Title: CONSIDER: A. APPROVING ?programming an additional $8,200,000 in Measure M Multi-Year Subregional Program (MSP) - I-605 Corridor "Hot Spot" Interchange Improvements Program (Expenditure Line 61), as shown in Attachment A; and B. AUTHORIZING the Chief Executive Officer (CEO) or their designee to negotiate and execute all necessary agreements and/or amendments for approved projects.?
Sponsors: Board of Directors - Regular Board Meeting
Attachments: 1. Attachment A - I-605 Corridor 'Hot Spot' Interchange Impr. Prog. Project List, 2. Presentation
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Meeting_Body

PLANNING AND PROGRAMMING COMMITTEE

OCTOBER 15, 2025

 

Subject

SUBJECT:                     MEASURE M MULTI-YEAR SUBREGIONAL PROGRAM - GATEWAY CITIES SUBREGION

 

Action

ACTION:                     APPROVE RECOMMENDATION

 

Heading

RECOMMENDATION

 

Title

CONSIDER:

 

A.                     APPROVING ​programming an additional $8,200,000 in Measure M Multi-Year Subregional Program (MSP) - I-605 Corridor “Hot Spot” Interchange Improvements Program (Expenditure Line 61), as shown in Attachment A; and

 

B.                     AUTHORIZING the Chief Executive Officer (CEO) or their designee to negotiate and execute all necessary agreements and/or amendments for approved projects.​

 

Issue

ISSUE

 

Measure M MSP, whose funds are limited to capital use, are included in the Measure M Expenditure Plan.  This update allows the Gateway Cities Subregion and implementing agencies to revise the scope of work, schedule and project budgets for previously funded I-605 Corridor “Hot Spot” Interchange Improvement (I-605) projects.  Funds are programmed through Fiscal Year (FY) 2028-29.  The Board’s approval is required to program additional funds and acknowledge the updated I-605 project list (Attachment A), which will serve as the basis for Metro entering into agreements and/or amendments with the respective implementing agencies.

 

Background

BACKGROUND

 

Based on the Measure M Expenditure Plan, a total amount of $234.66 million in Measure M MSP was forecasted to be available for programming for the I-605 projects for the Subregion from Fiscal Year (FY) 2017-18 to FY 2028-29.  In prior actions, the Board approved programming of $51.64 million in support of 12 projects.  Therefore, $183.02 million of Measure M MSP funds is available to the Subregion for programming as part of this update.  To date, $14.97 million (29% of programmed funds) has been expended.  One project is closed, and one other has been completed and is in the close-out audit process.

 

In line with the Metro Board adopted guidelines <https://www.dropbox.com/s/f4dntr4cfrby1z5/2017-MeasureM-final-guidelines.pdf?dl=0> and June 2022 Objectives for Multimodal Highway Investments <https://boardagendas.metro.net/board-report/2022-0302/> , agencies requesting funds must provide documentation demonstrating community support, project need, and multimodal transportation benefits that enhance safety, support traffic mobility, economic vitality, and enable a safer and well-maintained transportation system.  Cities and Councils of Governments lead and prioritize all proposed transportation improvements, including procurement, the environmental process, outreach, final design, and construction.

 

Discussion

DISCUSSION

 

The jurisdictional requests for updates presented herein were proposed by the cities and approved/forwarded by the subregion.  Metro staff worked closely with the Gateway Cities Council of Governments (GCCOG) and the implementing agencies to review and confirm funding eligibility of proposed projects, including changes to project scope of work/schedule and/or funding requests, as applicable.  

 

During staff review, Metro required a detailed project scope of work to confirm project eligibility and establish the program nexus including but not limited to project location and limits, length, elements, phase(s), total estimated expenses, funding requested, and schedules.  Final approval of funds for the projects shall be contingent upon the implementing agency demonstrating the eligibility of each project, as required in the Measure M Master Guidelines.  Staff collected project details to enable the timely execution of project Funding Agreements for approved projects.  All Measure M MSP funds must be expended within three years from the fiscal year in which the funds are programmed, according to the Guidelines Timely Use of Funds Lapsing Policy.  Staff will continue working with the implementing agencies and encouraging timely completion of the projects, in time for the 2028 Games.  Additionally, all projects are subject to a close-out audit after completion, according to the Guidelines.

 

I-605 Corridor “Hot Spot” Interchange Improvements (Expenditure Line 61)

 

This update includes funding adjustments to four existing projects as follows:

 

Cerritos

 

                     Program an additional $1,400,000 and reprogram previously awarded funds for MM5509.02 - Del Amo Bridge Replacement & Traffic Signal Sync Project.  The funds are programmed as follows: $400,000 in Fiscal Year (FY) 20, $790,384 in FY 22, $299,845 in FY 24 and $2,309,771 in FY 26 for a revised grant total of $3,800,000.  This  multimodal project will replace the structurally deficient bridge structure, to add an additional travel lane in each direction to match the four travel lanes at the bridge approaches, create a Class IV protected cycle track on the northern side of the bridge, add missing Class II bike lanes on surrounding local streets, provide five signal synchronized intersections with upgraded pedestrian countdown heads and leading pedestrian intervals, and incorporate roadway and pedestrian improvements including sidewalks, high visibility crosswalks, raised medians, and storm drains.  The project will likely increase Vehicle Miles Traveled (VMT).  The funds will be used for the project’s Project Approval and Environmental Document (PAED), Plans Specification and Estimates (PS&E), and Right-of-Way (ROW) phases. The Orange County Transportation Authority has provided funds for the environmental and design phases of this multi-jurisdictional project. 

 

Norwalk

 

                     Program an additional $5,000,000 for MM5509.06 - Firestone Boulevard Widening Project, Phase I.  The funds are programmed as follows: $3,284,900 in FY 23, $5,000,000 in FY 24, $5,000,000 in FY 25 and $5,000,000 in FY 26 for a revised grant total of $18,284,900.  This multimodal project will add a travel lane in each direction on Firestone Boulevard, widen the roadway bridge over UPRR freight tracks, provide a Class II bike lane on the entire project segment, construct ADA-compliant sidewalks, provide traffic signal improvements, add new street lighting, and install new retaining structures with guardrails for pedestrian safety.  The project will likely increase VMT.  The funds will be used for the project’s construction phase and expected to be completed by the 2028 Games.

 

Pico Rivera

 

                     Reprogram previously approved $3,739,267 as follows: $22,000 in FY 24, $107,217 in FY 25, $238,405 in FY 26, $43,729 in FY 27, $488,021 in FY 28, and $2,839,895 in FY 29 for MM5509.10 - Washington Boulevard Bridge Reconstruction Project.  This multimodal project will replace the structurally deficient bridge structure, provide Class II bike lanes in both directions, construct ADA-compliant sidewalks, and regrade the eastern abutment to meet hydraulic requirements.  The City of Pico Rivera is exploring design options and Caltrans approval to widen the bridge deck to accommodate both the Eastside Transit Corridor Phase II project and planned Class II bike facilities.  The project will likely decrease VMT.  The funds will be used for the project’s PAED, PS&E, and construction phases.

 

Whittier

 

                     Program an additional $1,800,000 and reprogram previously awarded funds for MM5509.07 - Beverly Boulevard at Norwalk Boulevard Realignment Project.  The funds are programmed as follows: $76,907 in FY 20, $2,023,093 in FY 26 and $1,500,000 in FY 27 for a revised grant total of $3,900,000.  This multimodal project will add a left-turn lane on Norwalk Boulevard, extend the dual left-turn pockets on Workman Mill Road, incorporate traffic signal upgrades, provide ADA-compliant curb ramps at all corners, and study the feasibility of a bus turnout on the westbound approach.  The project will likely increase VMT.  The funds will be used for the project’s PAED, PS&E, ROW and construction phases and expected to be completed by the 2028 Games.

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

Programming of Measure M MSP funds to the Gateway Cities Subregion projects will not have any adverse safety impacts on Metro’s employees or patrons.  The recommended projects support the development of a transportation system that will balance multimodal mobility options and improvements that enable people to spend less time traveling.

 

Financial_Impact

FINANCIAL IMPACT

 

In FY 2025-26, $2 million is budgeted in Cost Center 0442 (Highway Subsidies) for the I-605 Corridor “Hot Spot” Interchange Improvements Program (Project 475509).  Upon approval of this action, staff will reallocate necessary funds to appropriate projects within Cost Center 0442.  Since these are multi-year projects, Cost Center 0442 will be responsible for budgeting the cost in future years.

 

Impact to Budget

 

The sources of funds for these projects are Measure M Highway Construction 17%.  These fund sources are not eligible for Metro bus and rail operations expenses.

 

Equity_Platform

EQUITY PLATFORM

 

The Gateway Cities Subregion consists of 27 cities and unincorporated communities in Los Angeles County.  Forty-nine percent of census tracts in the subregion are defined as Equity Focus Communities (EFCs).  Cities within the subregion where most census tracts are EFCs include Bell, Bellflower, Bell Gardens, Commerce, Compton, Cudahy, Huntington Park, Lynwood, Maywood, Paramount, and South Gate.  As part of this report, additional funds are allocated to communities where less census tracts are designated as EFCs, but have the funding needs to complete the projects.  However, the projects will create safer routes for pedestrians and bicyclists with critical investments in safety, such as, improved crosswalks, curb ramps, lighting, and bicycle facilities, providing regional benefits for all vulnerable roadway users.

 

Metro staff provide technical assistance to jurisdictions, assisting agencies in determining funding eligibility and developing funding agreements, including project scope of work, cost and schedule.  Each city and/or agency, independently and in coordination with the subregion, undertakes their jurisdictionally determined community engagement process specific to the type of transportation improvement they seek to develop.  These locally determined and prioritized projects represent the needs of cities and the subregion.

 

Vehicle_Miles_Traveled_Outcome

VEHICLE MILES TRAVELED OUTCOME

 

VMT and VMT per capita in Los Angeles County are lower than national averages, the lowest in the SCAG region, and on the lower end of VMT per capita statewide, with these declining VMT trends due in part to Metro’s significant investment in rail and bus transit.*  Metro’s Board-adopted VMT reduction targets align with California’s statewide climate goals, including achieving carbon neutrality by 2045. To ensure continued progress, all Board items are assessed for their potential impact on VMT.

 

While the agency remains committed to reducing VMT through transit and multimodal investments, some projects may induce or increase personal vehicle travel. However, these individual projects aim to ensure the efficient and safe movement of people and goods. Each project’s VMT outcome is included in the brief project description earlier in this report. This Board item, which looks at a number of smaller investments across modes, will likely increase VMT in LA County, as it includes several project elements that encourage driving alone.  However, there are project elements related to safety, active transportation, improved ADA compliance and transit accommodation.

 

Although this item may not directly contribute to the achievement of the Board-adopted VMT Reduction Targets, the VMT Targets were developed to account for the cumulative effect of a suite of programs and projects within the Metro region, which individually may induce or increase VMT. Additionally, Metro has a voter-approved mandate to deliver multimodal projects that enhance mobility while ensuring the efficient and safe movement of people and goods.

 

*Based on population estimates from the United States Census and VMT estimates from Caltrans’ Highway Performance Monitoring System (HPMS) data between 2001-2019.

 

Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

Recommendation supports the following goals of the Metro Vision 2028 Strategic Plan: 

 

Goal 1: Provide high-quality mobility options that enable people to spend less time traveling by alleviating the current operational deficiencies and improving mobility along the projects.

 

Goal 4: Transform LA County through regional collaboration by partnering with the Council of Governments and the local jurisdictions to identify the needed improvements and take the lead in development and implementation of their projects.

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

The Board could elect not to approve the additional programming of funds for the Measure M MSP projects for the Gateway Cities Subregion.  This is not recommended as the Gateway Cities Subregion developed the proposed projects are in accordance with the Measure M Ordinance, Guidelines and Administrative Procedures.

 

Next_Steps

NEXT STEPS

 

Metro staff will continue to work with the subregion to identify and deliver projects. Funding Agreements and Amendments will be executed with those who programmed and or reprogrammed funds.  Program/Project updates will be provided to the Board annually.

 

Attachment

ATTACHMENT

 

Attachment A - I-605 Corridor “Hot Spot” Interchange Improvements Program Project List

 

Prepared_by

Prepared by:                     Fanny Pan, Executive Officer, Countywide Planning & Development, (213) 418-3433

                     Andres Roa, Transportation Planner, Countywide Planning & Development, (213) 348-4797

                     Laurie Lombardi, Senior Executive Officer, Countywide Planning & Development, (213) 418-3251

                     Nicole Ferrara, Deputy Chief Planning Officer, (213) 547-4322

 

Reviewed_By

Reviewed by: Ray Sosa, Chief Planning Officer, (213) 922-2920