ISSUE
At the May 27, 2021, regular Board meeting, Motion 47 (Solis, Sandoval, Butts, and Garcetti) on the I-710 (South) corridor improvements environmental process was approved (Attachment A). The Motion requested a report back at the September Board meeting.
Background
BACKGROUND
Draft EIR/EIS Development
The environmental studies for the I-710 corridor improvements started in 2008 to address significant traffic congestion, safety, and air quality issues resulting from increasing traffic volumes and infrastructure deficiencies. Metro, in partnership with Caltrans, Gateway Cities Council of Governments (GCCOG), Port of Los Angeles, Port of Long Beach, Southern California Association of Governments, and the I-5 Joint Powers Authority (collectively, the Funding Partners), completed scoping, alternatives analysis and other technical work in early 2011, leading to the preparation of the draft environmental document (DED) and preliminary engineering. The development of the potential improvement alternatives was guided by the stated purpose statement approved by all study Partners and regulatory and resources agencies:
? Improve air quality and public health
? Improve traffic safety
? Address design deficiencies
? Address projected traffic volume
? Address projected growth in population, employment, and economic activity related to goods movement
The development of the DED was guided by a public outreach framework.
The DED circulated on June 28, 2012, evaluated four build alternatives, three of which, in addition to improvements to the mainline freeway, included a grade-separated freight corridor. Close to 3,000 comments were received...