Meeting_Body
AD HOC CONGESTION, HIGHWAY AND ROADS COMMITTEE
OCTOBER 18, 2017
Subject
SUBJECT: MEASURE R HIGHWAY SUBREGIONAL PROGRAM
SEMI-ANNUAL UPDATE
Action
ACTION: APPROVE ADOPTION OF UPDATED SUBREGIONAL PROJECT LIST
Heading
RECOMMENDATION
Title
CONSIDER:
A. APPROVING $30.261 million of additional programming within the capacity of the Measure R Highway Subregional Programs and funding changes via the updated project list, as shown in Attachment A;
* Highway Operational Improvements in Arroyo Verdugo
* Highway Operational Improvements in Las Virgenes Malibu
* I-405, I-110, I-105 and SR-91 Ramp and Interchange Imp. (South Bay)
* I-605 Corridor "Hot Spots" Interchange Imp. in Gateway Cities
* I-710 South and/or Early Action Projects in Gateway Cities
B. APPROVING time extensions for 7 projects as shown in Attachment B; and
C. AUTHORIZING the CEO or his designee to negotiate and execute all necessary agreements for approved projects.
Issue
ISSUE
The Measure R Highway Subregional Program update allows the Highway Program and each subregion or lead agency to revise delivery priorities and amend project budgets for the implementation of the Measure R Highway subregional projects. The attached updated project lists include projects which have already received prior Board approval, as well as proposed changes related to schedules, scope, funding allocation and the addition or removal of projects. The Board's approval is required as the updated project lists serve as the basis for Metro to enter into agreements with the respective implementing agencies.
Discussion
DISCUSSION
The Measure R Expenditure Plan included the following Highway Capital Project Subfunds:
* Highway Operational Improvements in Arroyo Verdugo
* Highway Operational Improvements in Las Virgenes Malibu
* I-405, I-110, I-105 and SR-91 Ramp and Interchange Imp. (South Bay)
* I-605 Corridor "Hot Spots" Interchange Imp. in Gateway Cities
* I-710 South and/or Early Action ...
Click here for full text