AUTHORIZE the Chief Executive Officer to:
ESTABLISH the A650 Speed Code Cards capital project with a Life-of-Project (LOP) budget in the amount of $2,200,000;
FIND that the purchase and installation of A650 Speed Code Cards under Public Utilities Code (PUC) Section 130237 constitutes a single source procurement method for the purpose of replacing equipment already in use; and
AWARD a Sole Source five-month, firm-fixed price, Contract No. OP298873000, to QuEST Rail, LLC (QuEST) in the Not-To-Exceed (NTE) amount of $1,499,850 for the purchase and installation of Speed Code Cards to the A650 fleet comprised of 98 cars, subject to the resolution of any properly submitted protest(s), if any.
(REQUIRES TWO-THIRDS VOTE OF THE FULL BOARD)
Issue
ISSUE
Updates to the Metro Rail Design Criteria (MRDC) Section 9 Revision 16 (revised November 2017) added two additional speed codes (15 mph and 20 mph) to the operating definitions of the audio frequency cab signaling system for Metro’s B and D Lines. The new HR4000 vehicles can support and detect these new speed codes and are able to operate on the new PLE-1 segment where these speed codes were first implemented. However, Metro's legacy fleet of A650 vehicles can’t detect these new speed codes at rail crossovers and must be retrofitted with the speed code cards, in order to operate on tracks where the new speed codes have been implemented (PLE-1) and are in the process of being implemented (PLE-2, PLE-3, and Division 20 Yard). Metro requires the A650 vehicles to be retrofitted as soon as possible to not delay pre-revenue testing for the new PLE alignment expansion.
Staff determined that the most appropriate and effective approach to resolve the compatibility issue is to procure the required services through a sole sourc...