File #: 2023-0460   
Type: Contract Status: Passed
File created: 7/13/2023 In control: Operations, Safety, and Customer Experience Committee
On agenda: 1/18/2024 Final action: 1/25/2024
Title: AUTHORIZE the Chief Executive Officer (CEO) to execute Contract Modification No. 17 to BYD Coach & Bus, LLC, to perform the procurement and installation of four (4) 360kW depot chargers at Division 9 (D9) and the installation of four (4) 450kW Opportunity chargers at the El Monte Transit Center (EMTC) at a firm fixed price of $6,470,605, including tax and delivery.
Sponsors: Board of Directors - Regular Board Meeting
Indexes: Board approved a Motion, Budgeting, Bus 40'Ze W/ Byd (Project), Bus Acquisitions, Contracts, El Monte Busway, El Monte Transit Station Enhancement, Electrification, Grant Aid, Low Carbon Transit Operations Program, Metro Busway G Line, Metro Busway J Line, Metro Divisions, Metro Rail A Line, Motion / Motion Response, Procurement, Rolling stock, Safety, Strategic planning, Testing, Zero Emission Bus (ZEB) Master Plan, Zero Emissions
Attachments: 1. Attachment A - Board Motion #50, 2. Attachment B - Procurement Summary, 3. Attachment C - Contract Modification Change Order Log, 4. Attachment D - DEOD Summary, 5. Presentation
Related files: 2024-0125

Meeting Body

OPERATIONS, SAFETY, AND CUSTOMER EXPERIENCE COMMITTEE

JANUARY 18, 2024

 

Subject

SUBJECT:                     CONTRACT MODIFICATION WITH BYD FOR DEPOT AND OPPORTUNITY CHARGER INSTALLATION

 

Action

ACTION:                     APPROVE RECOMMENDATION

 

Heading

RECOMMENDATION

 

Title

AUTHORIZE the Chief Executive Officer (CEO) to execute Contract Modification No. 17 to BYD Coach & Bus, LLC, to perform the procurement and installation of four (4) 360kW depot chargers at Division 9 (D9) and the installation of four (4) 450kW Opportunity chargers at the El Monte Transit Center (EMTC) at a firm fixed price of $6,470,605, including tax and delivery.

 

Issue

ISSUE

 

Delivery of ninety-five (95) BYD Battery Electric Buses (BEBs) is anticipated to begin in February 2024, and forty-three (43) of those BEBs will be used to support the J Line. The installation of the charging infrastructure identified in this contract modification is necessary to support the BEB operations on the J Line and other services originating from D9.

 

Background

BACKGROUND

 

At its July 2017 meeting, the Board approved Motion #50 by Directors Bonin, Garcetti, Najarian, Hahn, and Solis, and as further amended by Directors Solis, Kuehl, Barger, and Fasana, to endorse Metro’s Strategic Plan to complete the transition to zero emission electric buses by 2030, including converting the J Line to full Zero Emissions (ZE) operation as soon as feasible following the conversion of the G Line.  Full BEB service on the G Line was completed in October 2021.

 

Planning and design efforts to electrify the J Line follow a similar model employed on the G Line, a combination of division charging and en route chargers. The J Line operates out of D9 and D18 (Carson). It also serves EMTC and HGTC. The delivery of ninety-five (95) BYD BEBs is scheduled to begin in February 2024, approximately two (2) years ahead of the fulfillment of complete charging infrastructure at D9 and D18.

 

This recommended contract modification for the installation of four (4) chargers at D9 and four (4) en route chargers at EMTC is necessary to meet the daily charging requirements for the forty-three (43) BEBs for operation on the J Line.

 

Discussion

DISCUSSION

 

Consistent with Metro’s Integrated Schedule for the Zero Emission Bus Program, Metro must install a limited number of chargers before full electrification to support the transition of Metro’s BRTs to BEB.

Full electrification work at D9 and D18 is projected to be completed by the end of 2025 and 2026, respectively in support of J Line electrification. However, charging infrastructure is needed to support the charging requirements for the BYD BEBs scheduled for delivery beginning February 2024. While chargers are being installed at D9 and EMTC as part of this contract modification, work will continue separately to advance en route charging at HGTC, which is expected to be completed in late Spring 2024.

 

Metro will utilize the chargers purchased through BYD and install them as noted above to support the delivery, testing, and operation of the 95 BYD BEBs. The scope of work for this contract modification includes the following:

 

                     EMTC - installation, testing, and commissioning four (4) x 450kW chargers and associated equipment

                     D9 - procurement, installation, testing, and commissioning of four (4) x 360kW chargers

 

Staff considered the installation of mobile chargers in advance of the full division transition; however, mobile chargers do not have the fast charge capability required to support J-Line service.

 

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

There is no impact on safety. The recommendations support the successful deployment and operation of 95 new BEBs and the full electrification of the J line.

 

Financial_Impact

FINANCIAL IMPACT

 

The budget for the recommended action is included in the Life of Project (LOP) budget of Capital project 201077 - BYD 40’ Zero Emission Buses. Since this is a multi-year contract and project, the Project Manager, Cost Center Manager, and Chief Operations Officer will be responsible for budgeting costs in the future.

 

Impact to Budget

 

The combined funding for these actions include Regional Improvement Funds, and Proposition C 40.  Additionally, there are multiple grant funding sources available, including LCTOP. Staff will continue to pursue all additional grant and rebate opportunities as they become available. This will help ensure that the Bus Acquisition and Electrification Program remains funded while enacting the fleet conversion to Zero Emissions.  These funds are eligible for Bus and Rail Operations.

 

Equity_Platform

EQUITY PLATFORM

 

The J Line provides bus services to Equity Focus Communities (EFCs) from the EMTC

through Downtown Los Angeles to the HGTC and approximately 75% of the walking distance catchment area along the route is designated as EFCs. The J Line runs through the 10 and 110 Freeways along a dedicated bus lane and serves the following ridership (Fall 2019 Silver Line Rider Survey):

                     48% below $25K household income

                     68.3% had no car available

                     74% use transit 5+ days a week

                     Rider Race/ethnicity Latino 58.3%; Black 15.2; White 10.6%; Asian/Pacific Islander 9.8%; Other 6.1%

 

It is recognized that BEBs provide improved air quality and quieter services compared to the current CNG bus fleet. The Transit Vehicle Manufacturer Disadvantaged Business Enterprise (DBE) requirements from the contract remain unchanged with this contract modification.

 

Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

This recommendation supports Goal #3, Enhance communities and lives through mobility and access to opportunity; and Goal #4, Transform LA County through regional collaboration and national leadership.

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

The alternative is to receive the ninety-five (95) BYD Battery Electric Buses (BEBs) but not put them into service.  This alternative is not recommended because it will require Metro to continue running CNG buses past the end of their design life, additional bus storage space, and potentially an additional investment in maintaining overaged CNG buses. Extending vehicle life also adversely impacts fleet reliability and diminishes the quality of services provided to Metro’s passengers.

 

Next_Steps

NEXT STEPS

 

Upon Board approval, staff will execute the Contract Modification to design and proceed with the  installation of chargers for D9 and  the EMTC to support the electrification of the J Line.

 

Attachments

ATTACHMENTS

 

Attachment A - Motion #50

Attachment B - Procurement Summary

Attachment C - Contract Modification/Change Order Log

Attachment D - DEOD Summary

 

Prepared_by

Prepared by:                      Julio Rodriguez, Sr. Manager, Project Control, (213) 922-6603
Jesus Montes, Sr. Executive Officer, Vehicle Engineering and Acquisition, (213) 418-3277

Debra Avila, Deputy Chief Vendor/Contract Management Officer, (213) 418-3051

 

Reviewed_By

Reviewed by:                      Conan Cheung, Chief Operations Officer, 213-418-3034