Meeting_Body
SYSTEM SAFETY, SECURITY AND OPERATIONS COMMITTEE
FEBRUARY 16, 2017
Subject/Action
SUBJECT: POWER SWEEPING SERVICES FOR ALL METRO FACILITIES
ACTION: APPROVE CONTRACT MODIFICATION
Heading
RECOMMENDATION
Title
AUTHORIZE the Chief Executive Officer to execute Modification No. 8 to Contract No. OP33672974, with Nationwide Environmental Services Inc., for power sweeping services, to exercise the second, one-year option in the amount of $1,563,646.08 increasing the total contract value from $5,911,123.32 to $7,474,769.40 and extend the contract term from June 1, 2017 to May 31, 2018.
Issue
ISSUE
Under this Contract with Nationwide Environmental Services Inc., power sweeping services are provided on a regular basis in accordance with the maintenance schedule and frequencies specified within the contract scope of work. The first option year for this Contract will expire on May 31, 2017. The contractor has been providing satisfactory maintenance services.
To continue providing the required power sweeping services, a Contract Modification is required to exercise option year two extending the period of performance through May 31, 2018.
Discussion
DISCUSSION
Under this Contract and option, power sweeping services are provided throughout Metro bus and rail facilities and State Owned Park and Ride (P&R) lots. This includes approximately 62 lots at bus divisions, terminals, locations, and stations, 43 lots at rail system stations and divisions, and 42 State Owned P&R lots.
The services provided under the existing Contract and options are based on an aggressive routine maintenance schedule to ensure delivering clean and well maintained parking lots and structures throughout Metro facilities.
Determination_Of_Safety_Impact
DETERMINATION OF SAFETY IMPACT
The approval of this item will provide on-going power sweeping services, improve Metro bus and rail facilities overall appearance and cleanliness, and provide prompt response time to ensure delivery of safe, quality, on-time, and reliable services system-wide.
Financial_Impact
FINANCIAL IMPACT
Funding of $130,303.84 under this Contract for the remainder of FY17 is included in the FY17 budget in cost center 3367 - Facilities Property Maintenance, account 50308, Service Contract Maintenance, under various projects.
Since this is a multi-year contract, the cost center manager, project managers, and Executive Director, Maintenance will ensure that the balance of funds is budgeted in future fiscal years.
Impact to Budget
The source of funds for this action will come from Federal, State, and local funding sources including sales tax and fares that are eligible for Bus and Rail Operating projects. These funding sources will maximize fund use based on funding allocation provisions.
Alternatives_Considered
ALTERNATIVES CONSIDERED
Staff considered providing this service with in-house staff. This would require the hiring and training of additional personnel, purchase of additional equipment, vehicles, and supplies to support the expanded responsibility. Staff's assessment indicates this is not a cost-effective option for Metro.
Next_Steps
NEXT STEPS
Upon approval by the Board, staff will execute Modification No. 8 to Contract No. OP33672974 to exercise option year two with Nationwide Environmental Services Inc., effective June 1, 2017, to provide power sweeping services system-wide.
Attachments
ATTACHMENTS
Attachment A - Procurement Summary
Attachment B - Contract Modification/Change Order Log
Attachment C - DEOD Summary
Prepared_by
Prepared by: Brady Branstetter, DEO, Facilities Maintenance, (213) 922-6767
Lena Babayan, Sr. Director, Facilities Maintenance, (213) 922-6765
Reviewed_By
Reviewed by: James T. Gallagher, Chief Operations Officer, (213) 922-4424
Debra Avila, Chief Vendor/Contract Management Officer, (213) 418-3051