Legislation Details

File #: 2026-0702   
Type: Contract Status: Agenda Ready
File created: 9/18/2026 In control: Operations, Safety, and Customer Experience Committee
On agenda: 11/19/2026 Final action:
Title: AUTHORIZE the Chief Executive Officer to: AWARD a three-year firm fixed price contract, Contract No. OP138405000 to Balfour Beatty Infrastructure, Inc., the lowest responsive and responsible bidder for the Metro C/K Line Mainline Fastener Replacement Project in the amount of $13,683,652, subject to the resolution of any properly submitted protest(s), if any; and INCREASE the Life of Project Budget (LOP) for Project 205695 - Metro C/K Line Mainline Fastener Replacement by $4,065,494, increasing the LOP from $17,100,000 to $21,165,494.
Sponsors: Board of Directors - Regular Board Meeting
Attachments: 1. Attachment A - Procurement Summary, 2. Attachment B - DEOD Summary, 3. Attachment C - Capital Project 205695 Expenditure Plan, 4. Presentation
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Meeting_Body

OPERATIONS, SAFETY, AND CUSTOMER EXPERIENCE COMMITTEE

NOVEMBER 19, 2026

 

Subject

SUBJECT:                     METRO C/K LINE MAINLINE FASTENER REPLACEMENT PROJECT

 

Action

ACTION:                     AWARD CONTRACT

 

Heading

RECOMMENDATION

 

Title

AUTHORIZE the Chief Executive Officer to:

 

A.                     AWARD a three-year firm fixed price contract, Contract No. OP138405000 to Balfour Beatty Infrastructure, Inc., the lowest responsive and responsible bidder for the Metro C/K Line Mainline Fastener Replacement Project in the amount of $13,683,652, subject to the resolution of any properly submitted protest(s), if any; and

 

B.                     INCREASE the Life of Project Budget (LOP) for Project 205695 - Metro C/K Line Mainline Fastener Replacement by $4,065,494, increasing the LOP from $17,100,000 to $21,165,494.

 

Issue

ISSUE

 

The Metro C Line and the southern segment of the Metro K Line make up a 19.3-mile double-track light rail line operating between Redondo Beach and Norwalk. The existing Type 1 direct fixation (DF) rail fasteners on these segments have been in active light rail service for over 30 years and are reaching the end of their useful life and require replacement to maintain rail operations.

 

Background

BACKGROUND

 

The Metro C/K Line Mainline Fastener Replacement Project is a Capital Improvement Project aimed at replacing the original Type 1 direct fixation (DF) rail fasteners across the Metro C Line and the southern segment of the K Line which are approaching the end of their useful life. DF rail fasteners are specialty track equipment, engineered to secure the track running rail to the track support structure such as a concrete track bed in direct fixation track, maintaining track alignment, reducing vibration and providing electrical isolation between the rail and the supporting structure.

 

The original Type 1 rail fasteners, manufactured by LORD Corp., were installed during the original construction of the C Line and have been in use since revenue service started in 1995. The original fasteners were designed with a life expectancy of 25 to 30 years. The continuous rail service in the predominantly elevated and at-grade coastal environment has led to some fasteners experiencing wear and cracking over time. The Track Maintenance Department inspects the fasteners regularly and replaces the failed fasteners when needed. However, this maintenance work has caused rail service to be impacted as trains are required to be single-tracked for replacement, or train speeds are required to be significantly reduced while repairs are made. Metro staff completed an examination of the condition of the mainline fasteners and determined that an entire replacement of C Line and southern segment of the K Line mainlines should be performed using dedicated resources within a specific timeframe.

 

Discussion

DISCUSSION

 

The scope of work involves removing 53,530 original Type 1 fasteners and replacing them with new and enhanced Type 1 fasteners engineered with an extended life expectancy of 30 to 35 years. These enhanced Type 1 fasteners feature advanced durability specialized for the predominantly elevated and at-grade coastal environments of the South Bay and Interstate 105 corridors. As a State of Good Repair (SGR) project, these critical infrastructure assets require scheduled replacement to uphold systemic safety. The capital project is scheduled to be completed within approximately three years. Executing this asset replacement will significantly increase the mainline reliability across the C Line and southern segment of the K Line while mitigating service disruptions caused by premature rail fastener fatigue or failure.

 

Based on the necessary project scope for Contract No. OP138405000, staff has determined a total LOP need of $21,165,494. To proceed with the contract award and fully support this critical project scope, an LOP budget increase of $4,065,494 is required.

 

The increase in the LOP is mainly attributed to increased labor costs to replace fasteners to complete this work per the schedule, engineering design and project management support necessary to oversee design submittals and ensure timely project completion of this effort, and contingency related to unforeseen price increases for critical materials required to produce the rail fasteners along with change orders that may be required during the construction phase of this work. Please refer to Attachment C for the cost breakdown of capital project 205695.

 

This project is part of Metro’s commitment to delivering a robust SGR program that invests in modernization, enhancement to renew asset life and reduce asset breakdowns that impact daily service and customer experience.

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

Rail fasteners directly impact the safety of train movements as they keep the rail fixed to the appropriate track gauge and prevent the rails from shifting. A train derailment can occur if fasteners do not hold the rail at the appropriate gauge and cause the rail to shift.

 

In accordance with Metro’s SGR requirements, fasteners that are nearing the end of their useful life must be replaced in a timely manner to comply with safety and reliability standards, alongside meeting Federal Transit Administration and California Public Utilities Commission regulations.

 

Financial_Impact

FINANCIAL IMPACT

 

The budget is contained in Capital Project 205695 - Metro C/K Line Mainline Fastener Replacement. This action increases the Life of Project (LOP) budget by $4,065,494 to $21,165,494. The adopted FY27 budget includes annual funding of $1,540,373 for this project.

 

Since this is a multi-year project, the Project Manager will ensure that the balance of the funds is budgeted in future fiscal years.

 

Impact to Budget

 

The current source of funds for this action are local funds, which are eligible for rail operations and Capital Projects.

 

Equity_Platform

EQUITY PLATFORM

 

The benefits of this action are to ensure that transit infrastructure assets are maintained in a state of good repair countywide, including assets that provide transit service for disadvantaged communities. The C Line and the southern K Line rail fasteners are located across Los Angeles County transit corridors, including within Equity Focus Communities (EFCs) in Norwalk, Downey, Paramount, Lynwood, Rancho Dominguez, Willowbrook, Athens, Westmont, Lennox, Hawthorne, Lawndale, Redondo Beach, and Torrance. The primary users of these lines originate from very low-income households and lack access to personal vehicles. These corridors also serve as vital transfer points to multiple bus and rail lines, supporting the mobility of workers, students, and residents. Replacing the rail fasteners will enhance transportation reliability and efficiency, directly benefiting these riders.

 

The Diversity & Economic Opportunity Department (DEOD) recommended a 2% Small Business Enterprise (SBE) goal for this procurement. The solicitation was also subject to Metro’s Local Small Business Enterprise (LSBE) program.  The recommended firm, Balfour Beatty Infrastructure, Inc. exceeded the goal by making a 17.82% SBE commitment.


Vehicle_Miles_Traveled_Outcome

VEHICLE MILES TRAVELED OUTCOME

 

VMT and VMT per capita in Los Angeles County are lower than national averages, the lowest in the SCAG region, and on the lower end of VMT per capita statewide, with these declining VMT trends due in part to Metro’s significant investment in rail and bus transit.* Metro’s Board-adopted VMT reduction targets align with California’s statewide climate goals, including achieving carbon neutrality by 2045. To ensure continued progress, all Board items are assessed for their potential impact on VMT.

 

As part of these ongoing efforts, this item is expected to contribute to further reductions in VMT. This item supports Metro’s strategy to prevent VMT increases through critical SGR capital improvement investments to replace the original Type 1 rail fasteners along the C Line and the southern segment of the K Line mainlines. These capital improvement investments preserve efficient, safe, and dependable rail infrastructure, which further encourages transit ridership, ridesharing, and active transportation. Metro’s Board-adopted VMT reduction targets were designed to build on the success of existing investments, and this item aligns with those objectives.

 

*Based on population estimates from the United States Census and VMT estimates from Caltrans’ Highway Performance Monitoring System (HPMS) data between 2001-2019.

 

Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

Approval of this recommendation supports the following Metro Strategic Plan Goals:

 

Goal # 1 Provide high-quality mobility options that enable people to spend less time traveling.

 

Goal # 2 Deliver outstanding trip experiences for all users of the transportation system.

 

Goal # 3 Enhance communities and lives through mobility and access to opportunity.

 

This project helps maintain system service, reliability and safety standards to provide a world-class transportation system that enhances the quality of life for all who live, work, and play within Los Angeles County.

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

The Board may choose not to award Contract No. OP138405000; however, staff does not recommend this option. Without proceeding with the SGR work to replace the track fasteners, fastener failures may result in service delays until repairs are completed.

 

Postponing or foregoing these replacements is not recommended because track fasteners are safety-sensitive rail infrastructure components that are essential to maintaining service reliability, passenger safety, and ride quality. In addition, performing unscheduled repairs on individual fasteners would result in higher operating costs and longer repair times compared with completing the replacements as scheduled.

 

Next_Steps

NEXT STEPS

 

Upon Board approval, staff will execute Contract No. OP138405000.

 

Attachments

ATTACHMENTS

 

Attachment A - Procurement Summary

Attachment B - DEOD Summary

Attachment C - Capital Project 205695 Expenditure Plan

 

Prepared_by

Prepared by:                      A. Rice, Senior Director, Project Control

D. Amores, Deputy Executive Officer, Project Management

K. Zan, Executive Officer, Projects Engineering

E. Taylor, Deputy Chief Operations Officer, Infrastructure Maintenance and Engineering

D. Avila, Deputy Chief Vendor/Contract Management Officer

 

Reviewed_By

Reviewed by:                      M. Antonelli, Chief Vendor/Contract Management Officer

C. Cheung, Chief Operations Officer