Skip to main content
File #: 2025-0611   
Type: Oral Report / Presentation Status: Agenda Ready
File created: 7/21/2025 In control: Measure M Independent Taxpayer Oversight Committee
On agenda: 9/10/2025 Final action:
Title: RECEIVE oral report on Measure M Active Transportation, programmed revenues, and uses to support discussion on the effective and efficient use of funds.
Sponsors: Program Management (Department), Maria Luk
Indexes: Active Transportation Program, Active Transportation Strategic Plan, Bids, Construction, Environmental Impact Report, First/Last Mile, LA River Bike Path Gap Closure Project, Maintenance practices, Maps, Metro Active Transport (MAT) project, Operations and Maintenance, Oral Report / Presentation, Partnerships, San Fernando, San Fernando Valley Service Sector, San Fernando Valley subregion
Attachments: 1. Presentation
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Meeting_Body

MEASURE M INDEPENDENT TAXPAYER OVERSIGHT COMMITTEE

SEPTEMBER 10, 2025

 

Subject

SUBJECT:                     MEASURE M ACTIVE TRANSPORTATION UPDATES

 

Action

ACTION:                     RECEIVE ORAL REPORT

 

Heading

RECOMMENDATION

 

Title

RECEIVE oral report on Measure M Active Transportation, programmed revenues, and uses to support discussion on the effective and efficient use of funds.

 

Issue

ISSUE

 

To support the discussion for the effective and efficient use of funds, this quarterly presentation provides the committee with the status of Metro active transportation activities related to Measure M projects.

 

Equity_Platform

EQUITY PLATFORM

 

The Measure M related activities for active transportation include two projects in the Measure M Expenditure Plan that will connect the bike path gaps along the Los Angeles River in the San Fernando Valley and in Central Los Angeles, as well as the Metro Active Transport, Transit and First/Last Mile (MAT) Program, a discretionary grant program guided by the priorities in the Active Transportation Strategic Plan (ATSP). Measure M also funds active transportation projects programmed by subregions through the Multiyear Subregional Program (MSP). In addition to funding these activities, Metro engages in First/Last Mile planning for communities to access existing and future major transit stops. Equity is built into Metro’s approach to all of these activities.

 

The 2023 ATSP identified and prioritized a regional active transportation network based on criteria, including overlap with Equity Focus Communities (EFC). Projects in the ATSP regional network are eligible for MAT Program Cycle 2 funding. In addition to evaluating projects for investments in EFCs, MAT Cycle 2 project applications were evaluated based on factors including robust partnerships with Community Based Organizations (CBO) to ensure community engagement in project development.  Project applications that were submitted for MAT Cycle 1 in 2020 were given bonus points for locations within EFCs. All selected projects that are being developed using Cooperative Agreements with Metro include CBO partnerships.

 

The LA River Project – Central City section directly serves seven EFC census tracts in the communities of Lincoln Heights, Chinatown, and Boyle Heights. Approximately 23% of the population in this area lives under the poverty line and more than 22% of the working-age population does not use cars as a primary mode of transportation.  This path will not only be used for recreational purposes but also serve as a low-cost transportation option for those who have limited car ownership. The LA River Project – San Fernando Valley section directly serves two EFCs in the community of Reseda. It is being delivered by the City of Los Angeles.

 

 

Attachments

ATTACHMENT

 

Attachment A - Presentation

 

Prepared_by

Prepared by: James Andrew, Senior Manager, Countywide Planning & Development,

(213) 547-4306

Peter Carter, Senior Director, Countywide Planning & Development,

(213) 922-7480

Allison Yoh, Executive Officer, Countywide Planning & Development, (213) 922-4812

David Mieger, Senior Executive Officer, Countywide Planning & Development, (213) 922-3040

Nicole Ferrara, Deputy Chief Planning & Development Officer, Countywide Planning & Development (213) 547-4322

 

Reviewed_By

Reviewed by: Ray Sosa, Chief Planning & Development Officer, (213) 547-4274