Subject
SUBJECT: DIVISION 11 AND 22 HVAC AND ROOF REPLACEMENT
Action
ACTION: APPROVE CONTRACT MODIFICATION
Heading
RECOMMENDATION
Title
AUTHORIZE the Chief Executive Officer to execute Contract Modification No. 3 to Contract No. C56872C1142 with Archico Design Build Inc. to provide Heating, Ventilation and Air Conditioning (HVAC) replacement and additional roofing replacement and increase the contract price by $1,820,450.00 from $6,570,294.00 to $8,390,744.00.
Issue
ISSUE
Archico Design Build Inc. is contracted to provide roof replacement at Metro Operating Divisions 11 and 22. During the project, a need for the replacement of the HVAC equipment at these locations was identified. Due to Archico Design Build Inc. removing the existing HVAC equipment as part of the scope of work for the roof replacement, it has been identified that replacement equipment can be added as part of the new scope of work. Maintenance of Way Engineering seeks board approval to modify the current contract.
Background
BACKGROUND
In May 2019, Metro awarded Contract No. C56872C1142 to Archico Design Build Inc. to perform a complete design, roofing system tear off and replacement at the Division 11 Ancillary Shop and Vehicle Shop Buildings and the Division 22 Maintenance Shop Building.
In January 2020, the HVAC equipment at Divisions 11 and 22 were identified to be at their end-of-Life, beyond repair, having significant environmental risks and leaking significant amounts of non-compliant refrigerants when the units fail, a violation that can result in fines. Due to Archico Design Build Inc. removing the existing HVAC equipment as part of the roof replacement scope, it has been determined that Archico Design Build Inc. could replace the equipment with new energy efficient equipment.
Discussion
DISCUSSION
Under this contract, Archico Design Build Inc. provides design, construction and project management services. The design includes heat load analysis, structural and seismic analysis, sustainability assessment, and system controls and integration. The construction includes the acquisition of the replacement HVAC equipment, installation, and necessary refurbishment, electrical and commissioning services.
Determination_Of_Safety_Impact
DETERMINATION OF SAFETY IMPACT
The approval of this item will ensure providing safe work environment for staff.
Financial_Impact
FINANCIAL IMPACT
Funding for the HVAC replacement contract modification is in the Board approved Life of Project (LOP) budget for Capital Project 204801 - Rail Facilities HVAC/Light Retrofit in the amount $4,205,100.
Impact to Budget
The funding source for the HVAC replacement at the two rail divisions will be a mix of eligible and available local funds such as Proposition A 35%, Green Fund, or other funds appropriate for state of good repair given approved funding provisions and guidelines.
Implementation_of_Strategic_Plan_Goals
IMPLEMENTATION OF STRATEGIC PLAN GOALS
This board action supports Strategic Goal 5; Provide responsive, accountable, and trustworthy governance within the Metro organization.
Alternatives_Considered
ALTERNATIVES CONSIDERED
The Board may decline to approve the contract modification. This alternative is not recommended as it will result in End-of-Life HVAC equipment being put back in service during the summer months while continuing to have significant environmental risks.
Next_Steps
NEXT STEPS
Upon Board approval, staff will execute Modification No. 3 to Contract No. C56872C1142 with Archico Design Build Inc. to begin construction to replace the HVAC equipment at Divisions 11 and 22.
Attachments
ATTACHMENTS
Attachment A - Procurement Summary
Attachment B - Contract Modification/Change Order Log
Attachment C - DEOD Summary
Prepared_by
Prepared by: Emmanuel Liban, Chief Sustainability Officer, Transit Project Delivery, (213)922-2471
Errol Taylor, Senior Executive Officer, Maintenance and Engineering, (213) 922-3227
Marshall Epler, DEO, Systems Engineering, (213) 617-6232
Reviewed_By
Reviewed by: James T. Gallagher, Chief Operations Officer, (213) 418-3108