX TRANSIT PROJECT

 

Action

ACTION:                     APPROVE RECOMMENDATION

 

Heading

RECOMMENDATION

 

Title

CONSIDER amending the Life-of-Project (LOP) budget by $90,000,000 for the Crenshaw/LAX Transit Project (Project) of $2,058,000,000 to $2,148,000,000, consistent with the provisions of the Board-adopted Measure R and Measure M Unified Cost Management Policy (Attachment B).

 

Issue

ISSUE

 

The Substantial Completion date for the Project is currently forecast to be delayed to December 2020 and the revenue service in 2021.  As a result, the Project LOP budget needs to be increased, requiring an additional $90,000,000 million beginning in the second half of 2020 for Metro staff and professional service contracts to continue management and oversight of the Project. No additional funding from this LOP increase is designated for the contractor.  This represents the first LOP adjustment since the beginning of construction on the Project in 2013.

Background

BACKGROUND

 

The Crenshaw/LAX Transit Project is a north/south light rail line that serves the cities of Los Angeles, Inglewood, Hawthorne and El Segundo as well as portions of unincorporated Los Angeles County.  The alignment extends 8.5 miles, from the Metro E (Expo) line at Crenshaw and Exposition Boulevards to a connection with the Metro Green Line south of the Aviation/LAX Station.  The project provides major connections with the Los Angeles International Airport (LAX) as well as links to the C Line (Green), the E Line (Expo) and countywide bus network. 

The alignment is comprised of a double-tracked rail line consisting of sections of at-grade in-street, at-grade within railroad right-of-way, aerial, and below-grade guideway sections, eight stations, park and ride facilities at two locations, utilities, landscaping, roadway improvements required by the project and a maintenance & storage facility (Division 16 - Southwestern Yard).

On June 27, 2013, the Board authorized an LOP budget of $1,923,000,000 for the base Project.  In addition, the Board authorized an increase to the LOP budget in the amount of $135,000,000 from $1,923,000,000 to $2,058,000,000, for the award of options for Leimert Park Station and Hindry Station (now called Westchester/Veterans Station).  The LOP budget has not been adjusted since that time.

Metro awarded a 57-month Design/Build contract to Walsh/Shea Corridor Constructors (WSCC) for construction of the Project in August 2013 and issued a Notice to Proceed to WSCC in September 2013. WSCC’s Substantial Completion date was September 2018 with a revenue service date of October 2019.

Discussion

DISCUSSION

 

In March 2017, Metro executed a Claims and Disputes Settlement Agreement with WSCC to resolve outstanding claims and disputes up to that point in the Project.  WSCC’s Contract Milestones were confirmed as part of the Agreement.  WSCC committed to a Substantial Completion date of May 2019 as part of an approved Completion Schedule, which still enabled the October 2019 revenue service date. 

WSCC’s progress in 2018 fell behind the Completion Schedule dates agreed upon in the Claims and Disputes Settlement Agreement.  Metro was informed by WSCC that, due to delays, it would not be able to complete its work by the projected deadline in the Completion Schedule.  Since WSCC was not able to demonstrate that its forecasted delay was an Excusable Delay or a Compensable Delay under the Contract Terms and Conditions, Metro executed a Non-Compensable Time Extension.  A Unilateral Change Order (CO-223.1) was executed in September 2018 resetting the Project Substantial Completion to December 11, 2019.

In 2019, the project continued to fall behind the dates reset in the Non-Compensable Time Extension.  There have been several areas of work along the alignment that could not be completed due to damaged, incomplete and missing components (rework).  This rework plus other performance and resource issues caused the contractor’s progress to be less than planned, impacting WSCC’s follow-on subcontractors work and creating inefficient performance.  Metro has been assessing liquidated damages.

Due to extending the Project’s Substantial Completion date, additional funding is now required.  The existing LOP budget includes funding obligations for the contractor’s work, but the LOP budget needs to be amended to provide additional funding for professional services that are required to support the completion of the Project.  The required support includes Metro staff and professional services consultants who provide various services to assist in the management and oversight of the Project.  The funding in Recommendation A is requested to provide support to achieve Substantial Completion in December 2020 and to allow revenue service to commence in 2021.  A detailed breakdown of the proposed uses for the additional $90 million LOP is contained in Attachment C.

 

 

Determination_Of_Safety_Impact
DETERMINATION OF SAFETY IMPACT

 

This Board action will not have an impact on established safety standards for Metro’s construction projects.

 

Financial_Impact
FINANCIAL IMPACT

 

Funds required through fiscal year 2020, in the amount of $127,950,000, are included in Project 865512 Crenshaw/LAX Transit Project, in Cost Center 8510 (Construction Project Management).

Since this is a multi-year capital project, the Chief Program Management Officer and the Project Manager will be responsible for budgeting costs in future fiscal years.

Impact to Budget

The sources of funds for the recommended actions are local funds available and eligible at the time of expenditure, including operating eligible funding sources. Eligible federal funds will also be utilized to fund the increase.

Multiyear Impact 

The sources of funds for the Project are capital funds identified in the recommended Funding/Expenditure Plan as shown in Attachment A. The project cost, prior to the proposed cost increase, is included and funded in the 2019 Long Range Transportation Plan Financial Forecast. With respect to the $90,000,000 increase, Attachment B shows the Measure R and Measure M Unified Cost Management Policy (the Policy) analysis and funding strategy required for cost increases to Measure R Projects.

To comply with the Policy of the Metro Board of Directors, Metro staff has evaluated potential offsetting cost reductions, including value engineering, shorter segment, and reductions to other Metro projects in the corridor and subregion, and has determined these are not feasible, and that additional local funding resources, which are to be considered prior to Metro's countywide funding, are potentially available. The Policy analysis identifies a Measure M multi-year subregional program, Measure R highway program, and federal formula CMAQ funding as available funding sources in the Long Range Transportation Plan Financial Forecast that can address the $90,000,000 cost increase.

This report identifies additional funding resources consistent with the Policy approved by the Board in 2018.  Attachment B provides a detailed discussion of the Policy.  In summary, the Policy was developed in recognition that some projects would need additional funding and the Policy provides a consistent and equitable process to assure that any financial impacts are limited to the subregion where the project is located and not have a region-wide impact.

The Policy defines a cascading list of actions that can be taken. Because the Project is so far along, actions such as value engineering or changes in scope are no longer feasible.  Additional funding is the only option.

The table at the end of Attachment B identifies the potential funding sources that are available. The selection and application of specific resources requires further discussion with stakeholders. Any use of Measure R Highway programming to this transit project requires a two-thirds vote by the Board (as part of its ongoing consideration of the 10 year Measure R ordinance transfer options).

It is important to note that the Project spans two subregions - South Bay 59% and Central City 41%. In addition, $33.1 million is available from CMAQ funds. Therefore, the net impact to any one subregion is less.

The most recent project to be evaluated under the Policy was the Foothill Extension to Pomona in 2019.  Although the two projects are not directly comparable (Foothill was not yet under construction, so had more opportunity for scope changes), there are similarities that could be instructive.

In that case, the financial deficit was addressed by the subregional equity program of the San Gabriel Valley. Funds were accelerated to be taken from the subregional equity pool in the year that funding became available (2044).  A board motion directed this approach.

Implementation_of_Strategic_Plan_Goals
IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

Recommendation supports Strategic Plan Goal #1 - Provide high-quality mobility options that enable people to spend less time traveling.

 

Alternatives_Considered
ALTERNATIVES CONSIDERED

 

The Board may choose to not move forward with amending the LOP Budget.  This is not recommended as Metro will be unable to provide funding for Metro staff or obligate any extension to existing professional service contracts, or other required services beyond June 2020.

 

Next_Steps
NEXT STEPS

 

Upon approval by the Board, the LOP Budget will be amended accordingly per Recommendation A.

 

Attachments
ATTACHMENTS

 

Attachment A - Funding/Expenditure Plan

Attachment B - Measure R and Measure M Unified Cost Management Policy Analysis

Attachment C - Breakdown of Additional $90 Million LOP

 

 

 

Prepared_by
Prepared by:
                     

 

Sameh Ghaly, Sr. Executive Officer/Project Management (213) 264-0693

William Brown, Deputy Executive Officer, Program Control (323) 903-4109

        

Reviewed_By
Reviewed by:
                     

 

Richard Clarke, Chief Program Management Officer, (213) 922-7557

James de la Loza, Chief Planning Officer, (213) 922-2920