File #: 2016-0171   
Type: Contract Status: Agenda Ready
File created: 2/18/2016 In control: System Safety, Security and Operations Committee
On agenda: 5/19/2016 Final action:
Title: AUTHORIZE the Chief Executive Officer to award contract No. PS21904205074 to Reliable Monitoring Systems (RMS), in the amount of $1,159,860, to provide a Gas Detection System (GDS) for Metro Red Line (MRL) and Metro Gold Line (MGL).
Sponsors: System Safety, Security and Operations Committee
Indexes: Budgeting, Contractors, Contracts, Maintenance, Metro Gold Line, Metro Green Line, Metro Rail B Line, Metro Red Line, Mrl Gas Analyzer Upgrade (Project), Procurement, Rail Operations Control Center, Safety, Safety and security, Security, Supervisory Control And Data Acquisition, System safety
Attachments: 1. Attachment A - Procurement Summary, 2. Attachment B - DEOD Summary

Meeting_Body

SYSTEM SAFETY, SECURITY AND OPERATIONS COMMITTEE

MAY 19, 2016

Subject/Action

SUBJECT:                     GAS DETECTION ANALYZER SYSTEM

 

ACTION:                     AWARD CONTRACT

 

Heading

RECOMMENDATION

 

Title

AUTHORIZE the Chief Executive Officer to award contract No. PS21904205074 to Reliable Monitoring Systems (RMS), in the amount of $1,159,860, to provide a Gas Detection System (GDS) for Metro Red Line (MRL) and Metro Gold Line (MGL).

 

Issue

ISSUE

 

In order to ensure the safety of our passengers and staff in the underground stations and right-of-way, a complete replacement of the Gas Detection System equipment is required. This procurement is for the parts and installation of the new system.

 

Metro rail underground stations are equipped with gas detection equipment. The gas detection devices were installed throughout the stations and cross passages. In the event that harmful gases are present, an alarm is triggered at the Rail Operations Control (ROC). Staff is immediately dispatched to assess and mitigate the issue. The current GDS devices were installed throughout the MRL in 2002 and underground MGL stations in 2003. In addition, the GDS’ main controller interface boards and peripheral equipment are obsolete, and replacement parts are difficult and expensive to obtain.

 

Discussion

DISCUSSION

 

The new GDS will replace and upgrade the current MRL and MGL equipment. This new microprocessor-based system performs functions including management of sensor modules, alarm relays, and interface with front panel display. The current equipment requires a labor-intensive system calibration every three months. 

 

New GDS equipment has an original equipment manufacturer recommendation of bi-annual calibration resulting in operating cost savings by reducing the labor cost by half. This system will improve the speed of data information communications and accuracy of incident response time. Also, the system will be connected to the Supervisory Control and Data Acquisition (SCADA) system.

 

The contractor shall provide the work covered by the proposed specifications including engineering services, which incorporates system audit and analysis. Following the award of the contract, the contractor will install the equipment within a year and a half. Installation requires replacing all sensors, control boards, power supplies, and data lines as necessary.

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

The Gas Detection System will provide additional safety features such as faster response time to incidents in the tunnel. The current response time is 5 to 10 seconds; the new response time will be improved to 2 to 5 seconds. The new system will report incident via Emergency Maintenance Panel, Fire Control Panel, Rail Operations Control, and SCADA interface module, utilizing the Remote Terminal Unit and Programmable Logic Units modules for immediate alarm recognition. A safe and reliable system is the key advantage to this new Gas Detection digital system.

 

Financial_Impact

FINANCIAL IMPACT

 

The funding of $1,159,860 is included in the Life of Project budget 205074 - Gas Analyzer Upgrade in cost center 3960.

 

Since this is a multi-year contract, the cost center manager, project managers, and Executive Director, Maintenance will ensure that the balance of funds is budgeted in future years.

 

Impact to Budget

 

The source of funding for this contract comes from Prop A 35%, which is eligible for bus and rail Operating and Capital Projects. No other funds were considered or eligible for this activity.

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

The alternative is to not award a contract for the GDS. However, based on the potential impact on Public Safety, this option is not recommended. The GDS provides a security measure to Metro Rail ridership. Metro demonstrates its commitment to putting Public Safety as a priority through the installation of this new system.

 

Next_Steps

NEXT STEPS

 

After approval of the Board, staff will execute Contract No. PS21904205074 with Reliable Monitoring Systems to provide GDS services for Metro Red Line and Gold Line.

 

Attachments

ATTACHMENTS

 

Attachment A - Procurement Summary

Attachment B - DEOD Summary

 

Prepared_by

Prepared by:                      Roger Largaespada, Wayside Systems Manager, (213) 613-2115
Chris Reyes, Transportation Planning Manager, (213) 922-4808

 

Reviewed_By

Reviewed by:                      Ivan Page, Interim Executive Director, Vendor/Contract Management, (213) 922-6383
James T. Gallagher, Chief Operations Officer, (213) 922-4424