Meeting_Body
CONSTRUCTION COMMITTEE
MAY 21, 2020
Subject
SUBJECT: CRENSHAW/LAX CLOSE OUT PROJECT
Action
ACTION: APPROVE RECOMMENDATION
Heading
RECOMMENDATION
Title
CONSIDER adopting the Life-of-Project (LOP) budget of $30,000,000 for a new Crenshaw/LAX Close Out Project.
Issue
ISSUE
The Crenshaw/LAX project is 95% complete. As the project reaches completion, Metro requires a close out project to provide funding for work anticipated to commence after substantial completion of the Crenshaw Project has been achieved. The funding is separate from the Crenshaw/LAX Construction Project which allows Metro flexibility to close out the Construction Project and related administrative elements in a timely manner. The scope of the new Project will include additional work required that due to timing constraints, is not recommended to be issued to the prime, Crenshaw/LAX Project design-builder. A new "catch-all contract" will be issued for bid to handle the remaining miscellaneous items that are required to be constructed separate from the design-build contract and may potentially be used for other projects as well.
Background
BACKGROUND
The Crenshaw/LAX Transit Project is a north/south light rail line that serves the cities of Los Angeles, Inglewood, Hawthorne and El Segundo as well as portions of unincorporated Los Angeles County. The alignment extends 8.5 miles, from the intersection of Crenshaw and Exposition Boulevards to a connection with the Metro Green Line south of the Aviation/LAX Station. The project provides major connections with the Los Angeles International Airport (LAX) as well as links to the C Line (Green), the E Line (Expo) and countywide bus network.
The alignment is comprised of a double-tracked rail line consisting of sections of at-grade in-street, at-grade within railroad right-of-way, aerial, and below-grade guideway sections, eight stations, park and ride facilities at two locations, utilities, landscaping, roadway improve...
Click here for full text