File #: 2020-0311   
Type: Contract Status: Passed
File created: 4/21/2020 In control: Construction Committee
On agenda: 6/18/2020 Final action: 6/25/2020
Title: AUTHORIZE Contract Modification No. 280 (CCO 280) by the California Department of Transportation (Caltrans) for the construction contract for Segment 3 (Empire) of I-5 North Capacity Enhancements Project between SR-134 and SR-118 (Project) in the amount $631,246.57 under Funding Agreement No. MOU.P0008355/8501A/A9 within the current LOP budget.
Sponsors: Construction Committee
Indexes: Bids, Budget, Budgeting, Construction, Contract administration, Contractors, Contracts, High occupancy vehicle lanes, I-5, I-5 N Hov Lanes Sr-134 To Sr-118 - Segment 2 (Sr-170 To Buena Vista) (Project), I-5 N Hov Lanes Sr-134 To Sr-118 - Segment 3 (Buena Vista To Magnolia) (Project), I-5 N Hov Lanes Sr-134 To Sr-118 - Segment 4 (Magnolia To Sr-134) (Project), I-5 North Corridor, I-5 North County Capacity Enhancements, Measure R, Payment, Project, Proposition C, Regional Surface Transportation Program, Southern California Highways, SR-118, SR-134, Subsidies
Related files: 2020-0447
Meeting_Body
CONSTRUCTION COMMITTEE
JUNE 18, 2020

Subject
SUBJECT: I-5 NORTH CAPACITY ENHANCEMENTS FROM SR- 118
TO SR-134; SEGMENT 3

Action
ACTION: APPROVE RECOMMENDATION

Heading
RECOMMENDATION

Title
AUTHORIZE Contract Modification No. 280 (CCO 280) by the California Department of Transportation (Caltrans) for the construction contract for Segment 3 (Empire) of I-5 North Capacity Enhancements Project between SR-134 and SR-118 (Project) in the amount $631,246.57 under Funding Agreement No. MOU.P0008355/8501A/A9 within the current LOP budget.

Issue
ISSUE

The construction contract for Segment 3 between West Magnolia Boulevard Overcrossing and 0.3 miles north of Buena Vista Street/Winona Avenue Undercrossing was awarded on November 29, 2012 with the scheduled completion date of September 27, 2017.

"Furnishing the RE's office and equipment" (Item) was a contract bid item with a lump sum payment of $742,000 in the original contract. Under this item, the contractor was responsible for furnishing and maintaining the RE office, equipment and supplies, and utilities. The project is now scheduled to open to traffic by December 2021 - 50 months beyond the original scheduled opening date - due to the delays resulting from relocation of utilities and other related work not accounted for in design, different site conditions, hazardous material encountered, additional work demanded by the affected communities, and design changes.

On October 1, 2019, the contractor filed a claim for $631,246.57 for the escalated cost of work related to furnishing Resident Engineer's (RE's) office to maintain office and equipment until December 24, 2021. Caltrans has conducted a force account analysis for the claim and has approved the amount presented in this report.

CCO 280 authorizes $631,246.57 to compensate the contractor for the Item until December 24, 2021. Contract modifications exceeding $500,000 require Board authorization.