File #: 2025-0187   
Type: Informational Report Status: Filed
File created: 3/4/2025 In control: Construction Committee
On agenda: 4/16/2025 Final action: 4/16/2025
Title: RECEIVE AND FILE Status Report on Program Management Quarterly Change Report.
Indexes: Budgeting, Construction, Informational Report, Program Management, Rail transit
Attachments: 1. Attachment A - Quarterly Change Orders Log for Dec. 1, 2024 - Feb. 28, 2025, 2. Attachment B - OIG Con. Change Order Spot Checks (Through Feb. 2025), 3. Presentation

Meeting_Body

CONSTRUCTION COMMITTEE

APRIL 16, 2025

 

Subject

SUBJECT:                     PROGRAM MANAGEMENT QUARTERLY CHANGE REPORT

 

Action

ACTION:                     RECEIVE AND FILE

 

Heading

RECOMMENDATION

 

Title

RECEIVE AND FILE Status Report on Program Management Quarterly Change Report.

 

Issue

ISSUE

 

This report provides a quarterly summary of the use of Board delegated authority to the Chief Executive Officer (CEO) regarding contract changes for transit and regional rail construction projects greater than $500,000.

 

Background

BACKGROUND

 

In January 2017, the Board approved a one-year pilot to delegate to the CEO authority to execute project agreements up to the Life-of-Project (LOP) budget for the Crenshaw/LAX, Regional Connector, and Purple Line Extension Section 1 & 2 projects.  The purpose of the pilot was to save time and minimize disruption due to the typical contract change administration approval process.

 

The pilot program was effective, generated cost savings, and avoided costly construction delays. At its January 2018 meeting, the Board approved the continuation and expansion of the delegation of authority within the LOP budget on all Transit and Regional Rail Capital Projects. Staff was directed to provide quarterly reports to the Board on change orders and modifications that are above $500,000 (Attachment A).  Board delegated authority to the CEO is very beneficial to expedite contract changes and avoid costly construction delays. Since inception of the program, up to 2,916 concurrent workdays or concurrent 11.3 years, aggregated across the program, have been saved (Attachment B). 

 

Discussion

DISCUSSION

 

The change activities for the reporting period between December 1, 2024 - February 28, 2025 are included in Attachment A.

 

Equity_Platform

EQUITY PLATFORM

 

The table below summarizes the percentage of each project within Equity Focus Communities (EFCs). These contract modifications are necessary to complete each capital project, which benefits EFCs.

 

 

 

 

Vehicle_Miles_Traveled _Outcome

VEHICLE MILES TRAVELED OUTCOME

 

VMT and VMT per capita in Los Angeles County are lower than national averages, the lowest in the SCAG region, and on the lower end of VMT per capita statewide, with these declining VMT trends due in part to Metro’s significant investment in rail and bus transit.*  Metro’s Board-adopted VMT reduction targets align with California’s statewide climate goals, including achieving carbon neutrality by 2045. To ensure continued progress, all Board items are assessed for their potential impact on VMT.

 

The projects in this report have mixed outcomes, but on the whole, most of the projects in this report will likely decrease VMT in LA County. Within this suite of projects, Metro seeks to reduce single-occupancy vehicle trips, provide a safe transportation system, and increase accessibility to destinations via transit, cycling, walking, and carpooling. Some of the projects within this status report include items that will ease congestion for cars and trucks, or expand vehicle capacity, resulting in the possibility of increased VMT. However, these projects also provide for carpooling infrastructure and reinvestment of funding towards transit projects. In addition, the projects’ multi-modal benefits may contribute to offsetting the possible increase in VMT.

 

While the agency remains committed to reducing VMT through transit and multimodal investments, some projects may induce or increase personal vehicle travel. However, these individual projects aim to ensure the efficient and safe movement of people and goods. Although the three highway projects above may not directly contribute to the achievement of the Board-adopted VMT Reduction Targets, the VMT Targets were developed to account for the cumulative effect of a suite of programs and projects within the Metro region, which individually may induce or increase VMT. Additionally, Metro has a voter-approved mandate to deliver multimodal projects that enhance mobility while ensuring the efficient and safe movement of people and goods.

 

 

 

 

 

*Based on population estimates from the United States Census and VMT estimates from Caltrans’ Highway Performance Monitoring System (HPMS) data between 2001-2019.

 

 

Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

The recommendation supports strategic plan goal # 5 to provide responsive, accountable, and trustworthy governance within the Metro organization by keeping the Board informed of the Projects’ change orders and modifications via submitting the Change Order log on a quarterly basis.

 

Next_Steps

NEXT STEPS

 

The next Program Management Quarterly Change Report will cover the period of March 1, 2025, through May 31, 2025, and will be presented to the July 2025 Construction Committee.

 

Attachments

ATTACHMENTS

 

Attachment A - Quarterly Change Orders Log for Reporting Period of December 1, 2024 - February 28, 2025.

 

Attachment B - OIG Construction Change Order Spot Checks CEO Delegated Authority Delays Avoided (Through February 2025)

 

Prepared_by

Prepared by:

                     Crenshaw/LAX - Sameh Ghaly, Deputy Chief Program Management Officer, (213) 418-3369

                     Westside Purple Line Ext 1 - James Cohen, Senior Executive Officer, Projects Engineering, (323) 900-2114

                     Westside Purple Line Ext 2 - Zephaniah Varley, Executive Officer, Projects Engineering (interim), (424) 551-4449

                     Westside Purple Line Ext 3 - Kimberly Ong, Senior Executive Officer, Projects Engineering, (424) 551-4501

                     Division 20 Portal - Albert Soliz, Deputy Executive Officer, Project Management, (213) 922-4002

                     Airport Metro Connector - Rafie Zamani, Senior Executive Officer, Projects Engineering (interim), (213) 418-3140

                     Metro Center Project - Albert Soliz, Deputy Executive Officer, Project Mgmt., (213) 922-4002

                     Rail to Rail - Rafie Zamani, Senior Executive Officer, Projects Engineering (interim), (213) 418-3140

                     I-5 North Country Enhancements - Mathew Antonelli, Deputy Chief Program Management Officer, (213) 893-7114

                     Metro G Line BRT Improvements - Annalisa Murphy, Deputy Executive Officer, Project Management, (213) 474-6838

                     I-105 Express Lanes - James Wei, Executive Officer, Program Management, (213) 922-7258

                     East San Fernando Valley Transit Corridor - Mathew Antonelli, Deputy Chief Program Management Officer, (213) 893-7114

                     Link Union Station - Michael McKenna, Deputy Chief Program Management Officer, (424) 551-4447

                     Report - Daniel Estrada, Senior Executive Officer, Program Management (Interim), (213) 418-3076

 

 