Legislation Details

File #: 2026-0638   
Type: Project Status: Agenda Ready
File created: 8/21/2026 In control: Planning and Programming Committee
On agenda: 11/18/2026 Final action:
Title: CONSIDER: A. APPROVING the Locally Preferred Alternative (LPA) for the LA River Path project as Modified Option 2, an 8-mile path between Riverside Drive and Atlantic Boulevard evaluated in the Draft Environmental Impact Report (EIR); B. APPROVING an approximately 5.5-mile gap closure through two simultaneous Initial Operating Segments (IOS) – the IOS-north between Riverside Drive and Spring Street; and the IOS-South, between Sixth Street and Atlantic Boulevard; and C. AUTHORIZING staff to work with the City of Los Angeles to bridge the 2.5 mile gap between IOS-north and IOS-south, to prioritize planned Class IV cycle tracks, in combination with the existing on-street bike lanes, which can serve as an interim connection until funding for the off-street river channel paths between Broadway/Spring Street and Sixth Street is secured.
Sponsors: Board of Directors - Regular Board Meeting
Attachments: 1. Attachment A - June 2021 Metro Board Amendment, 2. Attachment B - May 2026 Board Motion 46, 3. Attachment C - DEIR Alternatives-Path Types, 4. Attachment D - Draft EIR Executive Summary, 5. Attachment E - Draft EIR Outreach Summary, 6. Attachment F - LPA & IOS, 7. Attachment G - LA River Path Project Cost-Benefit Analysis, 8. Presentation
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Meeting_Body

PLANNING AND PROGRAMMING COMMITTEE

NOVEMBER 18, 2026

EXECUTIVE MANAGEMENT COMMITTEE

NOVEMBER 19, 2026

 

Subject

SUBJECT:                     LA RIVER PATH - LOCALLY PREFERRED ALTERNATIVE (LPA)

 

Action

ACTION:                     APPROVE RECOMMENDATION

 

Heading

RECOMMENDATION

 

Title

CONSIDER:

 

A.  APPROVING the Locally Preferred Alternative (LPA) for the LA River Path project as Modified Option 2, an 8-mile path between Riverside Drive and Atlantic Boulevard evaluated in the Draft Environmental Impact Report (EIR);

 

B.  APPROVING an approximately 5.5-mile gap closure through two simultaneous Initial Operating Segments (IOS) - the IOS-north between Riverside Drive and Spring Street; and the IOS-South, between Sixth Street and Atlantic Boulevard; and

 

C.  AUTHORIZING staff to work with the City of Los Angeles to bridge the 2.5 mile gap between IOS-north and IOS-south, to prioritize planned Class IV cycle tracks, in combination with the existing on-street bike lanes, which can serve as an interim connection until funding for the off-street river channel paths between Broadway/Spring Street and Sixth Street is secured.

 

Issue

ISSUE

 

Metro published a Draft EIR under the California Environmental Quality Act (CEQA) for the LA River Path Project on December 18, 2025. The Board's action to approve the LPA and the two simultaneous IOSs is necessary to continue advancing the Project design for state and federal environmental clearance, which is required for obtaining the United States Army Corps of Engineers (USACE) permit to build and operate the Project, and to allow Metro to support the LA River Governance Model Study (Governance Study). Selecting an LPA does not constitute approval of the project.

 

Background

BACKGROUND

 

The Project is included in the 2016 Measure M Expenditure Plan as the LA River Waterway & System Bike path, and in the Metro 2020 Long Range Transportation Plan (LRTP) as the LA River Path - Central LA. At its May 2018 meeting, the Board authorized staff to advance the Project through design, environmental clearance, and construction, based on the findings from the prior 2016 Feasibility Study. Metro published a Draft EIR under the California Environmental Quality Act (CEQA) for the LA River Path Project on December 18, 2025. 

 

The Project would close the longest remaining gap of the active transportation network along the LA River. This 8-mile segment between Elysian Valley in the City of Los Angeles and the City of Maywood poses an increased safety risk, as cyclists and pedestrians must use surface streets and busy intersections to traverse the existing network. By closing this gap through downtown Los Angeles and the City of Vernon, the Project would serve communities between the San Fernando Valley and the City of Long Beach, transforming how people travel across LA County. When complete, the Project would add to the existing 24-miles of active transportation network along the LA River, providing a seamless 32-mile traffic-separated active transportation facility.

 

Project History

 

Currently, 24 miles of non-continuous pedestrian and bicycle paths exist along the LA River. South of the Project, Los Angeles County opened the LA River Bicycle Path in 1983, a 17-mile route stretching from Maywood to Long Beach. Los Angeles County Department of Public Works (LADPW) published the first LA River Master Plan in 1996, which was subsequently updated in 2022 to include the Project. North of the Project, the City of Los Angeles opened the Los Angeles River Greenway Trail in 1997 from Elysian Valley to Burbank. 

 

In 2016, Measure M identified the LA River Waterway & System Bike Path in its expenditure plan, allocating $365 million (2015$) for its design, environmental clearance, and construction. Later rebranded as the LA River Path, the Project aims to create a safe, accessible pathway for pedestrians and cyclists and provide an alternative mode of transportation suitable for users of all ages and abilities, particularly for residents living within a 3-mile radius of the corridor. 

 

At its September 2016 meeting, the Metro Board approved the LA River Bike Path Gap Closure Feasibility Study, which concluded that gap closure was viable. 

 

Subsequently, at its September 2019 meeting, the Board received the LA River Path Conceptual Design Report (CDR), which incorporated significant public outreach findings and identified the alternatives evaluated in the Draft EIR. The CDR studied a bottom-of-channel (BOC) alignment that was not recommended for advancement in the environmental studies. This path type would incur significant risk from seasonal flooding, would require the longest access ramps to get on and off the path, and would not be able to provide many of the amenities and features, such as direct path lighting, rest stations, landscaping, and security features, as the path would be underwater during rain events and for a period of time during and after flooding events. In typical rain events, water can surge to 3-6 feet deep at 24 mph within 24 hours. Based on the last 25 years of rain events and USACE’s recommendation of a 72-hour post-storm stand-down, a BOC alignment could be closed between 1.9 months during dry years and 5.6 months during wet years. Aside from the flood risk, a BOC path's visibility is greatly impaired when it is placed at the bottom of the river with banks at least 25 feet high and flanked by active railroads. Women weigh visibility heavily when choosing trails. Studies of women trail users find that the feeling of being trapped or unable to exit quickly leads them to avoid routes they perceive as unsafe.

 

For these reasons, this alignment was not among the top three best-performing alternatives. The Board authorized the CEO to initiate the Draft EIR with the three best-performing alternatives: A, B, and C (Proposed Project, Option 1, and Option 2 in the Draft EIR). It also highlighted the design constraints to be further addressed in the Project area, including active freight and passenger rail abutting the river channel, utility towers, and bridges, some of which are designated as historic.

 

On November 18, 2021 <https://boardagendas.metro.net/board-report/2021-0556/>, in response to a June 2021 Metro Board Motion (Attachment A), the Board authorized staff to coordinate with the City and County of Los Angeles for ownership, operations, and maintenance of the Project, noting that Metro will not assume any financial responsibility for operating and maintaining the completed project. One of the biggest limitation cited in the response was Metro’s insignificant share of right-of-way (ROW) ownership along the corridor.  While the City of Los Angeles (including Los Angeles Department of Water and Power (LADWP), and the County of Los Angeles (including the Los Angeles County Flood Control District (LACFCD)) in total own approximately 80% of the ROW along the corridor, Metro ownership is less than 1% with the remaining 19% privately owned.   

 

At its May 2026 meeting, the Board approved Motion 46 (Attachment B) by Directors Bass, Solis, Horvath, Hahn, and Padilla, which identified LACFCD to lead a LA River Governance Model Study, and directed the CEO or her designee to enter into all necessary agreements with the County of Los Angeles, LACFCD, and/or City of Los Angeles to carry out and finance the Governance Study, and directed Metro staff to collaborate with all relative stakeholders throughout the development and implementation of recommendations from the Governance study.

 

Discussion

DISCUSSION

 

Decades before Measure M, the 1996 Los Angeles River Master Plan envisioned the five-mile Downtown corridor-stretching from the Arroyo Seco to Washington Boulevard-as a vital canvas for integrating urban flood control with community connections, aesthetic, and recreational revitalization.

 

The LA River Path advances that vision well beyond simple recreation. Entirely grade-separated from vehicular traffic, the path would offer a safe, multi-use transit corridor connecting commuters and visitors alike to key destinations throughout the urban core. Crucially, it would establish equitable mobility for historically underserved, transit-dependent communities along the river's east bank. By fusing safe recreational space for all ages and abilities with functional infrastructure, the project fundamentally reimagines mobility in Los Angeles.

 

The transformative impact of urban infrastructure is well illustrated by benchmark developments like the San Antonio River Walk and New York City’s High Line. By surrounding its downtown waterway with a seamless network of winding pathways and bridges, San Antonio converted an urban river into a world-class destination that draws millions of visitors annually and drives significant economic growth. Similarly, New York’s High Line reimagined a disused elevated rail line into a thriving linear park that empowers local communities through public programming while generating over $1.4 billion in tax revenue.

 

Environmental Review Process

 

On October 23, 2019, pursuant to CEQA Guideline Section 15082, Metro filed a Notice of Preparation (NOP) for the Project Draft EIR, with the State of California Office of Planning and Research (OPR) State Clearinghouse (SCH) and the Los Angeles County Clerk. Metro staff initiated public scoping for the Draft EIR, with a 45-day scoping period ending on December 6, 2019, and holding four in-person scoping meetings. Multiple commenters expressed preference for a BOC alternative, claiming lower construction costs, minimal rain-related closures in LA, and enhanced safety due to clearances from railroad tracks and overhead power lines near Union Station.

 

Following public scoping, Metro prepared conceptual engineering (CE) drawings for project alignments and design options, including environmental analysis and technical studies on 18 environmental resources. On December 18, 2025, Metro released the Draft EIR for public review during a 47-day comment period that concluded on February 2, 2026. In addition to the Draft EIR, Metro published the Preliminary Capital Cost Estimate Summary, Conceptual Engineering Plan Set, and Phase I Environmental Site Assessment, available on the Project website at <https://www.metro.net/projects/lariverpath/>

 

Alternatives and Options Evaluated in the Draft EIR

 

The Draft EIR evaluated seven alternatives with design options. Five alternatives close the entire 8-mile gap from Riverside Drive to Atlantic Boulevard, with each beginning and ending on the west bank of the LA River (maps in Attachment C, Figures C-1 thru C-7). The remaining two alternatives would serve as partial gap closures. Additionally, as required by CEQA, a “No Project” alternative was also considered. Draft EIR Executive Summary (Attachment D) is included for reference. A BOC alternative was considered but not carried forward into the Draft EIR (pursuant to CEQA Guidelines Section 15126.6(c)) due to significant concerns regarding safety, constructability, accessibility, and maintenance during periods of seasonal rains and flooding, as well as not meeting most of the project objectives. 

 

All alternatives have two key design features:

•                     Path Types: elevated (path on structures where either an incised or top-of-bank (TOB) right of way is unavailable), incised (path is cut into the trapezoidal embankment), and TOB (path on the riverbank) (Attachment C, Figure C-8). However, each alternative varies in alignment, path length, number and locations of river crossings, number and locations of access points, and distribution of path types

•                     River Crossings: pedestrian/bike crossings between each bank of the river to provide equitable access to communities on both banks of the river.

 

The core path alignment of each alternative generally follows the LA River channel. All alternatives connect to communities on both banks and to major destinations directly or indirectly, such as LA State Historic Park (LASHP), Albion Park, Union Station, Sixth Street PARC, and Bandini-Soto Triangle. The shorter alternatives, while connecting to communities on both banks, do not connect to all destinations.

 

Attachment C, Table C-1, summarizes project elements and capital cost for each alternative.

 

Community and Stakeholder Engagement and Comments

 

Public notification for the release of the Draft EIR was conducted in accordance with CEQA requirements and included direct mail (approximately 15,000 bilingual postcards), flyer door-to-door distribution (approximately 48,000 flyers), transit rider intercepts (390 transit riders), three legal advertisement publications (Los Angeles Times, La Opinión, and Daily News), e-blasts (approximately 6,700  contacts via email), media advertisements, earned media, press releases, and advertisement on the project website. The Notice of Availability (NOA) of the Draft EIR was filed with both the Los Angeles County Clerk and the California State Clearinghouse, including a Notice of Completion with the State Clearinghouse. The NOA was mailed to potentially affected government agencies, residents, tribal groups, and businesses at the start of the comment period to announce the availability of the Draft EIR and to invite participation in the four public hearings in January/February 2026.

 

During the 47-day public review period, Metro hosted three in-person and one virtual public hearings, during which the public could provide comments. Of the four public hearings, three were held on weekday evenings, and one on a weekend morning. The Draft EIR public review period included consultation with resource agencies, local, state, and federal agencies, cooperating and responsible agencies, including the USACE. In total, approximately 440 comment submissions (encompassing approximately 880 individual, delimited comments) were received through various methods, including oral and written comments at the Public Hearings, project email submissions, phone submissions, and online submissions.  A high-level summary of the community engagement conducted and the Draft EIR comments received are provided in Attachment E.

 

Overall, about 315 of the 440 comment submissions (over 70%) expressed support for the Project, regardless of any alternative. This included support for a BOC alternative, which some favored, claiming that it could be faster and cheaper to build.

As stated earlier, Metro has considered the BOC alternative but did not advance it for study in the Draft EIR due to its failure to meet most of the basic project objectives, safety concerns from permitting agencies, hydrological functions, and maintenance. Additionally, about 90 comment submittals (about 21%) expressed explicit preference for a specific alternative in the Draft EIR, including Option 2, often citing direct access to LASHP and Downtown Los Angeles.

 

The remaining comments received addressed several non-environmental topics, including requests for additional design details, concerns about path safety, cost estimates, and the funding gap.   

 

Metro received comment letters from six Responsible Agencies identified in the Draft EIR, as well as from 14 other agencies and stakeholders. Some specific comments received from these Responsible Agencies could further inform LPA selection, design refinement and/or additional study. These include:

 

•                     City of Los Angeles: Expressed support for an alternative that closes the existing 8-mile gap and provides access points to the EFCs. Expressed preference for TOB and incised path types over the elevated path type to minimize capital, operations, and maintenance costs. Apprehensive of the BOC designs due to flood vulnerability and lighting/access constraints.

 

•                     US Army Corps of Engineers (USACE): Expressed concerns about a BOC proposal because it raises life safety concerns and may require additional access ramps. Noted that USACE will not assume additional Operations and Maintenance (O&M) responsibilities associated with the Project.

•                     Los Angeles Department of Water and Power (LADWP): Noted that the project owner is to be clearly identified and held solely responsible for all liability, operation, and maintenance. Noted that no access point on Main Street on the west bank through LADWP property will be allowed and emphasized minimum clearances to LADWP facilities and over existing access roads.

 

Staff Recommendation for LPA

 

Based on environmental findings from the Draft EIR and comments received from individuals and key agency stakeholders during the Draft EIR review period, staff recommends Modified Option 2 as the LPA (Attachment F, Figure F-1), as it meets Project objectives most cost-effectively, accommodates community input on access locations along the corridor, and introduces no new environmental impacts.

 

•                     Project Objective - provides an alternative that caters to people of all ages and ability, provides direct access to major destinations, promotes equity by providing access on both banks, with more access to the EFCs on the east bank,

•                     Cost Effective - leverages an existing on-street Class IV segment, prioritizes top-of-bank (TOB) and incised paths over elevated structures where possible, and reduces river crossings

•                     Community Input - value engineered to respond to communities’ concern for cost, provides two additional accesses to be cleared environmentally for implementation later, subject to future funding.

 

For details on Modified Option 2, see Attachment F.

 

Preliminary Cost Estimates and Funding

 

The preliminary capital cost estimate for Modified Option 2 is approximately $872 million (2025$) based on 15 percent design. The cost estimates are based on early engineering and are consistent with those developed and published during the circulation of the Draft EIR. It includes baseline construction costs in 2025$, including labor, materials, and professional services, a right-of-way administration cost at 4% of the baseline construction costs, and a contingency 40% to account for known and unknown project risks.

 

The cost estimate for Modified Option 2 is lower than the cost estimates for all five 8-mile alternatives evaluated in the Draft EIR, which range between approximately $1.08 billion and $1.27 billion, depending on the alternative. Escalation to year of expenditure (YOE) was not included in the capital cost estimates and would be determined by a future funding plan and construction schedule.

 

The preliminary capital cost estimate for the LPA is $872 million, which exceeds approximately $433 million (escalated to 2025$ from 2015$) identified for the Project in the Measure M Expenditure Plan.

 

Preliminary estimates of annual O&M cost are between $1.3 million and $1.4 million. However, the O&M cost would have to be vetted and approved by the project’s committed O&M entity(ies). As mentioned earlier in this report, the Board noted in 2021 that Metro will partner with the City, County, and Federal agencies with ownership and

responsibility in the LA River corridor in regard to the overall management structure of the completed project, but will not assume any financial responsibility for operating and

maintaining the completed project.  This is based upon one of the biggest limitations for Metro  - the insignificant share of right-of-way along the 8-mile corridor.  While the City of Los Angeles (including Los Angeles Department of Water & Power) and the County of Los Angeles (including LA Flood Control) in total own approximately 80% of the right-of-way along the corridor, Metro ownership is less than 1%.  Of the remaining 20%, most is held as private ownership.  Hence, the permitting agencies other than USACE which has flood control jurisdiction over the river, will be the City of Los Angeles and the County of Los Angeles.

 

Further rationale for Metro not assuming responsibility for O&M is that at both its January 2026 and March 2026 meetings, the Board reviewed Metro’s current financial position, including an overview of the near-term budget outlook, which identified that starting in FY28, the operational fiscal cliff forecasts a deficit from $0.9 billion to as much as $2.0 billion.  Looking ahead, Metro projects a cumulative financial gap

in the range of $3.6 to $5.2 billion by FY30. The gap is comprised of $4.3 billion for Metro Transit Operations & Maintenance (O&M) and $0.9 billion for Metro Transit Capital Improvement Program (CIP).  Of the more than 130 different sources of funds available to Metro, less than 15 sources of funds are dedicated for mass transit operations.  Consequentially, any O&M funding set aside for an active transportation project takes away from available funding for transit operations.  As a result, the Board has adopted a foundational guiding principle to preserve essential services for addressing Metro’s fiscal cliff. 

 

Project Phasing and IOS

 

Based on available funding, Metro staff recommend advancing two simultaneous Initial Operating Segments (IOSs), each providing independent utility. The combined cost of these IOS segments is approximately $436 million, slightly exceeding the currently available Measure M funding of $433 million. As the project advances and reaches key milestones, such as certification of the Final EIR, staff will need to have commitments from County and/or City agencies to support in the development and lead the operations and maintenance of the project. Upon confirmation of these commitments, refinements to  the scope including pursuing value engineering opportunities will require review and concurrence by the agencies assuming operations and maintenance of the project.  These approvals are necessary while Metro is pursuing competitive Active Transportation Program grants at the state level and, if applicable, federal active transportation funding to close the remaining gap.

 

Attachment F, Table F-1, presents the cost and funding breakdown.

 

Project phasing enables incremental investment, allowing benefits to be realized with identified funds and enabling some of the Project’s mobility benefits to be realized sooner. Metro staff recommends two simultaneous IOS segments, each with independent utility, extending the existing active transportation network along the LA River and providing initial access to the many EFCs and key trip generators, including population centers, employment centers, and key destinations. These segments are:

 

•                     IOS-north: extend from the northern terminus of the Modified Option 2 at Riverside Drive to Spring Street and

•                     IOS-south: Modified Option 2 between Sixth Street and Atlantic Boulevard.

 

The IOS segments, shown in Attachment F, Figure F-2, collectively would include 7 access points, with 5 on the east bank, and 2 on the west bank. Combined, the IOSs would close approximately 5.5 miles of the 8-mile gap.  The IOS segments are not expected to impact the USACE’s LA River Ecosystem Restoration Project during its implementation. To bridge the gap between IOS-north and IOS-south, staff identified planned Class IV cycle tracks in the City of Los Angeles’ 2035 Mobility Plan. Metro will work with the City of Los Angeles to prioritize, these planned Class IV cycle tracks, in combination with the existing on-street bike lanes, which can serve as an interim connection until funding for the off-street river channel paths (between Broadway/Spring Street and Sixth Street) is secured. This interim route will improve access to EFCs directly adjacent to the LPA, particularly in Lincoln Heights, Chinatown, and Boyle Heights.

 

Some of the potential interim corridors identified are:

1)                     Spring/Alameda Safety & Mobility Project - anticipated completion 2026-2027

2)                     Alameda Corridor (Spring to Sixth)

3)                     Cesar Chavez Corridor (Alameda to Mission)

4)                     First Corridor (Alameda to Boyle)

5)                     Main Corridor (LA River to Mission)

6)                     Mission Corridor (Cesar Chavez to Main)

7)                     Whittier Corridor (Sixth to Soto)

8)                     Soto Corridor (Whittier to First)

 

Metro Cost-Benefit Analysis

 

At the July 2025 Board meeting, the Board approved a methodology framework for a Cost Benefit Analysis (CBA) to be conducted on Metro capital projects at key milestones to support investment and funding decisions. The CBA methodology includes two related components: Weighted Benefits Analysis (WBA) and Benefit-Cost Ratio (BCR).

 

The Project CBA, conducted in August 2026, evaluated six alternatives: Modified Option 2 (the staff-recommended LPA) and the five 8-mile alternatives evaluated in the Draft EIR. The WBA component of the CBA found that the Project provides significant benefits locally and regionally for all alternatives. Based on several qualitative and quantitative evaluation metrics, Modified Option 2 received a WBA score of 5.8 out of 7.0, which is comparable to the five 8-mile alternatives, which range from 5.8 to 6.0. All alternatives scored comparably with respect to path user demand, and connectivity to jobs, housing, amenities, public transit, and the existing and planned bicycle network. Under the WBA theme of Operational Sustainability & Delivery, Modified Option 2 scored the highest due to its greater cost-effectiveness and lower complexity in permitting and coordination with adjacent projects.

 

The BCR analysis found that Modified Option 2 performed best, with a BCR of 0.23. The BCR compares a project’s total monetized costs against a set of calculated monetizable benefits. BCRs below 1 indicate that a project will cost more than the monetizable benefits it creates. It is important to note that not all benefits or costs are quantifiable or easily monetized, especially at a larger regional scale such as this case. Specifically, the BCR does not capture all social, safety, and network benefits.  Hence, the BCR is presented alongside the WBA to provide more robust analysis of costs relative to benefits.

 

Modified Option 2 delivers comparable benefits at significantly lower construction costs (at least 20% lower) than the other five 8-mile alternatives evaluated in the Draft EIR. The recommended LPA has a BCR (0.23) nearly double that of the lowest-performing alternative (0.13).  Modified Option 2 achieves these cost savings by minimizing expensive elevated structures and river crossings, and prioritizing the cost-effective incised, TOB, and on-street path types.

 

Additional details on the Project CBA are presented in Attachment G.

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

By separating cyclists and pedestrians from vehicle traffic in a high-collision corridor, the Project will improve safety for active transportation users.

 

Financial_Impact

FINANCIAL IMPACT

 

The Fiscal Year 2026-2027 budget assigned about $4.4 million in funding to the project (No. 474303) for professional services within Countywide Planning and Development, including support for technical analysis and community engagement in response to the Draft EIR. Since this is a multi-year project, Cost Center Managers, Chief Planning Officer, and Chief Program Management Officer will be responsible for budgeting in future years.

 

Impact to Budget

Funding for this project comes from Measure M Capital Subfund for Highway, Active Transportation and Complete Streets - both from the 17% Highway Construction and the 2% Metro Active Transportation Program. These funds are not eligible for bus or rail operating expenses.

 

Equity_Platform

EQUITY PLATFORM

 

Socioeconomic data reveals that approximately 23% of the population within this 3-mile radius live in poverty, and 17% of working-age individuals either walk, bike, or use public transit to commute. Within the Project area, the proportion of older adults is relatively low (8.09%), while Black, Indigenous, and People of Color (BIPOC) individuals constitute a substantial 92%, with Latinos comprising 77%. The Project promises mobility choices and regional access to employment, education, and recreational opportunities for populations both in the Project vicinity and along the wider LA River active transportation network. The Project would be directly accessible to EFCs in Elysian Valley, Lincoln Heights, Chinatown, and Boyle Heights in the City of Los Angeles, as well as the City of Maywood.

 

To engage hard-to-reach populations who do not typically participate in community meetings, Metro circulated materials and notices, including the Draft EIR Executive Summary in both English and Spanish, held pop-up events at community events, and performed transit rider intercepts at rail stations and bus stops in the Project area. Metro released the Draft EIR on the online digital platform, improving accessibility and navigability of the environmental document. The online platform is also compatible with common Internet browsers and smartphones, with translation functions, allowing community members to translate the document from English to a language of their choice. During the public review and comment period, all in-person public hearings were held at EFCs in Lincoln Heights, Boyle Heights, and the City of Maywood to better engage hard-to-reach communities. All public hearings, including the virtual public hearing, included live Spanish translation services.

 

As part of future stages of project development, Metro would expand partnerships with community-based organizations (CBOs) to help disseminate project information, advise on outreach methods, and engage a diverse set of project stakeholders as the Project advances. Metro is committed to expanding community outreach to include additional languages spoken in EFCs and beyond, and to ensuring meaningful connections with riders of all ages and abilities, including seniors, people with disabilities, and those with mobility challenges.

 

Vehicle_Miles_Traveled_Outcome

VEHICLE MILES TRAVELED OUTCOME

 

Vehicle Miles Traveled (VMT) and VMT per capita in Los Angeles County are lower than national averages, the lowest in the Southern California Association of Governments (SCAG) region, and on the lower end of VMT per capita statewide, with these declining VMT trends due in part to Metro’s significant investment in rail and bus transit.* Metro’s Board adopted VMT reduction targets that align with California’s statewide climate goals, including achieving carbon neutrality by 2045. To ensure continued progress, all Board items are assessed for their potential impact on VMT.

 

As part of these ongoing efforts, this item is expected to contribute to further reductions in VMT. This Project supports Metro’s systemwide strategy to reduce VMT through planning activities that will improve and further encourage active transportation, transit ridership, and ridesharing. When complete, this project will provide a seamless, 32-mile active transportation network, offering car-free mobility options for users. Metro’s Board-adopted VMT reduction targets were designed to build on the success of existing investments, and this item aligns with those objectives.

 

Metro conducted a preliminary analysis to show that the net effect of this project will decrease VMT. The Draft EIR estimated that by 2031, the project would reduce average daily VMT by approximately 0.2% to 2% (translating to 20 to 1,410 vehicles per day in 2031, depending on roadway characteristics) due to trip reduction. This would also help the region meet climate change goals by reducing greenhouse gas emissions and regional energy use.

 

*Based on population estimates from the United States Census and VMT estimates from Caltrans’ Highway Performance Monitoring System (HPMS) data between 2001-2019.

 

Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

The Project supports the strategic plan goals identified in Vision 2028:

•                     Goal 3: Enhance communities and lives through mobility and access to opportunity;

•                     Goal 4: Transform LA County through regional collaboration and national leadership; and

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

The Board may choose to defer selection of an LPA and IOS segments given the low benefit cost-ratio. This is not recommended because it would delay project delivery thereby continuing to drive costs higher and moving it further from its Measure M schedule.  Deferring selection may also delay development of the LA River Governance Model Study as approved in the May 2026 Metro Board Motion (Attachment B).

 

The Board could select other alignments evaluated in the 2025 Draft EIR, or the No Project Alternative. However, Modified Option 2 delivers comparable benefits at the lowest cost per unit of benefit. It offers the lowest construction cost while maximizing ridership and equity, and provides a realistic opportunity to close the entire 8-mile gap: with the two IOSs, almost entirely within the remaining Measure M budget; the remaining gap of 2.5 miles closed in the interim, via non-Metro projects (City of Los Angeles on-street connections, which are existing, in construction or planned). The No Project alternative is not recommended as it does not meet the Project needs and objectives.

 

Next_Steps

NEXT STEPS

 

Upon Board approval of an LPA, staff will coordinate on directions and findings that emerge from the LA River Governance Model Study. As directed by the Board in November 2021, Metro will partner with these agencies but will not assume any financial responsibility for operating and maintain the completed project considering Metro owns about 1% of the ROW along the corridor.  Staff will collaborate with the County of Los Angeles, LACFCD, and/or City of Los Angeles, as well as all relevant stakeholders, including the USACE, by providing all requested Project-related information, technical expertise, right-of-way data, and review support for the Study. Staff collaboration also includes identifying the agency/agencies to assume ownership, delivery, and maintenance of the final Project.

 

Once the Governance Study identifies the agency/agencies for ownership, delivery, and maintenance of the final Project, and their commitments formalized, staff will advance the CEQA environmental clearance process and further design will be coordinated with the agency/agencies identified to assume ownership, delivery, and maintenance of the project, including development of the Final EIR for only IOS-north and IOS-south (total of 5.5 miles of the 8-mile gap), and proceed with a federal Environmental Assessment (EA), under the National Environmental Policy Act (NEPA), which is necessary for the USACE permit process.

 

As the project progresses, staff will continue coordinating with the Early Intervention Team to identify project risks and track mitigation opportunities. Once design and environmental re-initiate, staff will pursue activities to control costs for the IOS-north and IOS-South, including value engineering, collaborating with responsible jurisdictions exercising cooperative agreements, and pursuing streamlining the permitting process. Concurrently, staff will support the agreed upon governance structure to continue to support the exploration of grant funding opportunities for active transportation projects at the local, state, and federal levels to help minimize the funding gap.

 

Attachments

ATTACHMENTS

 

Attachment A - June 2021 Metro Board Amendment

Attachment B - May 2026 Metro Board Motion 46

Attachment C - Draft EIR Alternatives - Path Types

Attachment D - Draft EIR Executive Summary

Attachment E - Draft EIR Outreach Summary

Attachment F - LPA & IOS

Attachment G - LA River Path Project Cost-Benefit Analysis

 

Prepared_by

Prepared by: E. Cadena, Transportation Planner

K. Decastro, Manager Transportation Planning

M.Gupta, Senior Manager, Transportation Planning

J. Liu, Senior Director, Countywide Planning & Development

D. Roybal, Deputy Executive Officer, Countywide Planning & Development

A. Yoh, Senior Executive Officer, Countywide Planning & Development

D. Mieger, Senior Executive Officer, Countywide Planning & Development

M. Dierking, Director, Community Relations

J. Wei, Executive Director, Project Engineering/Delivery

C. Hoshijima, Executive Officer, Strategic Financial Planning

 

Reviewed_By

Reviewed by: R. Sosa, Chief Planning Officer