Skip to main content
File #: 2025-0869   
Type: Informational Report Status: Agenda Ready
File created: 9/25/2025 In control: Construction Committee
On agenda: 11/19/2025 Final action:
Title: AUTHORIZE the Chief Executive Officer to execute the FY26 Annual Work Plan Budget for the City of Los Angeles (Attachment A).
Sponsors: Construction Committee
Indexes: Budget, Budgeting, Central Los Angeles subregion, City of Los Angeles, Construction, Informational Report, Metro Vision 2028 Plan, Plan, Project delivery, Project management, San Fernando Valley subregion, South Bay Cities subregion, Strategic planning, Westside Cities subregion
Attachments: 1. Attachment A – FY26 Annual Work Plan Anticipated Budget for the City of LA, 2. Presentation
Related files: 2025-0520
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Meeting_Body

CONSTRUCTION COMMITTEE

NOVEMBER  19, 2025

 

Subject

SUBJECT:                     THIRD PARTY ADMINISTRATION - CITY OF LOS ANGELES

 

Action

ACTION:                     APPROVE RECOMMENDATION

 

Heading

RECOMMENDATION

 

Title

AUTHORIZE the Chief Executive Officer to execute the FY26 Annual Work Plan Budget for the City of Los Angeles (Attachment A).

 

Issue

ISSUE

 

During the design, construction and maintenance phases of Metro projects, a significant amount of support is required from local jurisdictions via an Annual Work Plan (AWP). The AWP serves as a commitment from the agency for the reimbursement of services by the City of Los Angeles reviewing departments for an estimated amount of services. Without an AWP, the City of Los Angeles departments have no funding sources to support the projects in a timely manner in order to meet Metro’s schedules. 

 

Background

BACKGROUND

 

In April of 2024, a new Master Cooperative Agreement (MCA) was executed between Metro and the City of Los Angeles. The intent of the agreement is to establish a streamlined process among both entities to successfully construct Metro’s ongoing projects. A primary function of the MCA is to clearly identify a yearly budget for each City department to provide those City services, which is labeled the AWP.  This work plan is consistent with the principles of the new MCA, which contains a streamlined escalation ladder, improved processes for design reviews and acceptance, early involvement and improved collaboration processes, and the inclusion of a Project Liaison to coordinate across City departments for future mega projects.

 

Discussion

DISCUSSION

 

The AWP funds Metro’s project plan reviews from various City of Los Angeles departments to support design and construction project plans on an annual basis. These services are essential for project delivery, which includes securing plan reviews and approvals, ensuring quality and effective construction measures, timely inspections, and other functional efforts as described above. All services are centered to avoid delays and effectively deliver the projects with minimal impacts on the community and provide benefits of enhanced mobility and regional access to underserved populations within the respective project areas.

 

Without the AWP process, the Agency would be subject to submitting design packages and permit requests via the retail counters at each respective Bureau and Department. This would put Metro in the queue with all others seeking development services from the City - thereby increasing time to review and almost certainly opening projects up to the risk of delay. 

 

The action contained herein provides funding for the City of Los Angeles participation in projects within the limit of the current approved FY26 budget for Third Party review and maintenance (Attachment A).

 

Metro’s efforts to proactively manage these costs will include the following:

 

A.                     Controlling the design review process through the early coordination of design efforts to define scope and establish/clarify standards and requirements.

B.                     Reviewing submittals for completeness.

C.                     Ensuring that third party requirements are identified and addressed prior to sending to the third party.

D.                     Reviewing timesheets with each third-party organization on a monthly basis to ensure that the hours charged are appropriate.

E.                     Conducting executive and staff level partnering with third parties.

 

The MCA and AWP are currently based on a reimbursement model for work performed by the City supporting Metro’s projects. In light of Executive Directive 16, issued by Mayor Bass on October 17, 2025, the City has expressed interest, and Metro is open to pursuing adjusting the funding model  to the City in areas where permit streamlining and development of innovative measures to accelerate project delivery are implemented. Approval of this item does not limit the City or Metro to advance these discussions.

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

The recommended action has no impact on safety.

 

Financial_Impact

FINANCIAL IMPACT

 

The funding of $35,804,586 which may be obligated and spent under this one-year work plan, is included in the FY26 adopted budget in the projects requiring the services to be performed by the City of Los Angeles as outlined in Attachment A. Since these are multi-year projects, the Project Managers and the Chief Program Management Officer will be responsible for budgeting future year’s costs. These fund sources are not eligible for rail and bus operating expenses.

 

Equity_Platform

EQUITY PLATFORM

 

While considering the projects, Metro will provide an estimated 42 miles of new transit and active transportation systems (pedestrian, bicycle, rail and bus) and 11 potential passenger stations within the City of L.A limits and within and near eight Equity Focus Communities (EFC).   This Board item action will reduce the likelihood of transit and active transportation project delays as well as provide other tangible benefits to people travelling in Los Angeles. This includes expedited, streamlined projects that improve safety and access for multimodal users with minimal negative impacts to the local communities. This will ultimately lead to our operating system providing a world class transit system with reduced air and noise pollution, more walkable neighborhoods, better transportation amenities for individuals with disabilities, less congestion and collisions, and will ultimately better connect communities. Not approving this action will have delays on the projects, which will ultimately affect the users of the system.

 

Vehicle_Miles_Traveled _Outcome

VEHICLE MILES TRAVELED OUTCOME

 

VMT and VMT per capita in Los Angeles County are lower than national averages, the lowest in the SCAG region, and on the lower end of VMT per capita statewide, with these declining VMT trends due in part to Metro’s significant investment in rail and bus transit.*  Metro’s Board-adopted VMT reduction targets align with California’s statewide climate goals, including achieving carbon neutrality by 2045. To ensure continued progress, all Board items are assessed for their potential impact on VMT. 

 

While this item does not directly encourage taking transit, sharing a ride, or using active transportation, it is a vital part of Metro operations, as it facilitates the progress of critical work with the City of Los Angeles departments to reduce red tape and improve outcomes in the planning and construction of Metros projects, which will serve to reduce VMT. Because the Metro Board has adopted an agency-wide VMT Reduction Target, and this item supports the overall function of the agency, this item is consistent with the goals of reducing VMT.

 

*Based on population estimates from the United States Census and VMT estimates from the highway performance monitoring system data between 2001-2019.

 

Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

Metro’s transit projects support the following strategic plan goals identified in Vision 2028: 

                     Goal 1: Provide high-quality mobility options that enable people to spend less time traveling. 

                     Goal 3: Enhance communities and lives through mobility and access to opportunity and.

                     Goal 5: Provide responsive, accountable, and trustworthy governance within the Metro organization.

 

By executing the AWP for FY26 and allowing the City departments to continue reviewing plans while advancing Metro’s transportation projects, it would positively support Metro’s overall plan and goal of expanding the transportation network, increasing mobility for all users and improve LA County’s overall transit networks and assets.

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

The Board may reject the recommendation and direct us to include this work under Construction or Professional Services contracts. This is not recommended because it will have the effect of significantly delaying Metro projects.

 

Next_Steps

NEXT STEPS

 

Upon Board approval of the AWP, the City of Los Angeles will submit the annual work plan to the Los Angeles City Council and Mayor’s Office for adoption.

 

Attachment

ATTACHMENT

 

Attachment A - FY26 Annual Work Plan Anticipated Budget for the City of Los Angeles

 

Prepared_by

Prepared by:                      Eduardo Cervantes, Executive Officer; 213-922-7255

 

 

Reviewed_By

Reviewed by:                      Timothy Lindholm, Chief Program Management Officer; 213-922-7297