Subject
SUBJECT: NORTH SAN FERNANDO VALLEY BUS RAPID TRANSIT IMPROVEMENTS
Action
ACTION: APPROVE RECOMMENDATIONS
Heading
RECOMMENDATION
Title
CONSIDER:
A. RECEIVING AND FILING the North San Fernando Valley BRT Corridor Alternatives Analysis Study Report; and
B. AUTHORIZING the CEO to initiate the Environmental Study based on the recommended project with design variations.
Issue
ISSUE
The North San Fernando Valley (SFV) Bus Rapid Transit (BRT) Improvements Project is a Measure M project, with a projected opening date between FY 2023 and FY 2025. Currently $180 million in Measure M funds is allocated for this project. This project is also included in the Twenty-Eight by '28 Initiative adopted by the Board in January 2018.
To meet the Measure M schedule, a Proposed Project for the corridor needs to be identified and environmentally cleared through an Alternative Analysis (AA) and environmental review study, respectively. This report includes the findings from the initial AA Phase and a recommendation for what to advance into environmental review.
Figure 1 shows where we are in the Project Development Process. Within the Planning Process, specifically, the project has completed the Alternatives Analysis and with this Board action would begin the Initial Study and Draft Environmental Clearance document. Final Environmental Clearance is the last step of the planning process.
Figure 1: Project Development Process - Current Status
Background
BACKGROUND
Metro is building an extensive transit network to connect the San Fernando Valley to the greater Los Angeles Region. The North SFV BRT project will close a significant gap in Metro's current transit network in the San Fernando Valley. The addition of a high-capacity, east-west transit service to provide access will enable people to spend less time traveling between key activity centers, including California State University...