Type:
|
Oral Report / Presentation
|
Status:
|
Agenda Ready
|
On agenda:
|
1/15/2025
|
Final action:
|
|
Title:
|
RECEIVE AND FILE the Program Management Project Status Report.
|
Indexes:
|
7th Street/Metro Center Station, Access Services Inc., Access-To-Jobs, Advertising, Airport Metro Connector (AMC) Station Project, Alignment, Alignment 1104, Allen Station, Arroyo Verdugo subregion, Artesia, Arts District, Azusa, Barriers (Roads), Bell, Bellflower, Beverly Hills, Bids, Bikeways, Board approved Contract, Budgeting, Burbank, Bus rapid transit, Business Interruption Fund, Business Solution Center, California Transportation Commission, Capital Project, Castaic, Century City, Century City/Constellation Station, Cerritos, City of Los Angeles, Civic Center/Grand Park Station, Claremont, Commerce, Construction, Construction management, Construction safety, Contractors, Crossovers, Cudahy, Del Mar Station, Design build, Disadvantaged business enterprises, Division 20, Downey, Downtown Los Angeles, Eagle Rock, East San Fernando Valley Light Rail Project, East San Fernando Valley Transit Corridor, El Segundo, Elevators, Environmental Impact Report, Equity Focus Communities, Escalators, Express lanes, Federal Transit Administration, Fillmore Station, Florence, Foothill Gold Line Construction Authority, Full Funding Grant Agreement, Gateway Cities (Southeast LA County) Service Sector, Gateway Cities subregion, Glendale, Glendora, Gold Line Foothill Extension 2A, Gold Line Foothill Extension 2B, Grade separations, Hawthorne, High occupancy vehicle lanes, Housing, Hubs, Huntington Park, I-10, I-105, I-105 ExpressLanes Project, I-5, Inglewood, Intersections, Koreatown, L.A. Live, La Verne, Lake Avenue Station, Landscaping, Light rail transit, Light rail vehicles, Link Union Station, Little Tokyo/Arts District Station, Los Angeles County Museum of Art, Los Angeles International Airport, Lynwood, Maintenance, Maintenance of way, Maps, Memorial Park Station, Metro Busway G Line, Metro Divisions, Metro Equity Platform, Metro ExpressLanes, Metro Rail A Line, Metro Rail B Line, Metro Rail C Line, Metro Rail D Line, Metro Rail E Line, Metro Rail K Line, Metro Vision 2028 Plan, Minorities, Miracle Mile, Mitigation, North Hollywood, North San Fernando Valley Transit Corridor, Norwalk, Oral Report / Presentation, Orange Line Bus Rapid Transit Improvements, Outreach, Pacoima, Paramount, Partnerships, Pasadena, Payment, Pershing Square Station, Pomona, Port of Long Beach, Port of Los Angeles, Procurement, Program Management, Progressive Design/Build, Project, Project delivery, Project management, Project Status Report, Property acquisition, Public relations, Race and ethnicity, Regional Connector Transit Corridor Project, Safety, Safety and security, San Dimas, San Fernando, San Fernando Valley Service Sector, San Fernando Valley subregion, San Gabriel, San Pedro, Sierra Madre Villa Station, Small Business Enterprise, South Gate, Southern California Highways, Start of first construction, Station 0602, Station 0608, Storage facilities, Supervisory Control And Data Acquisition, Terminal 220, Test trains, Testing, Tolls, Traffic signals, Transit centers, Translations, Travel time, Truck lanes, Trucking, Twenty-eight by '28 Initiative, Van Nuys, Variance, Vernon, Walking, Westlake/Macarthur Park Station, Westside Cities subregion, Westside Subway Extension/Purple Line Extension Phase 1, Westside Subway Extension/Purple Line Extension Phase 2, Westside Subway Extension/Purple Line Extension Phase 3, Westside/Central Service Sector, Westwood/UCLA Station, Westwood/VA Hospital Station, Wilshire/Fairfax Station, Wilshire/La Brea Station, Wilshire/La Cienega Station, Wilshire/Rodeo Station, Wilshire/Vermont Station
|
CONSTRUCTION COMMITTEE JANUARY 15, 2025 Subject SUBJECT: PROGRAM MANAGEMENT PROJECT STATUS Action ACTION: RECEIVE AND FILE Heading RECOMMENDATION Title RECEIVE AND FILE the Program Management Project Status Report. Issue ISSUE Program Management's capital project status report provides significant highlights regarding several capital projects nearing or under construction. Background BACKGROUND Metro's mission is to provide a world-class transportation system that enhances the quality of life for all who live, work, and play within LA County. Program Management oversees the construction of capital projects. The attached project status report provides significant information about the progress of 12 major capital projects. Discussion DISCUSSION The project status report includes a summary of 12 major projects including cost and schedule performance, small business project participation status, safety, risk, and equity (Westside Purple Line Sections 1, 2, and 3, Division 20 Portal Widening Turnback, Gold Line Foothill Ext. Phase 2B, Airport Metro Connector, I-5 North County Enhancements, East San Fernando Valley Transit Corridor, North Hollywood to Pasadena BRT Project, G Line BRT Improvements, I-105 Express Lanes Projects, and Southeast Gateway Line). The report highlights construction activities, and safety data is based on the latest available information, consistent with reporting timelines. Equity_Platform EQUITY PLATFORM The following table summarizes Equity Focus Communities (EFC) percentage data for the individual projects covered in this report. Please see the refreshed equity section baseline in Attachment A for additional information. Implementation_of_Strategic_Plan_Goals IMPLEMENTATION OF STRATEGIC PLAN GOALS Strategic plan goal # 1, Metro will expand transportation options, improve the quality of its transit network and assets, and take steps to manage demands on the entire network. SAFETY The average national sa... Click here for full text
|