Title: AUTHORIZE the Chief Executive Officer (CEO) to: A. AWARD a five-year firm fixed unit rate Contract No. PS131648000 to Intueor Consulting, Inc. to provide program support for the implementation of the Advanced Transportation Management System (ATMS) II Computer Aided Dispatch / Automated Vehicle Location (CAD/AVL) System in the Not-to-Exceed (NTE) amount of $10,799,089.84, subject to the resolution of any properly submitted protest(s), if any; and B. EXECUTE individual contract modifications within the Board-approved contract modification authority.
Sponsors: Board of Directors - Regular Board Meeting
Indexes: Advanced Transportation Management System, Automatic vehicle location, Budgeting, Bus Acquisitions, Bus Operations Control Center, Computers, Contracts, Customer service, Fleet management, Informational Report, Procurement, Program, Program Management, Radio, Radio equipment, Radio frequency, Rolling stock, Safety, Transit Radio System
Attachments: 1. Attachment A - Procurement Summary, 2. Attachment B - DEOD Summary, 3. Presentation
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Meeting_Body

OPERATIONS, SAFETY, AND CUSTOMER EXPERIENCE COMMITTEE

NOVEMBER 20, 2025

 

Subject

SUBJECT:                     ADVANCED TRANSPORTATION MANAGEMENT SYSTEM (ATMS) II PROGRAM IMPLEMENTATION SUPPORT

 

Action

ACTION:                     AWARD CONTRACT

 

Heading

RECOMMENDATION

 

Title

AUTHORIZE the Chief Executive Officer (CEO) to:

 

A.                     AWARD a five-year firm fixed unit rate Contract No. PS131648000 to Intueor Consulting, Inc. to provide program support for the implementation of the Advanced Transportation Management System (ATMS) II Computer Aided Dispatch / Automated Vehicle Location (CAD/AVL) System in the Not-to-Exceed (NTE) amount of $10,799,089.84, subject to the resolution of any properly submitted protest(s), if any; and

 

B.                     EXECUTE individual contract modifications within the Board-approved contract modification authority.

 

Issue

ISSUE

 

The ATMS II program represents a major agency-wide initiative impacting every bus, rail car, bus/rail operations control centers, as well as bus/rail operators and supervisors. The awarded contract being recommended will support the implementation and integration of this new system across Metro’s operations. The goal is to deploy comprehensive fleet management and customer-focused tools in alignment with Metro’s NextGen transit vision and to prepare for upcoming transit-focused special events.

 

Background

BACKGROUND

 

A contract was awarded to Clever Devices Ltd. in June 2025 to upgrade Metro’s bus and rail fleet management system as part of the ATMS II program. However, the successful implementation of a program of this magnitude demands far more than simply delivering technology. It requires rigorous program management, complex systems integration, stakeholder coordination, and continuous oversight to ensure that the technology is not only deployed but fully adopted and operationalized across Metro’s bus and rail fleet.

Metro will need to maintain the current Bus Operations Control (BOC) center while setting up a new hosted solution and data center for the Land Mobile Radio (LMR) equipment. 

In addition, the new ATMS II Program must integrate with several existing systems, including HASTUS Daily, EAM (Enterprise Asset Management), SWIFTLY (Arrival Prediction Software), DIMS (Digital Incident Management System), HR (Human Resources) systems, and more. This effort will involve collaborating with technical teams from each area to ensure no data is lost and both systems remain fully functional until the old ATMS system is phased out.

Metro is also currently managing multiple ongoing implementations that necessitate synchronization with the new ATMS II Program, such as transitioning its entire bus fleet to electric buses. The ATMS II implementation must align closely with this fleet upgrade to ensure seamless integration with both new and existing buses. Specialized software coordination is required to monitor and manage electric vehicles effectively within the system. 

Moreover, Metro will be upgrading its radio system from analog to digital. This transition will involve installing new radio equipment at Metro's Radio Frequency (RF) sites throughout LA County and developing a new system to accommodate these changes. At minimum, Metro will be performing a major upgrade to the existing radio towers as well as the entire voice radio system for the bus fleet.

Discussion

DISCUSSION

 

Given the overlap of the ATMS II implementation with multiple projects, meticulous orchestration is crucial to prevent any operational disruption. An experienced team with a strong background in CAD/AVL and bus rail technology implementation is essential to ensure continuity as well as a smooth transition. The new team will be complementing the current Metro staff to help achieve the essential goal of a seamless transition to ATMS II.

 

Awarding this contract to Intueor Consulting, Inc. will provide Metro with dedicated program support resources, including technical project management, system integration coordination, testing oversight, and risk management. Intueor Consulting, Inc. has extensive experience supporting large-scale transit technology projects, including Computer Aided Dispatch/Automatic Vehicle Location implementations, and has worked closely with Metro staff on prior efforts.

 

This support will be critical to coordinate among multiple vendors and Metro departments, such as integrating Computer Aided Dispatch/Automated Vehicle Location with existing enterprise systems, as well as aligning implementation with parallel initiatives, including the bus electrification program and radio system upgrades. Without this additional program support, Metro will increase the risk of delays, operational disruptions, or incomplete integration, which could impact service reliability and customer experience. Engaging Intueor Consulting, Inc. under this contract will provide the expertise and capacity needed to keep the ATMS II program on track, as well as ensure that Metro delivers a modernized, integrated fleet management system that meets the agency’s operational and customer service goals.

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

The award of this contract does not directly impact the safety of Metro’s bus or rail operations. However, the program support provided through this contract will help ensure a safe and reliable implementation of the ATMS II system by coordinating system integration, testing, and transition activities. A modernized ATMS system will enhance Metro’s ability to monitor and manage fleet operations in real time, improving incident response, operator communication, and overall passenger safety.

 

Financial_Impact

FINANCIAL IMPACT

 

 Funding for this contract is included within the Life of Project (LOP) budgets for CP 207168 - ATMS Bus System Replacement and CP 207185 - ATMS II System Integration, with a combined total of $167 million. The ATMS II contract, valued at $129.7 million, was awarded in June 2025. For Fiscal Year 2026 (FY26), the project’s annual budget allocation is $11,207,272. The remaining $28 million is designated for hardware, labor, and Radio Frequencies (RF) modifications in support of the ATMS II implementation. Since this is a multi-year program, the project manager and the Chief Operations Officer shall be responsible for future fiscal year budgeting.

 

Impact to Budget

The current funding source for this action is TDA 4, which is eligible for bus and rail operations and capital projects.

Equity_Platform

EQUITY PLATFORM

 

The award of this contract will support the implementation of ATMS II, which is designed to improve service reliability, real-time information, and incident response across Metro’s bus and rail network. These improvements will benefit customers, especially those who rely most on public transit, such as low-income riders, people of color, seniors, and persons with disabilities. Enhanced fleet management and customer-facing tools will provide more accurate service information and reduce service disruptions, ensuring a more consistent transit experience.

 

The Diversity and Economic Opportunity Department (DEOD) established a 22% Disadvantaged Business Enterprise (DBE) goal for this solicitation.  While Intueor Consulting, Inc. made a DBE commitment, the U.S. Department of Transportation (USDOT) has issued an Interim Final Rule (IFR) that makes changes to the DBE Program, including suspension of goals and enforcement, effective October 3, 2025.  Metro is currently reviewing the Interim Final Rule (IFR) to identify necessary program and procedural changes to ensure full compliance. 

 

Although the DBE commitment is not a factor in the staff recommendation, there are two certified small businesses participating in this contract.  This is noteworthy since small businesses are vital for the economy as they drive job creation, foster innovation, and strengthen local communities.

 


Vehicle_Miles_Traveled_Outcome
VEHICLE MILES TRAVELED OUTCOME

 

VMT and VMT per capita in Los Angeles County are lower than national averages, the lowest in the SCAG region, and on the lower end of VMT per capita statewide, with these declining VMT trends due in part to Metro’s significant investment in rail and bus transit.* Metro’s Board-adopted VMT reduction targets align with California’s statewide climate goals, including achieving carbon neutrality by 2045. To ensure continued progress, all Board items are assessed for their potential impact on VMT.

 

As part of these ongoing efforts, this item is expected to contribute to further reductions in VMT. This item supports Metro’s systemwide strategy to reduce VMT through operational activities that will minimize negative impacts to service reliability and customer experience and further encourage transit ridership, ridesharing, and active transportation. Metro’s Board-adopted VMT reduction targets were designed to build on the success of existing investments, and this item aligns with those objectives.

 

*Based on population estimates from the United States Census and VMT estimates from Caltrans’ Highway Performance Monitoring System (HPMS) data between 2001-2019.

 

Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

This Board action supports Strategic Goal 2: Deliver outstanding trip experiences for all transportation system users, as we are committed to providing attractive, affordable, efficient, and safe service. 

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

Metro could choose not to award this contract and rely solely on existing staff resources. However, this alternative is not recommended, as the ATMS II program is highly complex and requires dedicated expertise in Computer Aided Dispatch/Automatic Vehicle Location, system integration, testing, as well as risk management. Without additional program support, Metro would face significant risks of delays, operational disruptions, and cost overruns.  This alternative is also preferred to the staff increase option, since the program support effort is not intended to extend indefinitely. 

 

Next_Steps

NEXT STEPS

 

Upon approval by the Board, staff will execute Contract No. PS131648000 with Intueor Consulting, Inc., and establish a plan and schedule for the Program Support of the ATMS II CAD/AVL system.

 

Attachments

ATTACHMENTS

 

Attachment A - Procurement Summary

Attachment B - DEOD Summary

 

Prepared_by

Prepared by:                      Bahram Chaudry, Senior Director, Operations (213) 922 - 6441

Al Martinez, Deputy Executive Officer, Operations (213) 276 - 0117

Debra Avila, Deputy Chief Vendor/Contract Management Officer (213) 418-3051

 

Reviewed_By

Reviewed by:                      Conan Cheung, Chief Operations Officer, (213) 418-3034