File #: 2018-0485   
Type: Contract Status: Agenda Ready
File created: 7/24/2018 In control: Operations, Safety, and Customer Experience Committee
On agenda: 11/15/2018 Final action:
Title: APPROVE a Modification to Contract No. P3010 with Kinkisharyo International, LLC for Request for Change (RFC) No. 28, Crenshaw Final Cutover Automatic Train Control (ATC) Software Release, for a firm fixed price of $2,350,680 increasing the total Contract value from $921,755,722 to $924,106,402. The contract increase is within the Life of Project Budget.
Sponsors: Operations, Safety, and Customer Experience Commit
Indexes: Active Transportation Program, Airport Metro Connector (AMC) Station Project, Budgeting, Contracts, Crenshaw District, Crenshaw/LAX Transit Corridor Project, Equipment Procurement (Project), Inglewood, Light rail vehicles, Long range planning, Long Range Transportation Plan, Los Angeles International Airport, Metro Crenshaw Line, Metro Exposition Line, Metro Green Line, Metro Rail C Line, Metro Rail E Line, Metro Rail K Line, Procurement, Project, Safety, Strategic planning, Suppliers, Westchester
Attachments: 1. Attachment A - Procurement Summary, 2. Attachment B - Contract Modification Authority Summary, 3. Attachment C - DEOD Summary
Related files: 2018-0784
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.
Meeting_Body
OPERATIONS, SAFETY AND CUSTOMER EXPERIENCE COMMITTEE
NOVEMBER 15, 2018

Subject
SUBJECT: P3010 LIGHT RAIL VEHICLE PROCUREMENT

Action
ACTION: APPROVE CHANGE ORDER

Heading
RECOMMENDATION

Title
APPROVE a Modification to Contract No. P3010 with Kinkisharyo International, LLC for Request for Change (RFC) No. 28, Crenshaw Final Cutover Automatic Train Control (ATC) Software Release, for a firm fixed price of $2,350,680 increasing the total Contract value from $921,755,722 to $924,106,402. The contract increase is within the Life of Project Budget.

Issue
ISSUE

P3010 Light Rail Vehicles (LRV's) are intended to support service on all Metro's light rail lines, including the Crenshaw/LAX Line. In 2013, when the P3010 design was being finalized, the Crenshaw design was still in development.

For the P3010 vehicles to support service on the new Line it is necessary for the ATC and the Automatic Train Protection (ATP) systems to be upgraded and qualified for compatibility with the Crenshaw/LAX wayside system to ensure safe and reliable operation.

As the RFC amount exceeds Metro's Chief Executive Officer's delegated negotiating authority of $1,000,000, staff is requesting Board approval for the contract change.

Background
BACKGROUND

In April 2012, Kinkisharyo International, LLC was awarded the P3010 LRV contract for a base order of 78 LRVs. Four options, for an additional 157 LRVs, were subsequently exercised, for a total of 235 vehicles to be delivered. In accordance with Metro's Long Range Transportation Plan, the P3010 LRVs are intended to support service on all Metro's light rail lines, including the Crenshaw/LAX Line.



Discussion
DISCUSSION

P3010 vehicles are currently not compatible with the wayside signaling system being implemented on the Crenshaw/LAX Line. In 2013, when the P3010 design was being finalized, information was not available to ensure compatibility of the P3010 LRVs with the Crenshaw/LAX Line as the Crenshaw design ...

Click here for full text