Meeting_Body
CONSTRUCTION COMMITTEE
OCTOBER 15, 2020
Subject
SUBJECT: AIRPORT METRO CONNECTOR PROJECT
Action
ACTION: APPROVE RECOMMENDATION
Heading
RECOMMENDATION
Title
CONSIDER:
AUTHORIZING the CEO to direct specific Rail and Bus operations, communications and security equipment from single sources and to procure subcontracts to design, program and install proprietary rail and rail-car operating systems and equipment for the Airport Metro Connector (AMC) Project in order to safely and securely link critical station infrastructure with the currently installed rail systems and equipment on the Crenshaw/LAX Line (CLAX).
(REQUIRES TWO-THIRDS VOTE)
Issue
ISSUE
This action is to direct and allow the bidders on the AMC Project (AMC), currently issued, to single source specific rail and bus operations, communications, security and safety equipment and systems for the AMC Station Project to safely and securely connect and operate with the same equipment currently installed as part of the network for the CLAX line. As a new station on the established CLAX line, this procurement is required to ensure that the AMC Station has the critical equipment and systems in order to mitigate conflicts and maintain operations, communications, safety and security during both construction and public operations with the CLAX and Metro Systems overall.
Background
BACKGROUND
After award of the CLAX Line design-build contract authorized by the Board on June 26, 2014, a new Metro transit station at 96th Street was added to the Crenshaw/LAX Transit Corridor to connect with the future Airport Automated People Mover (APM) system being built and operated by the Los Angeles World Airports (LAWA). This new station (AMC) was to be implemented under stand-alone contracts, competitively procured, for design and construction, and be fully integrated with the operations of the CLAX Line once constructed.
During extensive coordination of rail and bus operations throughout the development of the AMC Station project design, concerns were raised by Metro Rail Communications Engineering, Systems Engineering, Operations, and IT Departments regarding the integration of the following systems to the CLAX Line:
• Rail Operations Systems - Rail Car and Track Operations
• Rail and Bus Communications (TPIS, VMS, Public Address, Fire Alarm)
• Rail and Bus Security - Specifically security cameras and access controls
• Future Maintenance for these Systems
To meet these concerns, the 100% design and construction documents for the AMC Station have been fully coordinated with the required single-source components included within; however, specific Board approval to do so is required.
Discussion
DISCUSSION
The justification for this single source procurement is based on avoiding current and future operational difficulties, including safety and security conflicts with the CLAX Line during both the construction of the AMC Project and the final use of the Station once open for public operations. The procurement of standardized systems equipment by the AMC Contractor, as prescribed in the contract documents, will provide secure and stable transition and operations of the following in delivering the AMC Project:
• Integration of Rail Communications, Rail and Rail Car Programming, Fire Alarm Systems to the current CLAX Line and Southwest Yard Maintenance Facility (SWY), for the temporary transfer and operations of the CLAX rail service during AMC construction;
• Continuity and stabilization in the integration and performance of systems for the final AMC Station to the CLAX Line and Metro Systems overall;
• Fully integrated Station Security between two distinct security systems (Metro Rail and Metro Bus);
The AMC Project Team is confident that these conditions can only be addressed with the procurement of specific equipment and related operating systems established on the CLAX Line.
A list of the specific components and systems equipment included within the IFB and this Board action is included as Attachment A. During construction of the AMC project, Metro Project Management, in coordination with Vendor/Contract Management, will review and accept all project equipment submittals to ensure proper compliance with the plans and specifications and this board action.
Determination_Of_Safety_Impact
DETERMINATION OF SAFETY IMPACT
Approval of this action and the award of the AMC construction contract will result in a positive impact on safety by avoiding operations, safety and security conflicts with the CLAX Line. The installation of these bus and rail communication systems and security system, will ensure safe and uninterrupted service during the construction of the AMC Project and the final use of the Station once open for public operations.
Financial_Impact
FINANCIAL IMPACT
This board report seeks Board approval for sole source systems and equipment which are to be acquired by the contractor(s) and/or subcontractor selected to work on the AMC project. The cost of the systems and equipment is to be incorporated as part of the construction contract bid price. FY21 budget includes funds for this effort. Details will be provided at the time of contract award as the procurement is currently in blackout phase. Since this is a multi-year contract, the cost center manager, project manager, and Chief Program Management Officer will ensure that all related costs are budgeted in future fiscal years.
Impact to Budget
Airport Metro Connector is funded through Measure R Transit 35%, Measure M Transit 35%, and state grant SB1. These funds are not eligible for bus or rail operations.
Implementation_Of_Strategic_Plan_Goals
IMPLEMENTATION OF STRATEGIC PLAN GOALS
This action directly supports the Project which is consistent with Metro’s Strategic Plan Goals to enhance communities and lives through mobility and access to opportunity. By increasing capacity at the station, better integrating rail service to the APM, and creating a more intuitive and efficient passenger experience, the Project seeks to better connect residents to a wider range of regional employment, travel, and cultural opportunities.
Alternatives_Considered
ALTERNATIVES CONSIDERED
The Board may choose not to approve the single source procurement method and proceed with a competitive bid. The competitive procuring of the specific rail operations, rail and bus communications and security systems equipment is not recommended since it does not provide the assurance that fully compatible equipment will be installed. This may lead to operations, safety and security conflicts with the CLAX Line, causing costly delays and costs to the Project in both the near term construction and the long term future operations of the AMC Station.
Next_Steps
NEXT STEPS
Upon Board approval, staff will procced with amending the IFB to provide for the single source procurement of systems equipment and third-party systems design.
Attachments
ATTACHMENTS
Attachment A - Description of requested equipment
Prepared_by
Prepared by:
Paul Whang, Senior Director, Engineering, Program Management, (213) 922-4705;
Tim Lindholm, Senior Executive Officer, Program Management, (213) 922 -7297
Reviewed_By
Reviewed by: Debra Avila, Chief Vendor/Contract Management Officer, (213) 418-3051;
Richard Clarke, Chief Program Management Officer, (213) 922-7557