PLANNING AND PROGRAMMING COMMITTEE
NOVEMBER 18, 2026
Subject
SUBJECT: MEASURE M MULTI-YEAR SUBREGIONAL PROGRAM ANNUAL UPDATE - GATEWAY CITIES SUBREGION
Action
ACTION: APPROVE RECOMMENDATION
Heading
RECOMMENDATION
Title
CONSIDER:
A. APPROVING programming an additional $222,633,182 in Measure M Multi-Year Subregional Program (MSP) – I-605 Corridor “Hot Spot” Interchange Improvements Program (Expenditure Line 61), as shown in Attachment A; and
B. AUTHORIZING the Chief Executive Officer (CEO) or their designee to negotiate and execute all necessary agreements and/or amendments for approved projects.
Issue
ISSUE
Measure M MSPs are included in the Measure M Expenditure Plan, which is an attachment to the Measure M Ordinance. All MSP funds are limited to capital projects. This update allows the Gateway Cities Subregion and implementing agencies to approve new eligible projects for funding, and revise the project scope of work, project budget, and schedule for previously funded projects. Funds are programmed through Fiscal Year (FY) 2029-30. The Board’s approval is required to program additional funds and to acknowledge the updated project list (Attachment A), which serves as the basis for Metro entering into agreements and/or amendments with the respective implementing agencies.
Background
BACKGROUND
Based on the Measure M Expenditure Plan, a total of $284.26 million was forecast to be available for programming for the Gateway Cities Subregion (Subregion) for FY 2017-18 to FY 2029-30. In prior actions, the Board approved programming $59.84 million in support of 12 local multimodal projects. Therefore, $224.42 million is available to the Subregion for programming under this update. To date, $39.55 million (66% of programmed funds) has been expended. Two projects have been closed out and audited, and three others are complete and being closed out. Staff will continue working with the implementing agencies to advance the delivery of all ...