File #: 2025-0506   
Type: Contract Status: Agenda Ready
File created: 6/3/2025 In control: Operations, Safety, and Customer Experience Committee
On agenda: 7/17/2025 Final action:
Title: AUTHORIZE the Chief Executive Officer to: A. EXECUTE Contract Modification No. 31 to Contract No PS20113000, a cost plus fixed-fee contract with CH2M Hill, Inc. for the P2000 Light Rail Vehicle (LRV) Overhaul Program Consultant Support Services, increasing the Not-To-Exceed (NTE) contract price by $1,448,394.00 from $9,563,696.20 to $11,012,090.20, and extending the period of performance from December 31, 2025, to June 30, 2026; and B. EXECUTE individual contract modifications within the Board-approved contract modification authority.
Sponsors: Board of Directors - Regular Board Meeting
Indexes: Board approved Contract, Budgeting, Contracts, Cost-plus Contract, Light rail vehicles, Perform Mid Life Overhaul Of Siemens P2000 Lrv (Project), Procurement, Professional Services, Program, Program Management, Project, Project management, Revenue Service, Testing, Warranty, Witnesses
Attachments: 1. Attachment A - Procurement Summary, 2. Attachment B - Contract Modification Log, 3. Attachment C - DEOD Summary, 4. Presentation
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.
Meeting_Body
OPERATIONS, SAFETY, AND CUSTOMER EXPERIENCE COMMITTEE
JULY 17, 2025

Subject
SUBJECT: P2000 LIGHT RAIL VEHICLE (LRV) OVERHAUL PROGRAM CONSULTANT SUPPORT SERVICES

Action
ACTION: APPROVE RECOMMENDATION

Heading
RECOMMENDATION

Title
AUTHORIZE the Chief Executive Officer to:

A. EXECUTE Contract Modification No. 31 to Contract No PS20113000, a cost plus fixed-fee contract with CH2M Hill, Inc. for the P2000 Light Rail Vehicle (LRV) Overhaul Program Consultant Support Services, increasing the Not-To-Exceed (NTE) contract price by $1,448,394.00 from $9,563,696.20 to $11,012,090.20, and extending the period of performance from December 31, 2025, to June 30, 2026; and

B. EXECUTE individual contract modifications within the Board-approved contract modification authority.

Issue
ISSUE

This Contract provides the agency with program and technical consultant support for the P2000 LRV Modernization Contract that is set to expire on December 31, 2025. Due to the newly identified obsolete components, unforeseen technical issues and systems impacting performance and the global pandemic recovery, which continue to impact the supply chain, availability of resources, inspections, and test activities, the project schedule continues to be affected with the Final Acceptance of all existing P2000 LRVs (52 LRVs total) deferred to June 2026.

Background
BACKGROUND

The P2000 LRV Midlife Modernization Project permits Metro to maintain the P2000 LRV fleet in a State of Good Repair (SGR). At its March 2017 meeting, the Board approved Contract No. PS20113000, a cost plus, fixed fee contract to CH2M Hill, Inc., in the amount of $5,829,626 (base contract) for technical and program management services in support of the P2000 LRV Modernization Project. The base contract duration was five years. A no-cost contract modification was issued in February 2022, extending the base contract from March 2022 through September 2022.

At its September 2022 meeting, the Board approve...

Click here for full text