CONSTRUCTION COMMITTEE
JULY 18, 2019
Subject
SUBJECT: AIRPORT METRO CONNECTOR
Action
ACTION: APPROVE RECOMMENDATIONS
Heading
RECOMMENDATION
Title
AUTHORIZE:
A. The Chief Executive Officer to execute a 5-year cost-plus fixed fee Contract No. PS58330MC075 with KDG+DE Construction Support Services to provide Construction Support Services for the Airport Metro Connector (AMC) 96th Street Transit Station Project, in an amount not-to-exceed $25,943,154.86 and exercise 2 one-year options, when deemed appropriate; and
B. Contract Modification Authority in the amount of $5,188,630.97 or 20% of the not-to-exceed contract award value and authorize the CEO to execute individual Contract Modifications within the Board approved Contract Modification Authority.
Issue
ISSUE
A Construction Support Services Consultant (CSSC) is required to assist Metro Project staff in management oversight for construction of the AMC 96th Street Transit Station Project. Services will be provided from final design through pre-construction activities, construction, and contract close out.
The recommended Board action will provide funding through FY24 when construction of the Project must be complete in order to open for public service on the same schedule with Los Angeles World Airport's (LAWA) Automated People Mover.
Background
BACKGROUND
On July 15, 2015, the Metro Board of Directors approved the award of a design contract for the AMC 96th Street Transit Station Project. This new Metro station that will be owned and operated by Metro is planned to connect with LAWA's future Automated People Mover (APM) system and the Crenshaw/LAX and Green line light rail systems. The APM will provide direct service to and from the AMC station and the terminal area at Los Angeles International Airport (LAX). The design for the AMC 96th Street Transit Station requires extensive coordination with LAWA during the environmental review, design and construction phases with particular ...