File #: 2023-0410   
Type: Informational Report Status: Agenda Ready
File created: 6/9/2023 In control: Construction Committee
On agenda: 7/20/2023 Final action:
Title: RECEIVE AND FILE Status Report on Program Management Quarterly Change Report (Attachment A).
Sponsors: Board of Directors - Regular Board Meeting
Indexes: Budgeting, Construction, Informational Report, Program Management, Project management
Attachments: 1. Attachment A - Quarterly Change Orders Log for Period of 3.1.23-5.31.23, 2. Attachment B – OIG Construction Change Order Spot Checks, 3. Presentation
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Meeting_Body

CONSTRUCTION COMMITTEE

JULY 20, 2023

 

Subject

SUBJECT:                     PROGRAM MANAGEMENT QUARTERLY CHANGE REPORT

 

Action

ACTION:                     RECEIVE AND FILE

 

Heading

RECOMMENDATION

 

Title

RECEIVE AND FILE Status Report on Program Management Quarterly Change Report (Attachment A).

 

Issue
ISSUE

 

This board report is a receive and file that summarizes quarterly changes valued at greater than $500,000 for projects managed by Program Management.  Additional detail is provided in Attachment A - Quarterly Change Orders Log for Reporting Period of March 1, 2023 - May 31, 2023.

 

Background

BACKGROUND

 

In January 2017, the Metro Board approved a one-year pilot to delegate the CEO the authority to execute project agreements up to the Life-of-Project (LOP) budget for the Crenshaw/LAX, Regional Connector, and Purple Line Extension Section 1 & 2 projects.  The purpose of the pilot was to save time and minimize disruption due to the typical contract change administration approval process.

 

The pilot program was effective, generated cost savings, and avoided costly construction delays. At the January 26, 2018 Board meeting, the Board approved the continuation and expansion of the delegation of authority within Life of Project budget management on all Transit and Regional Rail Capital Projects.  Staff was directed to provide quarterly reports to the Board on change orders and modifications that are above $500,000.  This CEO delegated authority of changes is very beneficial to expedite contract changes and avoid costly construction delays. Since the inception of the program up to 2,344 concurrent workdays or concurrent 9.1 years, aggregated across the program, have been saved. (For more information refer to Attachment B entitled OIG Construction Change Order Spot Checks CEO Delegated Authority Total Delays Avoided). 

 

Discussion
DISCUSSION

 

The change activities for the reporting period between March 1, 2023, and May 31, 2023, are included in Attachment A.

 

Financial_Impact
FINANCIAL IMPACT

 

The changes included in this report are within the approved LOP budget for each project.

 

Equity_Platform

EQUITY PLATFORM

 

The cost and time savings from the expansion of delegation of authority within Life of Project budget management has allowed Metro to more efficiently implement mobility options, benefiting transit riders and other marginalized communities.

 

Crenshaw/LAX

Equity - 8 of 8 stations (100%) are within or adjacent to Equity Focus Communities

Regional Connector

Equity - 3 of 3 stations (100%) are within or adjacent to Equity Focus Communities

Westside Purple Line Ext 1

Equity - This project is not located within or adjacent to Equity Focus Communities

Westside Purple Line Ext 2

Equity - This project is not located within or adjacent to Equity Focus Communities

Westside Purple Line Ext 3

Equity - 1 of 2 stations (50%) are within or adjacent to Equity Focus Communities

Division 20

Equity - 100% of the project is within or adjacent to Equity Focus Communities

Airport Metro Connector

Equity - 100% of the project is within or adjacent to Equity Focus Communities

Rail to Rail

Equity - 100% of the project is within or adjacent to Equity Focus Communities

 

Note: This analysis was conducted with the 2022 EFC map.

 

 

Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

The recommendation supports strategic plan goal # 5 to provide responsive, accountable, and trustworthy governance within the Metro organization by keeping the Board informed of the Projects’ change orders and modifications via submitting the Change Order log on a quarterly basis.

 

Next_Steps
NEXT STEPS

 

The next Change Order Log will cover the period of June 1, 2023 through August 31, 2023 and will be presented to the October 2023 Construction Committee.

 

Attachments

ATTACHMENTS

 

Attachment A - Quarterly Change Orders Log for Reporting Period of March 1, 2023 - May 31, 2023

 

Attachment B - OIG Construction Change Order Spot Checks CEO Delegated Authority Delays Avoided

 

Prepared_by

Prepared by:

                     Crenshaw/LAX - Sameh Ghaly, Chief Program Management Officer (Interim), (213) 418-3369

                     Regional Connector - Mathew Antonelli, Deputy Chief Program Management Officer, (213) 893-7114

                     Westside Purple Line Ext 1 - James Cohen, Senior Executive Officer, Projects Engineering (Interim), (323) 900-2114

                     Westside Purple Line Ext 2 - Michael McKenna, Senior Executive Officer, Projects Engineering (Interim),  (424) 551-4447

                     Westside Purple Line Ext 3 - Kimberly Ong, Senior Executive Officer, Projects Engineering (Interim), (424) 551-4501

                     Division 20 Portal - Albert Soliz, Deputy Executive Officer, Project Management, (213) 922-4002

                     Airport Metro Connector - Tim Lindholm, Deputy Chief Program Management Officer, (213) 922-7297

                     Rail to Rail - Tim Lindholm, Deputy Chief Program Management Officer, (213) 922-7297

                     I-105 Express Lanes - Tim Lindholm, Deputy Chief Program Management Officer, (213) 922-7297

                     Report - Julie Owen, Senior Executive Officer, Program Control, (213) 922-7313

 

Reviewed_By

Reviewed by:

Sameh Ghaly, Chief Program Management Officer (Interim), (213) 418-3369