Title: AUTHORIZE the Chief Executive Officer to execute Contract Modification No. 12 to Contract No. PS73193000-P2550, a cost plus fixed-fee contract with Hatch Associates Consultants, Inc. (formerly LTK Consultant Services, Inc.) to provide consultant support services for the P2550 Light Rail Vehicle Modernization Project, increasing the Not-To-Exceed (NTE) contract price by $4,796,082, from $7,038,584 to $11,834,666, and extend the period of performance from October 31, 2026 through December 31, 2031.
Sponsors: Board of Directors - Regular Board Meeting
Indexes: Budgeting, Contracts, Research, Safety
Attachments: 1. Attachment A - Procurement Summary, 2. Attachment B - Contract Modification and Change Order Log, 3. Attachment C - DEOD Summary, 4. Presentation
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.
Meeting_Body
OPERATIONS, SAFETY, AND CUSTOMER EXPERIENCE COMMITTEE
OCTOBER 15, 2026

Subject
SUBJECT: P2550 LIGHT RAIL VEHICLE (LRV) MIDLIFE MODERNIZATION CONSULTANT SUPPORT SERVICES

Action
ACTION: APPROVE RECOMMENDATION

Heading
RECOMMENDATION

Title
AUTHORIZE the Chief Executive Officer to execute Contract Modification No. 12 to Contract No. PS73193000-P2550, a cost plus fixed-fee contract with Hatch Associates Consultants, Inc. (formerly LTK Consultant Services, Inc.) to provide consultant support services for the P2550 Light Rail Vehicle Modernization Project, increasing the Not-To-Exceed (NTE) contract price by $4,796,082, from $7,038,584 to $11,834,666, and extend the period of performance from October 31, 2026 through December 31, 2031.

Issue
ISSUE

This Contract provides program and technical consulting support for the P2550 LRV Modernization Contract. Continued technical support is necessary to oversee the remaining thirty-three (33) vehicle acceptances and manage warranty requirements. With the final LRV projected for conditional acceptance in 2028 and a subsequent three-year warranty period, consultant support is needed through December 31, 2031.

Background
BACKGROUND

In March 2021, the Board approved Contract No. PS73193000-P2550, a cost-plus fixed-fee contract to Hatch Associates Consultants, Inc. (formerly LTK Consultant Services, Inc.) in the amount of $6,470,848.47 for technical and program management services in support of the P2550 LRV Midlife Modernization Project. The base contract duration was five years.

Hatch Associates Consultants, Inc. currently provides staff support in the following disciplines, as directed by Metro:

Project Management
Systems Engineering
Systems Integration
Inspection & Testing Activities at LRV Production/Modernization Site
LRV Commissioning and Acceptance Activities
Quality Assurance
Document Control

All work and assignments are issued as needed and directed by the Metro P2550 Project Team through ...