Meeting_Body
REVISED
PLANNING AND PROGRAMMING COMMITTEE
MAY 16, 2018
Subject
SUBJECT: LA RIVER BIKE PATH GAP CLOSURE PROJECT
TECHNICAL SERVICES
Action
ACTION: APPROVE RECOMMENDATIONS
Heading
RECOMMENDATION
Title
AUTHORIZE the Chief Executive Officer (CEO) to:
A. AWARD AND EXECUTE an 88-month, firm fixed price Contract No. AE47795000 with CH2M Hill, Inc. for $45,891,279 for Los Angeles River Bike Path Gap Closure Project Technical Services (Project), subject to resolution of protest(s), if any;
B. APPROVE Contract Modification Authority (CMA) specific to and execute modifications for Contract No. AE47795000 in the amount of $6,883,692 (15%) to support the cost of unforeseen issues that may arise during the course of the Contract; and
C. NEGOTIATE and enter into a Memorandum of Understanding (MOU) with Los Angeles County Department of Public Works (LACDPW) for construction management and delivery of the Project with an option for final design; and
D. NEGOTIATE and enter into a Cooperative Agreement with the City of Los Angeles, the City of Vernon, and LACDPW.
Issue
ISSUE
In response to the June 2014 Board motion (Attachment C), the Los Angeles River Bike Path Gap Closure Feasibility Study was completed and presented to the Metro Board in 2016. The Study found that the Project is feasible and would help serve the transportation needs of communities neighboring the Project Area (Attachment D) as well as provide a regionally significant active transportation corridor.
To deliver the Project and create a continuous 32-mile grade-separated Class I bikeway, staff recommends awarding Contract No. AE47795000 with CH2M Hill, Inc. for $45,891,279. Because unforeseen circumstances may arise as the project develops, but are not known at this conceptual stage, staff recommends 15% CMA. Executing an MOU with LACDPW will allow Metro to define final project delivery responsibilities as Metro advances the project through environmental clearance and design.
...