File #: 2015-1107   
Type: Informational Report Status: Filed
File created: 7/16/2015 In control: Planning and Programming Committee
On agenda: 9/16/2015 Final action: 9/16/2015
Title: RECEIVE AND FILE Metro Countywide Bikeshare Program update.
Sponsors: Planning and Development (Department)
Indexes: Arroyo Verdugo subregion, Beverly Hills, Bicycling, Board approved a Motion, Central Los Angeles subregion, City of Los Angeles, Culver City, Downtown Los Angeles, Fare Structure, Gateway Cities (Southeast LA County) Service Sector, Gateway Cities subregion, Huntington Park, Informational Report, Long Beach, Metro Bike Share, Motion / Motion Response, Pasadena, Program, Request For Proposal, San Fernando Valley subregion, Santa Monica, South Bay Cities subregion, Venice, West Hollywood, Westside Cities subregion, Westside/Central Service Sector
Attachments: 1. Attachment A - Motion 22.1, 2. Attachment B - Metro Bikeshare Design
Meeting_Body
PLANNING AND PROGRAMMING COMITTEE
SEPTEMBER 16, 2015

Subject/Action
SUBJECT: METRO COUNTYWIDE BIKESHARE PROGRAM

ACTION: RECEIVE AND FILE UPDATE

Heading
RECOMMENDATION

Title
RECEIVE AND FILE Metro Countywide Bikeshare Program update.

Discussion
DISCUSSION

At the June 2015 meeting, the Board awarded a two-year contract to Bicycle Transit Systems (BTS) for the equipment, installation and operations of the Metro Countywide Bikeshare Phase 1 Pilot in downtown Los Angeles (DTLA Pilot). At the July 23, 2015 meeting, the Board approved Motion 22.1 (attachment A) providing staff with direction on next steps for implementing the Countywide Bikeshare Program. Included within Motion 22.1 was direction on addressing interoperability, working towards an accelerated schedule, conducting feasibility and station siting for other communities.

On a parallel track, staff has been working with the City of Los Angeles in preparing for the launch of the Pilot, meeting with cities on a one-on-one basis, and carrying out work that will facilitate interoperability as well as work that will accelerate Metro's program. Staff has scheduled two meetings for September. One meeting is exclusively with cities that have opted to launch a Sobi/CycleHop system. The second meeting is exclusively with cities that have opted to join Metro's Countywide Bikeshare Program.

Below is a more detailed update on work carried out to date.

Downtown Los Angeles Update

The following is a brief overview of work that has been carried out since award of contract as it relates to the DTLA Pilot:
* Staff has held a number of bikeshare demonstration outreach efforts aimed at making the downtown community aware of what bikeshare is and that a network will be established in downtown. Demonstration events held include participating at the Arts District Farmers Market, Lunch A La Park in Grand Park and the CicLAvia Culver City Meets Venice. Additional demonstr...

Click here for full text